A can do a piece of work in 20 days and ...

A can do a piece of work in 20 days and B can do same work in 25 days. Both A and B start the work and after 8 days A left. In how many days will the total work be completed ?

Text Solution

Verified by Experts

The correct Answer is:
15 days
Promotional Banner

Topper's Solved these Questions

  • SIMPLE INTEREST

    ADVANCED MATHS BY ABHINAY MATHS ENGLISH|Exercise QUESTIONS|108 Videos
  • TIME, SPEED & DISTNACE

    ADVANCED MATHS BY ABHINAY MATHS ENGLISH|Exercise QUESTIONS|108 Videos

Similar Questions

Explore conceptually related problems

A can do a piece of work in 12 days and B can do same work in 18 days. Both A and B start the work and after some days A left and B complete the remaining work in 8 days. After how many days will A left work?

A can complete a work in 20 days & B can complete the same work in 25 days. If they start the work together but After 5 days A left the work . In how many days the total work would be finished ?

If A can do a piece of work in 4 days, B can do the same work in 8 days and C can do the same work in 12 days , then working together , how many days will they take to complete the work ?

A and B can do a piece of work in 20 days and 30 days respectively. A start the work and they do this work in alternate days. In how many days will this work be completed ?

A can do a work in 10 days and that of B in 15 days . B starts the work alone but after 3 days he left the work & A joined the work . In how many days will the total work be finished ?

A and B can do a piece of work in 8 days, B and C can do the same work in 12 days. If A, B and C can complete the same work in 6 days, in how many days can A and C complete the same work?

ADVANCED MATHS BY ABHINAY MATHS ENGLISH-TIME & WORK -QUESTIONS
  1. (A + B) can do a piece of work in 20 days and A can do same work in 60...

    Text Solution

    |

  2. A can do a piece of work in 10 days and B can do same work in 15 days....

    Text Solution

    |

  3. A can do a piece of work in 20 days and B can do same work in 25 days....

    Text Solution

    |

  4. A can do a piece of work in 12 days and B can do same work in 18 days....

    Text Solution

    |

  5. A can do a piece of work in 20 days and B can do same work in 15 days....

    Text Solution

    |

  6. (A + B) can do a piece of work in 10 days. A works 2(1)/(2) days and ...

    Text Solution

    |

  7. (A + B) can do a piece of work in 14 days. A works 3(1)/(2) days and...

    Text Solution

    |

  8. (A + B) can do a piece of work in 5 days. If A works with twice of his...

    Text Solution

    |

  9. (A + B) can do a piece of work in 5 days. If A works with twice of his...

    Text Solution

    |

  10. A can do a piece of work in 4 hours. (B + C) can do the same work in 3...

    Text Solution

    |

  11. A can make (1)/(3) part of a wall in 9 days and B can make (2)/(3) p...

    Text Solution

    |

  12. A can do (13)/(56) part of a work in 111 days and B can do (43)/(56) ...

    Text Solution

    |

  13. A can do (1)/(4) part of a work in 21 days and B can do (1)/(4) part...

    Text Solution

    |

  14. (A + B) can do a piece of work in 12 days. (B + C) can do same work in...

    Text Solution

    |

  15. (A + B) can do a piece of work in 12 days. (B + C) can do same work in...

    Text Solution

    |

  16. A work for 2 days, then B complete the remaining work in 9 days. If A ...

    Text Solution

    |

  17. A can do a piece of work in 80 days. A works for 10 days, then B compl...

    Text Solution

    |

  18. A and B can do a piece of work in 45 and 40 days respectively. They...

    Text Solution

    |

  19. A and B can do a piece of work in 20 days and 30 days respectively. A ...

    Text Solution

    |

  20. A and B can do a piece of work in 20 days and 25 days. A start the wor...

    Text Solution

    |