A can do a work in 20 days, while B can ...

A can do a work in 20 days, while B can do the same work in 25 days. They started the work jointly. Few days later C also joined them and thus all of them completed the whole work in 10 days. All of them were paid total of rs 700. What is the share of C?
A किसी कार्य को 20 दिनों में कर सकता है जबकि B इसी कार्य को 25 दिनों में कर सकता है | उन्होंने एक साथ इस कार्य को शुरू किया | कुछ दिनों बाद C उनके साथ शामिल हो गया और इस प्रकार उन सभी ने इस पूरे कार्य को 10 दिनों में पूरा किया | उन सभी को कुल 700 रुपये का भुगतान किया गया |C का हिस्सा क्या है ?

A

₹ 130

B

₹ 185

C

₹ 70

D

can’t be determined

Text Solution

Verified by Experts

The correct Answer is:
C
Promotional Banner

Topper's Solved these Questions

  • THEORY OF EQUATIONS

    QUANTUM CAT|Exercise QUESTION BANK|573 Videos
  • TIME, SPEED AND DISTANCE

    QUANTUM CAT|Exercise QUESTION BANK|368 Videos
QUANTUM CAT-TIME AND WORK-QUESTION BANK
  1. A, B and C three weavers have to supply an order of 100 shawls. A can ...

    Text Solution

    |

  2. Arun and Satyam can complete a work individually in ,12 working days a...

    Text Solution

    |

  3. A can do a work in 20 days, while B can do the same work in 25 days. T...

    Text Solution

    |

  4. A and B can complete the work individually in 24 days and 30 days resp...

    Text Solution

    |

  5. In the previous question,

    Text Solution

    |

  6. Working together B and C take 50% more number of days than A,B and C t...

    Text Solution

    |

  7. At Technosys Pvt Ltd. there are some engineering students employed as ...

    Text Solution

    |

  8. At Atharva Prakashan every book goes through 3 phases – typing, compos...

    Text Solution

    |

  9. If company has hired 12 more people, who can do any of the three jobs,...

    Text Solution

    |

  10. In the given pie-chart. what is the number of employees working in dep...

    Text Solution

    |

  11. Bunty and Babli working together completed a job in 8 days. If Bunty w...

    Text Solution

    |

  12. A single reservoir supplies the petrol to the whole city, while the re...

    Text Solution

    |

  13. Railneer is packaged in a water bottling plant, with die help of two m...

    Text Solution

    |

  14. A Contractor employed a certain number of workers to finish construct...

    Text Solution

    |

  15. Some-time after the new workers were introduced, all of the newly intr...

    Text Solution

    |

  16. 30 men can do a piece of work in 14 days. After how many days 10 men l...

    Text Solution

    |

  17. Mr. Stenley employed a tain number of typists for his project. 8 days ...

    Text Solution

    |

  18. Mr. Stenley employed a tain number of typists for his project. 8 days ...

    Text Solution

    |

  19. P can do a piece of work in 6 days and Q can complete the same work ...

    Text Solution

    |

  20. 16 days after the 20% typist left the job it was decided to complete t...

    Text Solution

    |