Home
Class 14
MATHS
A completes (2)/(3) of a certain job in ...

A completes `(2)/(3)` of a certain job in 6 days. B can complete `(1)/(3)` of the same job in 8 days and C can complete `(3)/(4)` of the work in 12 days. All of them work together for 4 days and then A and C quit. How long will it take for B to complete the remaining work alone?

A

3.8 days

B

3.33 days

C

2.22 days

D

4.3 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will first determine the work rates of A, B, and C, then calculate the total work done when they work together, and finally find out how long it takes for B to finish the remaining work alone. ### Step 1: Calculate the total time taken by A, B, and C to complete the entire job. 1. **A's work rate**: - A completes \( \frac{2}{3} \) of the job in 6 days. - Therefore, to complete the entire job, A would take: \[ \text{Total time for A} = 6 \times \frac{3}{2} = 9 \text{ days} \] 2. **B's work rate**: - B completes \( \frac{1}{3} \) of the job in 8 days. - Therefore, to complete the entire job, B would take: \[ \text{Total time for B} = 8 \times 3 = 24 \text{ days} \] 3. **C's work rate**: - C completes \( \frac{3}{4} \) of the job in 12 days. - Therefore, to complete the entire job, C would take: \[ \text{Total time for C} = 12 \times \frac{4}{3} = 16 \text{ days} \] ### Step 2: Calculate the work done by A, B, and C in one day. 1. **A's work per day**: \[ \text{A's work per day} = \frac{1}{9} \text{ of the job} \] 2. **B's work per day**: \[ \text{B's work per day} = \frac{1}{24} \text{ of the job} \] 3. **C's work per day**: \[ \text{C's work per day} = \frac{1}{16} \text{ of the job} \] ### Step 3: Calculate the total work done by A, B, and C together in 4 days. 1. **Combined work rate**: \[ \text{Combined work rate} = \text{A's work per day} + \text{B's work per day} + \text{C's work per day} \] \[ = \frac{1}{9} + \frac{1}{24} + \frac{1}{16} \] To add these fractions, find a common denominator. The least common multiple (LCM) of 9, 24, and 16 is 144. - Convert each fraction: \[ \frac{1}{9} = \frac{16}{144}, \quad \frac{1}{24} = \frac{6}{144}, \quad \frac{1}{16} = \frac{9}{144} \] - Now add them: \[ \text{Combined work rate} = \frac{16 + 6 + 9}{144} = \frac{31}{144} \] 2. **Work done in 4 days**: \[ \text{Work done in 4 days} = \text{Combined work rate} \times 4 = \frac{31}{144} \times 4 = \frac{124}{144} = \frac{31}{36} \text{ of the job} \] ### Step 4: Calculate the remaining work. 1. **Remaining work**: \[ \text{Remaining work} = 1 - \frac{31}{36} = \frac{5}{36} \text{ of the job} \] ### Step 5: Calculate how long it will take for B to complete the remaining work alone. 1. **B's work rate**: \[ \text{B's work per day} = \frac{1}{24} \text{ of the job} \] 2. **Time taken by B to complete the remaining work**: \[ \text{Time} = \frac{\text{Remaining work}}{\text{B's work per day}} = \frac{\frac{5}{36}}{\frac{1}{24}} = \frac{5}{36} \times 24 = \frac{120}{36} = \frac{10}{3} \text{ days} \approx 3.33 \text{ days} \] ### Final Answer: B will take approximately \( 3.33 \) days to complete the remaining work alone. ---
Promotional Banner

Topper's Solved these Questions

  • COORDINATE GEOMETRY

    ADVANCED MATHS BY ABHINAY MATHS ENGLISH|Exercise Questions|47 Videos
  • GEOMETRY

    ADVANCED MATHS BY ABHINAY MATHS ENGLISH|Exercise QUESTIONS|158 Videos

Similar Questions

Explore conceptually related problems

A can complete of a work in 8 days. B can complete 3/5 of the same work in 12 days and C can complete 4/9 of the same work in 8 days. A and B worked together for 5 days. How much time(in days) will C alone take to complete the remaining work?

A can do (3)/(5)th of a work in 12 days, B can do (1)/(3) rd of that work in 15 days. They worked together for 12 days and then A left the work , B alone will complete the remaining work in?

A and B can complete a job in 24 days working together. A alone can complete it in 32 days. Both of them worked together for 8 days and then A left. The number of days B will take to complete the remaining job is

A alone can complete a work in 12 days. A and B together can complete it in 8 days. How long will B alone take to complete the work?

A can do (2)/(5) of a work in 6 days and B can do (2)/(3) of the same work in 12 days. A and B worked together for 6 days. C alone completed the remaining work in 8 days. A and C, working together, will complete the same work in:

‘A’ completes a work in 12 days. ‘B’ completes the same work in 15 days. ‘A’ started working alone and after 3 days B joined him. How many days will they now take together to complete the remaining work?

If A can complete work in 6 days, B can complete the work in 8 days and C can complete the same work in 12 days. In how much time A, B, and C can complete the work.

ADVANCED MATHS BY ABHINAY MATHS ENGLISH-FREE MATHS LIVE MOCK 20-MULTIPLE CHOICE QUESTIONS
  1. a, b, c are the lengths of three sides of a DeltaABC. If a, b, c are r...

    Text Solution

    |

  2. The weight of three heaps of gold are in the ratio 5 : 6 : 7. By what ...

    Text Solution

    |

  3. A completes (2)/(3) of a certain job in 6 days. B can complete (1)/(3)...

    Text Solution

    |

  4. Two cars started simultaneously towards each other from town A and B t...

    Text Solution

    |

  5. A man bought an article and sold it at a gain of 5%. If he had bought ...

    Text Solution

    |

  6. In the given figure, AD is the bisector of angleBAC,AB=6cm,AC=5cm and ...

    Text Solution

    |

  7. In figure, if AB = a, calculate the area of triangle ADC (angleB=90^(@...

    Text Solution

    |

  8. If a+(1)/(a)+1=0,(ane0), then the value of (a^(5)-a^(2)) is

    Text Solution

    |

  9. If the radii of two circles be 8 cm and 4 cm and the length of the tra...

    Text Solution

    |

  10. If 2x = sqrt(a) - (1)/(sqrt(a)) , then the value of (sqrt(x^(2) + 1)...

    Text Solution

    |

  11. The difference between the time taken by two buses to travel a distanc...

    Text Solution

    |

  12. If a^(x)=b^(y)=c^(z) and abc=1, then find ((x^(2))/(x^(2)-zy)+(y^(2))/...

    Text Solution

    |

  13. In DeltaABC,AB=AC and AC=CD,angleB=80^(@) then angleADE=?

    Text Solution

    |

  14. If bc + ab + ca = abc, then the value of (b+c)/(bc(1-a))+(a+c)/(ac(1-b...

    Text Solution

    |

  15. Simplify (sintheta+sectheta)^(2)+(costheta+cosectheta)^(2).

    Text Solution

    |

  16. If (x+1)/(x-1)=a/b and (1-y)/(1+y)=b/a , then the value of (x-y)/(1...

    Text Solution

    |

  17. A reduction of Rs.1 per dozen in the price of eggs means that a dozen ...

    Text Solution

    |

  18. If cos e ctheta-sintheta=ma n dsectheta-costheta=n , prove that (m^(2n...

    Text Solution

    |

  19. A and B working together can finish a job in x days. If A works alone ...

    Text Solution

    |

  20. A circus tent is cylindrical upto a height of 3m and conical above it....

    Text Solution

    |