Home
Class 14
MATHS
A, B and C can complete a piece of-work ...

A, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?

A

`7 3/10`

B

`10 2/15`

C

`10 7/30`

D

none of these

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will first determine the work done by A, B, and C, and then calculate how long it took to complete the work given the conditions. ### Step 1: Determine the work rates of A, B, and C - A can complete the work in 15 days, so A's work rate is \( \frac{1}{15} \) of the work per day. - B can complete the work in 30 days, so B's work rate is \( \frac{1}{30} \) of the work per day. - C can complete the work in 40 days, so C's work rate is \( \frac{1}{40} \) of the work per day. ### Step 2: Find the combined work rate of A, B, and C To find the combined work rate, we need to find a common denominator for their work rates: - The LCM of 15, 30, and 40 is 120. - A's work rate in terms of units of work is \( \frac{120}{15} = 8 \) units per day. - B's work rate in terms of units of work is \( \frac{120}{30} = 4 \) units per day. - C's work rate in terms of units of work is \( \frac{120}{40} = 3 \) units per day. Thus, the combined work rate of A, B, and C is: \[ 8 + 4 + 3 = 15 \text{ units per day} \] ### Step 3: Determine the work done in the last days Let \( x \) be the total number of days taken to complete the work. According to the problem: - A left 2 days before completion, so A worked for \( x - 2 \) days. - B left 4 days before completion, so B worked for \( x - 4 \) days. - C worked for all \( x \) days. ### Step 4: Calculate the total work done The total work done can be expressed as: \[ \text{Work done by A} = 8(x - 2) \] \[ \text{Work done by B} = 4(x - 4) \] \[ \text{Work done by C} = 3x \] The total work done is equal to the total work (120 units): \[ 8(x - 2) + 4(x - 4) + 3x = 120 \] ### Step 5: Simplify the equation Expanding the equation: \[ 8x - 16 + 4x - 16 + 3x = 120 \] Combining like terms: \[ (8x + 4x + 3x) - 32 = 120 \] \[ 15x - 32 = 120 \] ### Step 6: Solve for \( x \) Adding 32 to both sides: \[ 15x = 152 \] Dividing by 15: \[ x = \frac{152}{15} \approx 10.13 \] ### Step 7: Determine the total days taken Since \( x \) must be a whole number, we round up to the nearest whole number, which gives us \( x = 11 \) days. ### Final Answer The total number of days taken to complete the work is **11 days**. ---
Promotional Banner

Topper's Solved these Questions

  • THEORY OF EQUATIONS

    QUANTUM CAT|Exercise QUESTION BANK|573 Videos
  • TIME, SPEED AND DISTANCE

    QUANTUM CAT|Exercise QUESTION BANK|368 Videos

Similar Questions

Explore conceptually related problems

A, B and C can complete a piec of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work in completed ?

A , B and C can do a piece of work in 24days,36 days and 108 days, respectively. They started the work together but A left 9 days after the start of the work and B left 3 days before the work was completed. For how many days did C work ?

A, B and C can do a piece of work in 36, 54 and 72 days respectively. They started the work but A left 8 days before the completion of the work while B left 12 days before the completion. The number of days for which C worked is a. 4 b. 8 c.12 d. 24

A,B and C can complete a work in 10,12 and 15 days respectively.They started the work together.But A left the work 5 days before its completion.B also left the work 2 days after A left.In how many days was the work completed? 4 b.15 c.7 d.8

A, B and C can complete a work in 16, 24 and 32 days, respectively. They started together but C left after 4 days of starting and A left 6 days before completion of the work. In how many days will the work be completed ?

QUANTUM CAT-TIME AND WORK-QUESTION BANK
  1. Ahluwalia and Bimal together take 6 days to finish the work.'Bimal and...

    Text Solution

    |

  2. B is twice efficient as A and A can do a piece of work in 15 days. A s...

    Text Solution

    |

  3. A, B and C can complete a piece of-work in 15, 30 and 40 days respecti...

    Text Solution

    |

  4. There was a leakage in the container of the refined oil. If 11 kg oil ...

    Text Solution

    |

  5. A contractor undertook to complete the work in 40 days and he deployed...

    Text Solution

    |

  6. 7 Indian and 4 Chinese finish a job in 5 days. 7 Japanese and 3 Chines...

    Text Solution

    |

  7. A, B and C are three book binders. A takes 8 .minutes, B takes 12 minu...

    Text Solution

    |

  8. A piece of work can be completed by 10 men and 6 women in 18 days. Men...

    Text Solution

    |

  9. B and C are equally efficient, but the efficiency of-A is half of each...

    Text Solution

    |

  10. A can do a piece of work in 10 days, B in 15 days. They work together ...

    Text Solution

    |

  11. A can do a piece of work in 2 hours, B can do thrice the work in 8 hou...

    Text Solution

    |

  12. A is twice efficient as B and together they do the same work, in as mu...

    Text Solution

    |

  13. 4 men and 2 boys can finish a piece of work in 5 days. 3 women and 4 b...

    Text Solution

    |

  14. If m men can do a work in r days, then the number of days taken by (m+...

    Text Solution

    |

  15. Pipe A can fill a tank in 36 minutes and pipe B can fill it in 45 minu...

    Text Solution

    |

  16. Tap A can fill the empty tank in 12 hours, but due to a leak in the bo...

    Text Solution

    |

  17. Pipe A and B can fill a cistern in 10 hours and 15 hours respectively....

    Text Solution

    |

  18. A cistern has a leak which would empty it in 6 hours. A tap is turned ...

    Text Solution

    |

  19. Tap a fills a tank in 10 hours and B can fill it in 15 hours. Both are...

    Text Solution

    |

  20. Tap A can fill a tank in 20 hours, B in 25 hours but tap C can J empty...

    Text Solution

    |