16 days after the 20% typist left the jo...

16 days after the `20%` typist left the job it was decided to complete the work on time by increasing the work-force again. By how much percentage increase in work-force is requried?

A

`100%`

B

`50%`

C

`200%`

D

none of these

Text Solution

Verified by Experts

The correct Answer is:
D
Promotional Banner

Topper's Solved these Questions

  • THEORY OF EQUATIONS

    QUANTUM CAT|Exercise QUESTION BANK|573 Videos
  • TIME, SPEED AND DISTANCE

    QUANTUM CAT|Exercise QUESTION BANK|368 Videos

Similar Questions

Explore conceptually related problems

If the radius of a circle is increased by 20% then by how much will its area be increased?

A contractor undertook a work to complete in 60 days. But just after 20 days he observed that only (1)/(5)th of the project work had been completed. To complete the work in time in rest days minimum how many workers he had to increase, if there were initially 75 workers were deployed for the task?

QUANTUM CAT-TIME AND WORK-QUESTION BANK
  1. Mr. Stenley employed a tain number of typists for his project. 8 days ...

    Text Solution

    |

  2. P can do a piece of work in 6 days and Q can complete the same work ...

    Text Solution

    |

  3. 16 days after the 20% typist left the job it was decided to complete t...

    Text Solution

    |

  4. Five tailors A, B, C, D and E stich 1800 shirts in 90 days working alt...

    Text Solution

    |

  5. If 4 men, 3 women and 4 boys worked together everyday for 5 hours, the...

    Text Solution

    |

  6. 16 men finished one-third work in 6 days. The number of additional men...

    Text Solution

    |

  7. Eklavya can do the 6 times the actual work in 36 days while Faizal can...

    Text Solution

    |

  8. Progressive Company Pvt. Ltd. hired some employees in a fix pattern. O...

    Text Solution

    |

  9. Two persons having different productivity of labour, working together ...

    Text Solution

    |

  10. The total number of men, women and children working in a factory is 18...

    Text Solution

    |

  11. A group of workers was put on a job. From the second day onwards, one...

    Text Solution

    |

  12. Two workers undertake to do a job. The second-worker started working 2...

    Text Solution

    |

  13. A group of men deaded to do a job in 4 days. But since 20 men dropped ...

    Text Solution

    |

  14. Brahma, Vishnu and Mahesh are three friends with different productivit...

    Text Solution

    |

  15. Milinda takes 8 1/3 hours more when she works alone in comparison of w...

    Text Solution

    |

  16. Pascal and Rascal are two workers. Working together they can complete ...

    Text Solution

    |

  17. Boston, Churchill and David are three workers, employed by a contracto...

    Text Solution

    |

  18. There are three boats B1, B2 and B3 working together they carry 60 peo...

    Text Solution

    |

  19. Three men and 5 women together can finish a job in 3 days. Working on ...

    Text Solution

    |

  20. Henry and Ford are two different persons, but when they work together,...

    Text Solution

    |