Home
Class 14
MATHS
C is twice efficient as A. B takes thric...

C is twice efficient as A. B takes thrice as many days as C. A takes 12 days to finish the work alone. If they work in pairs (ie, AB, BC, CA) starting with AB on the first day then BC on the second day and AC on the third day and so on, then how many days are required to finish the work?

A

`6 1/5` days

B

4.5 days

C

`5 1/9` days

D

8 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, let's break down the information given and calculate the required work completion time. ### Step 1: Determine the efficiencies of A, B, and C 1. **Efficiency of A**: A takes 12 days to complete the work alone. Therefore, A's efficiency is: \[ \text{Efficiency of A} = \frac{1 \text{ work}}{12 \text{ days}} = \frac{1}{12} \text{ work/day} \] 2. **Efficiency of C**: C is twice as efficient as A. Therefore, C's efficiency is: \[ \text{Efficiency of C} = 2 \times \text{Efficiency of A} = 2 \times \frac{1}{12} = \frac{1}{6} \text{ work/day} \] 3. **Efficiency of B**: B takes thrice as many days as C. Since C takes 6 days to complete the work alone, B takes: \[ \text{Days taken by B} = 3 \times 6 = 18 \text{ days} \] Thus, B's efficiency is: \[ \text{Efficiency of B} = \frac{1 \text{ work}}{18 \text{ days}} = \frac{1}{18} \text{ work/day} \] ### Step 2: Calculate the total work The total work can be calculated using A's efficiency: \[ \text{Total Work} = \text{Efficiency of A} \times \text{Days taken by A} = \frac{1}{12} \times 12 = 1 \text{ work unit} \] ### Step 3: Calculate the work done in pairs 1. **Day 1 (A and B)**: \[ \text{Work done} = \text{Efficiency of A} + \text{Efficiency of B} = \frac{1}{12} + \frac{1}{18} \] To add these fractions, find a common denominator (36): \[ = \frac{3}{36} + \frac{2}{36} = \frac{5}{36} \text{ work units} \] 2. **Day 2 (B and C)**: \[ \text{Work done} = \text{Efficiency of B} + \text{Efficiency of C} = \frac{1}{18} + \frac{1}{6} \] Common denominator (18): \[ = \frac{1}{18} + \frac{3}{18} = \frac{4}{18} = \frac{2}{9} \text{ work units} \] 3. **Day 3 (C and A)**: \[ \text{Work done} = \text{Efficiency of C} + \text{Efficiency of A} = \frac{1}{6} + \frac{1}{12} \] Common denominator (12): \[ = \frac{2}{12} + \frac{1}{12} = \frac{3}{12} = \frac{1}{4} \text{ work units} \] ### Step 4: Total work done in three days Now, let's calculate the total work done in three days: \[ \text{Total work in 3 days} = \frac{5}{36} + \frac{2}{9} + \frac{1}{4} \] Finding a common denominator (36): \[ = \frac{5}{36} + \frac{8}{36} + \frac{9}{36} = \frac{22}{36} = \frac{11}{18} \text{ work units} \] ### Step 5: Calculate remaining work and days needed After 3 days, the remaining work is: \[ \text{Remaining work} = 1 - \frac{11}{18} = \frac{7}{18} \text{ work units} \] ### Step 6: Work done in the next cycles 1. **Day 4 (A and B)**: \[ \text{Work done} = \frac{5}{36} \] Remaining work after Day 4: \[ \frac{7}{18} - \frac{5}{36} = \frac{14}{36} - \frac{5}{36} = \frac{9}{36} = \frac{1}{4} \] 2. **Day 5 (B and C)**: \[ \text{Work done} = \frac{2}{9} \] Remaining work after Day 5: \[ \frac{1}{4} - \frac{2}{9} = \frac{9}{36} - \frac{8}{36} = \frac{1}{36} \] 3. **Day 6 (C and A)**: \[ \text{Work done} = \frac{1}{4} \] On Day 6, they will complete the remaining work of \(\frac{1}{36}\). ### Final Calculation of Total Days Total days taken: - 5 full days + a fraction of the 6th day. Thus, the total time taken to complete the work is: \[ \text{Total Days} = 6 \text{ days} \] ### Final Answer The total number of days required to finish the work is **6 days**.
Promotional Banner

Topper's Solved these Questions

  • THEORY OF EQUATIONS

    QUANTUM CAT|Exercise QUESTION BANK|573 Videos
  • TIME, SPEED AND DISTANCE

    QUANTUM CAT|Exercise QUESTION BANK|368 Videos

Similar Questions

Explore conceptually related problems

A is thrice efficient as B and A-takes 20 days to do a job, then in how many days B can finish the same job?

A is thrice as efficient as B. If B takes 8 days more than A, what is the number of days taken by A to finish the whole work, alone?

A is twice as good a workman as B and together they finish a piece of work in 14 days. In how many days can A alone finish the work?

QUANTUM CAT-TIME AND WORK-QUESTION BANK
  1. 33 men can do a job in 30 days. If 44 men started the job together and...

    Text Solution

    |

  2. Abhishek can do a piece of work in 40 days. He alone worked at it for ...

    Text Solution

    |

  3. C is twice efficient as A. B takes thrice as many days as C. A takes 1...

    Text Solution

    |

  4. Ahluwalia and Bimal together take 6 days to finish the work.'Bimal and...

    Text Solution

    |

  5. B is twice efficient as A and A can do a piece of work in 15 days. A s...

    Text Solution

    |

  6. A, B and C can complete a piece of-work in 15, 30 and 40 days respecti...

    Text Solution

    |

  7. There was a leakage in the container of the refined oil. If 11 kg oil ...

    Text Solution

    |

  8. A contractor undertook to complete the work in 40 days and he deployed...

    Text Solution

    |

  9. 7 Indian and 4 Chinese finish a job in 5 days. 7 Japanese and 3 Chines...

    Text Solution

    |

  10. A, B and C are three book binders. A takes 8 .minutes, B takes 12 minu...

    Text Solution

    |

  11. A piece of work can be completed by 10 men and 6 women in 18 days. Men...

    Text Solution

    |

  12. B and C are equally efficient, but the efficiency of-A is half of each...

    Text Solution

    |

  13. A can do a piece of work in 10 days, B in 15 days. They work together ...

    Text Solution

    |

  14. A can do a piece of work in 2 hours, B can do thrice the work in 8 hou...

    Text Solution

    |

  15. A is twice efficient as B and together they do the same work, in as mu...

    Text Solution

    |

  16. 4 men and 2 boys can finish a piece of work in 5 days. 3 women and 4 b...

    Text Solution

    |

  17. If m men can do a work in r days, then the number of days taken by (m+...

    Text Solution

    |

  18. Pipe A can fill a tank in 36 minutes and pipe B can fill it in 45 minu...

    Text Solution

    |

  19. Tap A can fill the empty tank in 12 hours, but due to a leak in the bo...

    Text Solution

    |

  20. Pipe A and B can fill a cistern in 10 hours and 15 hours respectively....

    Text Solution

    |