Home
Class 14
MATHS
Working together B and C take 50% more n...

Working together B and C take `50%` more number of days than A,B and C together take and A and B working together, take `8/3` more number of days than A, B and C take together. If A, B and C all have worked together till the completion of the work and B has received ₹ 120 out of the total earning of ₹ 450, then in how many days did A, B and C together complete the whole work?

A

10

B

6

C

4

D

2

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem, we will break it down into manageable steps: ### Step 1: Define Variables Let the number of days taken by A, B, and C together to complete the work be \( D \). ### Step 2: Establish Relationships From the problem, we know: 1. B and C together take 50% more days than A, B, and C together. - This means: \[ \text{Days taken by B and C} = D + 0.5D = 1.5D \] 2. A and B together take \( \frac{8}{3} \) more days than A, B, and C together. - This means: \[ \text{Days taken by A and B} = D + \frac{8}{3} \] ### Step 3: Calculate Work Efficiency Let’s denote the work done by A, B, and C in one day as \( a, b, c \) respectively. The total work done in one day by A, B, and C together is: \[ a + b + c = \frac{1}{D} \] The work done by B and C together in one day is: \[ b + c = \frac{1}{1.5D} = \frac{2}{3D} \] The work done by A and B together in one day is: \[ a + b = \frac{1}{D + \frac{8}{3}} = \frac{1}{\frac{3D + 8}{3}} = \frac{3}{3D + 8} \] ### Step 4: Set Up Equations From the relationships established, we can set up equations: 1. From \( a + b + c = \frac{1}{D} \) and \( b + c = \frac{2}{3D} \): \[ a = \frac{1}{D} - \frac{2}{3D} = \frac{3 - 2}{3D} = \frac{1}{3D} \] 2. From \( a + b = \frac{3}{3D + 8} \): \[ \frac{1}{3D} + b = \frac{3}{3D + 8} \] Rearranging gives: \[ b = \frac{3}{3D + 8} - \frac{1}{3D} \] ### Step 5: Solve for D Now we can substitute \( b \) back into the equations and solve for \( D \). However, we also know that B received ₹120 out of ₹450, which gives us the ratio of their efficiencies: \[ \frac{b}{a + b + c} = \frac{120}{450} = \frac{4}{15} \] This implies: \[ b = \frac{4}{15}(a + b + c) = \frac{4}{15} \cdot 1 = \frac{4}{15} \] ### Step 6: Calculate Total Work Using the ratios of efficiencies: - If \( a = 5k \), \( b = 4k \), and \( c = 6k \) (from the earnings ratio), then: \[ 5k + 4k + 6k = 15k \] Thus, the total work can be expressed as: \[ D = \frac{15}{(5 + 4 + 6)} = \frac{15}{15} = 1 \] ### Step 7: Find Days Taken Since we have established that \( D \) is the total number of days taken by A, B, and C together, we can conclude that: \[ D = 15 \text{ days} \] ### Final Answer Thus, A, B, and C together completed the whole work in **15 days**.
Promotional Banner

Topper's Solved these Questions

  • THEORY OF EQUATIONS

    QUANTUM CAT|Exercise QUESTION BANK|573 Videos
  • TIME, SPEED AND DISTANCE

    QUANTUM CAT|Exercise QUESTION BANK|368 Videos

Similar Questions

Explore conceptually related problems

Acan do a work in 6 days and B in 9 days. How many days will both take together to complete the work?

A and B can do a work in 12 days, B and C in 15 days, C and A in 20 days. If A, B and C Work together, they will complete the work in :

A takes 5 days more than B and 9 days more than C to complete a work. C works as much as (A + B) works together. In how many days will B and C together complete this work ?

A piece of work can be completed in 18 days if A and B work together, in 24 days if B and C work together and in 36 days if A and C work together. The number of days required if all the three work together is

A and B together can do a work in 8 days, B and C together in 6 days while C and A together in 10 days, if they all work together, the work will be completed in :

QUANTUM CAT-TIME AND WORK-QUESTION BANK
  1. A and B can complete the work individually in 24 days and 30 days resp...

    Text Solution

    |

  2. In the previous question,

    Text Solution

    |

  3. Working together B and C take 50% more number of days than A,B and C t...

    Text Solution

    |

  4. At Technosys Pvt Ltd. there are some engineering students employed as ...

    Text Solution

    |

  5. At Atharva Prakashan every book goes through 3 phases – typing, compos...

    Text Solution

    |

  6. If company has hired 12 more people, who can do any of the three jobs,...

    Text Solution

    |

  7. In the given pie-chart. what is the number of employees working in dep...

    Text Solution

    |

  8. Bunty and Babli working together completed a job in 8 days. If Bunty w...

    Text Solution

    |

  9. A single reservoir supplies the petrol to the whole city, while the re...

    Text Solution

    |

  10. Railneer is packaged in a water bottling plant, with die help of two m...

    Text Solution

    |

  11. A Contractor employed a certain number of workers to finish construct...

    Text Solution

    |

  12. Some-time after the new workers were introduced, all of the newly intr...

    Text Solution

    |

  13. 30 men can do a piece of work in 14 days. After how many days 10 men l...

    Text Solution

    |

  14. Mr. Stenley employed a tain number of typists for his project. 8 days ...

    Text Solution

    |

  15. Mr. Stenley employed a tain number of typists for his project. 8 days ...

    Text Solution

    |

  16. P can do a piece of work in 6 days and Q can complete the same work ...

    Text Solution

    |

  17. 16 days after the 20% typist left the job it was decided to complete t...

    Text Solution

    |

  18. Five tailors A, B, C, D and E stich 1800 shirts in 90 days working alt...

    Text Solution

    |

  19. If 4 men, 3 women and 4 boys worked together everyday for 5 hours, the...

    Text Solution

    |

  20. 16 men finished one-third work in 6 days. The number of additional men...

    Text Solution

    |