Home
Class 14
MATHS
Arun and Satyam can complete a work indi...

Arun and Satyam can complete a work individually in ,12 working days and 15 working days respectively with their full efficiencies. Arun does work only on Monday, Wednesday and Friday while Satyam does the work on Tuesday, Thursday and Saturday. Sunday is always off. But Arun and Satyam both works with half of their efficiencies on Friday and Saturday respectively. If Arun started the work on 1st January which falls on Monday followed by Satyam on the next day and so on (i.e., they work collectively in alternate days), then on which day work will be completed?

A

Tuesday

B

Wednesday

C

Thursday

D

Friday

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem, we need to determine how much work Arun and Satyam complete in a week and then find out when the total work will be completed. Let's break it down step by step. ### Step 1: Calculate the daily work efficiency of Arun and Satyam. - Arun can complete the work in 12 days. Therefore, his work efficiency is: \[ \text{Arun's efficiency} = \frac{1}{12} \text{ of the work per day} \] - Satyam can complete the work in 15 days. Therefore, his work efficiency is: \[ \text{Satyam's efficiency} = \frac{1}{15} \text{ of the work per day} \] ### Step 2: Determine their effective work on specific days. - Arun works on Monday, Wednesday, and Friday: - On Monday and Wednesday, he works at full efficiency: \[ \text{Work on Monday} = \frac{1}{12}, \quad \text{Work on Wednesday} = \frac{1}{12} \] - On Friday, he works at half efficiency: \[ \text{Work on Friday} = \frac{1}{2} \times \frac{1}{12} = \frac{1}{24} \] - Satyam works on Tuesday, Thursday, and Saturday: - On Tuesday and Thursday, he works at full efficiency: \[ \text{Work on Tuesday} = \frac{1}{15}, \quad \text{Work on Thursday} = \frac{1}{15} \] - On Saturday, he works at half efficiency: \[ \text{Work on Saturday} = \frac{1}{2} \times \frac{1}{15} = \frac{1}{30} \] ### Step 3: Calculate the total work done in one week. Now, let's sum up the work done in one complete week (Monday to Sunday): - Total work in one week: \[ \text{Total work} = \left(\frac{1}{12} + \frac{1}{15} + \frac{1}{12} + \frac{1}{15} + \frac{1}{24} + \frac{1}{30}\right) \] Calculating each term: - Convert to a common denominator (the least common multiple of 12, 15, 24, and 30 is 120): \[ \frac{1}{12} = \frac{10}{120}, \quad \frac{1}{15} = \frac{8}{120}, \quad \frac{1}{24} = \frac{5}{120}, \quad \frac{1}{30} = \frac{4}{120} \] Now substituting these values: \[ \text{Total work} = \left(\frac{10}{120} + \frac{8}{120} + \frac{10}{120} + \frac{8}{120} + \frac{5}{120} + \frac{4}{120}\right) = \frac{45}{120} = \frac{3}{8} \] ### Step 4: Determine how many weeks are needed to complete the work. Since the total work is 1 (whole work), we need to find out how many weeks it takes to complete the work: \[ \text{Weeks required} = \frac{1}{\frac{3}{8}} = \frac{8}{3} \text{ weeks} \approx 2.67 \text{ weeks} \] ### Step 5: Calculate the total days to complete the work. Since 2.67 weeks equals 2 weeks and 4 days (0.67 weeks is approximately 4 days), we can calculate the completion date: - 2 weeks from January 1st (Monday) is January 15th (Monday). - Adding 4 more days: - January 16th (Tuesday) - January 17th (Wednesday) - January 18th (Thursday) - January 19th (Friday) ### Conclusion The work will be completed on **Friday, January 19th**.
Promotional Banner

Topper's Solved these Questions

  • THEORY OF EQUATIONS

    QUANTUM CAT|Exercise QUESTION BANK|573 Videos
  • TIME, SPEED AND DISTANCE

    QUANTUM CAT|Exercise QUESTION BANK|368 Videos
QUANTUM CAT-TIME AND WORK-QUESTION BANK
  1. Pipe A can fill an empty tank in 30 hours while B can fill it in 45 ho...

    Text Solution

    |

  2. A, B and C three weavers have to supply an order of 100 shawls. A can ...

    Text Solution

    |

  3. Arun and Satyam can complete a work individually in ,12 working days a...

    Text Solution

    |

  4. A can do a work in 20 days, while B can do the same work in 25 days. T...

    Text Solution

    |

  5. A and B can complete the work individually in 24 days and 30 days resp...

    Text Solution

    |

  6. In the previous question,

    Text Solution

    |

  7. Working together B and C take 50% more number of days than A,B and C t...

    Text Solution

    |

  8. At Technosys Pvt Ltd. there are some engineering students employed as ...

    Text Solution

    |

  9. At Atharva Prakashan every book goes through 3 phases – typing, compos...

    Text Solution

    |

  10. If company has hired 12 more people, who can do any of the three jobs,...

    Text Solution

    |

  11. In the given pie-chart. what is the number of employees working in dep...

    Text Solution

    |

  12. Bunty and Babli working together completed a job in 8 days. If Bunty w...

    Text Solution

    |

  13. A single reservoir supplies the petrol to the whole city, while the re...

    Text Solution

    |

  14. Railneer is packaged in a water bottling plant, with die help of two m...

    Text Solution

    |

  15. A Contractor employed a certain number of workers to finish construct...

    Text Solution

    |

  16. Some-time after the new workers were introduced, all of the newly intr...

    Text Solution

    |

  17. 30 men can do a piece of work in 14 days. After how many days 10 men l...

    Text Solution

    |

  18. Mr. Stenley employed a tain number of typists for his project. 8 days ...

    Text Solution

    |

  19. Mr. Stenley employed a tain number of typists for his project. 8 days ...

    Text Solution

    |

  20. P can do a piece of work in 6 days and Q can complete the same work ...

    Text Solution

    |