Home
Class 14
MATHS
A contractor undertook to complete the w...

A contractor undertook to complete the work in 40 days and he deployed 20 men for his work. 8 days before the scheduled time he realised that `1/2`th of the work was still to be done. How many more men were required.to complete the work in stipulated time?

A

60

B

80

C

20

D

25

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will follow the logic laid out in the video transcript. ### Step 1: Understand the total work and initial deployment The contractor has 40 days to complete the work with 20 men. **Hint:** Remember that the total work can be represented as a unit of work that needs to be completed. ### Step 2: Calculate the amount of work done in the initial period The contractor has been working for 32 days (40 days - 8 days remaining). In this time, he has completed half of the work. **Hint:** If half of the work is done in 32 days, then the remaining half must be completed in the remaining 8 days. ### Step 3: Determine the work left to be done Since half of the work is completed, there is still 1 unit of work left to be done in the remaining 8 days. **Hint:** Think about how much work needs to be done in the remaining time. ### Step 4: Calculate the work rate of the initial workforce The initial workforce of 20 men completed 1 unit of work in 32 days. Therefore, the work rate of 20 men can be calculated as follows: - Work done by 20 men in 32 days = 1 unit - Work done by 1 man in 32 days = 1/20 units - Work done by 1 man in 1 day = 1/(20 * 32) = 1/640 units **Hint:** Consider how many units of work one man can do in one day. ### Step 5: Determine the work rate needed to complete the remaining work To complete the remaining 1 unit of work in 8 days, we need to find out how many men (let's call this number X) are required: - Work required per day = 1 unit / 8 days = 1/8 units per day **Hint:** Set up an equation based on the work rate needed to complete the remaining work. ### Step 6: Set up the equation for the number of men required The work done by X men in one day should equal the required work per day: \[ X \times \frac{1}{640} = \frac{1}{8} \] To find X, multiply both sides by 640: \[ X = 640 \times \frac{1}{8} = 80 \] **Hint:** Make sure to isolate X to find the total number of men needed. ### Step 7: Calculate the additional men required The contractor initially had 20 men. Now he needs 80 men to complete the work on time. Therefore, the additional number of men required is: \[ 80 - 20 = 60 \] **Hint:** Subtract the initial number of men from the total number of men needed to find out how many more are required. ### Final Answer The contractor needs **60 more men** to complete the work in the stipulated time. ---
Promotional Banner

Topper's Solved these Questions

  • THEORY OF EQUATIONS

    QUANTUM CAT|Exercise QUESTION BANK|573 Videos
  • TIME, SPEED AND DISTANCE

    QUANTUM CAT|Exercise QUESTION BANK|368 Videos

Similar Questions

Explore conceptually related problems

A contractor undertook to complete the work in 40 days and he deployed 20 men for his work. 8 days before the scheduled time he realised that (1)/(3)rd of the work was still to be done. How many more men were required to complete the work in stipulated time?

10 men can make a wall in 8 days. How many men required to complete the same work in half day

A contractor undertakes to complete a work in 20 days. He employs 30 labourers on this job. How many more labourers would he employ to complete the work in 15 days?

Twelve men are required to complete a work in 24 days.How many men are required to complete twice the work in 16 days?

20 men can do a work in 35 days. How many men are needed to complete the same work in 25 days.

A contractor undertakes to complete a road 360 m long in 120 days and employs 30 men for the work. After 60 days he finds that only 120 m length of the road has been made. How many more men should he employ so that the work may be completed in time ?

QUANTUM CAT-TIME AND WORK-QUESTION BANK
  1. A, B and C can complete a piece of-work in 15, 30 and 40 days respecti...

    Text Solution

    |

  2. There was a leakage in the container of the refined oil. If 11 kg oil ...

    Text Solution

    |

  3. A contractor undertook to complete the work in 40 days and he deployed...

    Text Solution

    |

  4. 7 Indian and 4 Chinese finish a job in 5 days. 7 Japanese and 3 Chines...

    Text Solution

    |

  5. A, B and C are three book binders. A takes 8 .minutes, B takes 12 minu...

    Text Solution

    |

  6. A piece of work can be completed by 10 men and 6 women in 18 days. Men...

    Text Solution

    |

  7. B and C are equally efficient, but the efficiency of-A is half of each...

    Text Solution

    |

  8. A can do a piece of work in 10 days, B in 15 days. They work together ...

    Text Solution

    |

  9. A can do a piece of work in 2 hours, B can do thrice the work in 8 hou...

    Text Solution

    |

  10. A is twice efficient as B and together they do the same work, in as mu...

    Text Solution

    |

  11. 4 men and 2 boys can finish a piece of work in 5 days. 3 women and 4 b...

    Text Solution

    |

  12. If m men can do a work in r days, then the number of days taken by (m+...

    Text Solution

    |

  13. Pipe A can fill a tank in 36 minutes and pipe B can fill it in 45 minu...

    Text Solution

    |

  14. Tap A can fill the empty tank in 12 hours, but due to a leak in the bo...

    Text Solution

    |

  15. Pipe A and B can fill a cistern in 10 hours and 15 hours respectively....

    Text Solution

    |

  16. A cistern has a leak which would empty it in 6 hours. A tap is turned ...

    Text Solution

    |

  17. Tap a fills a tank in 10 hours and B can fill it in 15 hours. Both are...

    Text Solution

    |

  18. Tap A can fill a tank in 20 hours, B in 25 hours but tap C can J empty...

    Text Solution

    |

  19. if one pipe A can fill a tank in 20 minutes, then 5 pipes, each of 20%...

    Text Solution

    |

  20. Pipe A basically used as inlet pipe and pipe B is used as outlet pipe....

    Text Solution

    |