Home
Class 14
MATHS
Ahluwalia and Bimal together take 6 days...

Ahluwalia and Bimal together take 6 days to finish the work.'Bimal and Jalan together take 10. days to finish the Work What is the difference between number of day taken by Ahluwalia and Jalan when :they worked, alone to complete the whole work?

A

12 days

B

16 days

C

15 days

D

can’t be determined

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem, we need to determine the individual work rates of Ahluwalia, Bimal, and Jalan. Let's denote: - A = number of days taken by Ahluwalia to complete the work alone. - B = number of days taken by Bimal to complete the work alone. - J = number of days taken by Jalan to complete the work alone. ### Step 1: Establish the equations based on the given information. 1. **Ahluwalia and Bimal together take 6 days to finish the work.** This means their combined work rate is: \[ \frac{1}{A} + \frac{1}{B} = \frac{1}{6} \] 2. **Bimal and Jalan together take 10 days to finish the work.** This means their combined work rate is: \[ \frac{1}{B} + \frac{1}{J} = \frac{1}{10} \] ### Step 2: Rearranging the equations. From the first equation, we can express it as: \[ \frac{1}{A} = \frac{1}{6} - \frac{1}{B} \quad \text{(1)} \] From the second equation, we can express it as: \[ \frac{1}{J} = \frac{1}{10} - \frac{1}{B} \quad \text{(2)} \] ### Step 3: Solve for B in terms of A and J. From equation (1): \[ \frac{1}{B} = \frac{1}{6} - \frac{1}{A} \] From equation (2): \[ \frac{1}{B} = \frac{1}{10} - \frac{1}{J} \] ### Step 4: Set the two expressions for \(\frac{1}{B}\) equal to each other. \[ \frac{1}{6} - \frac{1}{A} = \frac{1}{10} - \frac{1}{J} \] ### Step 5: Cross-multiply to eliminate the fractions. Cross-multiplying gives us: \[ \left(\frac{1}{6} - \frac{1}{10}\right) = \left(\frac{1}{A} - \frac{1}{J}\right) \] Calculating \(\frac{1}{6} - \frac{1}{10}\): \[ \frac{5 - 3}{30} = \frac{2}{30} = \frac{1}{15} \] So we have: \[ \frac{1}{A} - \frac{1}{J} = \frac{1}{15} \] ### Step 6: Rearranging gives us the difference in days. This can be expressed as: \[ \frac{1}{A} = \frac{1}{J} + \frac{1}{15} \] Taking the reciprocal gives: \[ A = \frac{15J}{J + 15} \] ### Step 7: Find the difference between A and J. To find the difference \( |A - J| \): \[ |A - J| = \left| \frac{15J}{J + 15} - J \right| \] \[ = \left| \frac{15J - J(J + 15)}{J + 15} \right| \] \[ = \left| \frac{15J - J^2 - 15J}{J + 15} \right| \] \[ = \left| \frac{-J^2}{J + 15} \right| \] ### Conclusion The difference between the number of days taken by Ahluwalia and Jalan to complete the work alone cannot be determined without additional information about their individual efficiencies.
Promotional Banner

Topper's Solved these Questions

  • THEORY OF EQUATIONS

    QUANTUM CAT|Exercise QUESTION BANK|573 Videos
  • TIME, SPEED AND DISTANCE

    QUANTUM CAT|Exercise QUESTION BANK|368 Videos

Similar Questions

Explore conceptually related problems

A is thrice as efficient as B. If B takes 8 days more than A, what is the number of days taken by A to finish the whole work, alone?

A is twice as good as B and together they finish a piece of work in 16 days. The number of days taken by A alone to finish the work is

P is twice as good as Q and together they finish a piece of work in 36 days. The number of days taken by P alone to finish the work?

A and B together can do a piece of work in 12 days, while B alone can finish it in 30 days. A alone can finish the work in

A takes 4 days more to finish certain piece of work than that of B. If working together they can finish the work in 8(8)/(9) days. Then in how many days working alone each can finish the work?

QUANTUM CAT-TIME AND WORK-QUESTION BANK
  1. Abhishek can do a piece of work in 40 days. He alone worked at it for ...

    Text Solution

    |

  2. C is twice efficient as A. B takes thrice as many days as C. A takes 1...

    Text Solution

    |

  3. Ahluwalia and Bimal together take 6 days to finish the work.'Bimal and...

    Text Solution

    |

  4. B is twice efficient as A and A can do a piece of work in 15 days. A s...

    Text Solution

    |

  5. A, B and C can complete a piece of-work in 15, 30 and 40 days respecti...

    Text Solution

    |

  6. There was a leakage in the container of the refined oil. If 11 kg oil ...

    Text Solution

    |

  7. A contractor undertook to complete the work in 40 days and he deployed...

    Text Solution

    |

  8. 7 Indian and 4 Chinese finish a job in 5 days. 7 Japanese and 3 Chines...

    Text Solution

    |

  9. A, B and C are three book binders. A takes 8 .minutes, B takes 12 minu...

    Text Solution

    |

  10. A piece of work can be completed by 10 men and 6 women in 18 days. Men...

    Text Solution

    |

  11. B and C are equally efficient, but the efficiency of-A is half of each...

    Text Solution

    |

  12. A can do a piece of work in 10 days, B in 15 days. They work together ...

    Text Solution

    |

  13. A can do a piece of work in 2 hours, B can do thrice the work in 8 hou...

    Text Solution

    |

  14. A is twice efficient as B and together they do the same work, in as mu...

    Text Solution

    |

  15. 4 men and 2 boys can finish a piece of work in 5 days. 3 women and 4 b...

    Text Solution

    |

  16. If m men can do a work in r days, then the number of days taken by (m+...

    Text Solution

    |

  17. Pipe A can fill a tank in 36 minutes and pipe B can fill it in 45 minu...

    Text Solution

    |

  18. Tap A can fill the empty tank in 12 hours, but due to a leak in the bo...

    Text Solution

    |

  19. Pipe A and B can fill a cistern in 10 hours and 15 hours respectively....

    Text Solution

    |

  20. A cistern has a leak which would empty it in 6 hours. A tap is turned ...

    Text Solution

    |