Home
Class 14
MATHS
Some-time after the new workers were int...

Some-time after the new workers were introduced, all of the newly introduced workers left the work due to heavy rain and the efficiency of the remaining workers reduced by `20%` due to which the work finally got completed by delay of `60%` of the scheduled time then how much work still remained incomplete by the end of the scheduled time?

A

`17 3/5%`

B

`21%`

C

`27 5/7%`

D

`28%`

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will analyze the situation and calculate the amount of work that remains incomplete by the end of the scheduled time. ### Step 1: Define Variables Let: - \( M \) = number of original workers - \( X \) = number of newly introduced workers - \( T \) = scheduled time to complete the work ### Step 2: Calculate Total Work The total work done by all workers together in scheduled time \( T \) is: \[ \text{Total Work} = (M + X) \times T \] ### Step 3: Calculate Efficiency After New Workers Leave After the new workers leave, the efficiency of the remaining workers reduces by 20%. Therefore, the efficiency of the remaining workers becomes: \[ \text{Remaining Efficiency} = 80\% \text{ of } (M + X) = 0.8(M + X) \] ### Step 4: Calculate Delayed Time The work is completed with a delay of 60% of the scheduled time. Therefore, the actual time taken to complete the work is: \[ \text{Actual Time} = T + 0.6T = 1.6T \] ### Step 5: Calculate Work Done in Actual Time The work done by the remaining workers in the actual time is: \[ \text{Work Done} = \text{Remaining Efficiency} \times \text{Actual Time} = 0.8(M + X) \times 1.6T = 1.28(M + X)T \] ### Step 6: Set Up the Equation Now, we can set up the equation based on the total work and the work done: \[ 1.28(M + X)T = (M + X)T \] This indicates that the total work done in the actual time is less than the total work required. ### Step 7: Calculate Work Remaining The remaining work can be calculated as: \[ \text{Remaining Work} = \text{Total Work} - \text{Work Done} = (M + X)T - 1.28(M + X)T \] \[ = (1 - 1.28)(M + X)T = -0.28(M + X)T \] ### Step 8: Calculate Percentage of Incomplete Work To find out how much work remains incomplete by the end of the scheduled time, we can express this as a percentage of the total work: \[ \text{Percentage of Incomplete Work} = \left(\frac{-0.28(M + X)T}{(M + X)T}\right) \times 100 = -28\% \] ### Conclusion Since the negative percentage indicates that the work was not completed as planned, we can conclude that 28% of the work remains incomplete by the end of the scheduled time.
Promotional Banner

Topper's Solved these Questions

  • THEORY OF EQUATIONS

    QUANTUM CAT|Exercise QUESTION BANK|573 Videos
  • TIME, SPEED AND DISTANCE

    QUANTUM CAT|Exercise QUESTION BANK|368 Videos
QUANTUM CAT-TIME AND WORK-QUESTION BANK
  1. Railneer is packaged in a water bottling plant, with die help of two m...

    Text Solution

    |

  2. A Contractor employed a certain number of workers to finish construct...

    Text Solution

    |

  3. Some-time after the new workers were introduced, all of the newly intr...

    Text Solution

    |

  4. 30 men can do a piece of work in 14 days. After how many days 10 men l...

    Text Solution

    |

  5. Mr. Stenley employed a tain number of typists for his project. 8 days ...

    Text Solution

    |

  6. Mr. Stenley employed a tain number of typists for his project. 8 days ...

    Text Solution

    |

  7. P can do a piece of work in 6 days and Q can complete the same work ...

    Text Solution

    |

  8. 16 days after the 20% typist left the job it was decided to complete t...

    Text Solution

    |

  9. Five tailors A, B, C, D and E stich 1800 shirts in 90 days working alt...

    Text Solution

    |

  10. If 4 men, 3 women and 4 boys worked together everyday for 5 hours, the...

    Text Solution

    |

  11. 16 men finished one-third work in 6 days. The number of additional men...

    Text Solution

    |

  12. Eklavya can do the 6 times the actual work in 36 days while Faizal can...

    Text Solution

    |

  13. Progressive Company Pvt. Ltd. hired some employees in a fix pattern. O...

    Text Solution

    |

  14. Two persons having different productivity of labour, working together ...

    Text Solution

    |

  15. The total number of men, women and children working in a factory is 18...

    Text Solution

    |

  16. A group of workers was put on a job. From the second day onwards, one...

    Text Solution

    |

  17. Two workers undertake to do a job. The second-worker started working 2...

    Text Solution

    |

  18. A group of men deaded to do a job in 4 days. But since 20 men dropped ...

    Text Solution

    |

  19. Brahma, Vishnu and Mahesh are three friends with different productivit...

    Text Solution

    |

  20. Milinda takes 8 1/3 hours more when she works alone in comparison of w...

    Text Solution

    |