Home
Class 14
MATHS
(A + B) can do a piece of work in 5 days...

(A + B) can do a piece of work in 5 days. If A works with twice of his efficiency and B works with half of his efficiency, then work will be completed in 4 days. In how many days will A and B do this work alone ?

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will first define the efficiencies of A and B, then use the information given to find out how long each person would take to complete the work alone. ### Step 1: Define the efficiencies of A and B Let the efficiency of A be \( A \) units of work per day and the efficiency of B be \( B \) units of work per day. ### Step 2: Set up the equation based on the first condition According to the problem, A and B together can complete the work in 5 days. Therefore, the total work can be expressed as: \[ \text{Total Work} = (A + B) \times 5 \] ### Step 3: Set up the equation based on the second condition When A works with twice his efficiency and B works with half his efficiency, they complete the same work in 4 days. This can be expressed as: \[ \text{Total Work} = (2A + \frac{B}{2}) \times 4 \] ### Step 4: Equate the two expressions for total work Since both expressions represent the same total work, we can set them equal to each other: \[ (A + B) \times 5 = (2A + \frac{B}{2}) \times 4 \] ### Step 5: Simplify the equation Expanding both sides gives: \[ 5A + 5B = 8A + 2B \] Rearranging the equation leads to: \[ 5B - 2B = 8A - 5A \] This simplifies to: \[ 3B = 3A \] Thus, we find: \[ A = B \] ### Step 6: Substitute A in terms of B Let’s denote both A and B as \( K \) (since they are equal): \[ A = K \quad \text{and} \quad B = K \] ### Step 7: Find the total work in terms of K Substituting \( A \) and \( B \) back into the total work equation: \[ \text{Total Work} = (K + K) \times 5 = 10K \] ### Step 8: Calculate the time taken by A and B alone Now, substituting back into the equation for total work: \[ 10K = (2K + \frac{K}{2}) \times 4 \] Simplifying the right side: \[ 10K = (2K + 0.5K) \times 4 = (2.5K) \times 4 = 10K \] This confirms our calculations are consistent. ### Step 9: Calculate the time taken by A and B alone Since \( A \) and \( B \) both work at \( K \) units per day, the time taken by A alone to complete the work is: \[ \text{Time taken by A} = \frac{\text{Total Work}}{A} = \frac{10K}{K} = 10 \text{ days} \] Similarly, the time taken by B alone is: \[ \text{Time taken by B} = \frac{\text{Total Work}}{B} = \frac{10K}{K} = 10 \text{ days} \] ### Conclusion Thus, A will take 10 days to complete the work alone, and B will also take 10 days to complete the work alone. ---
Promotional Banner

Topper's Solved these Questions

  • SIMPLE INTEREST

    ADVANCED MATHS BY ABHINAY MATHS ENGLISH|Exercise QUESTIONS|108 Videos
  • TIME, SPEED & DISTNACE

    ADVANCED MATHS BY ABHINAY MATHS ENGLISH|Exercise QUESTIONS|108 Videos

Similar Questions

Explore conceptually related problems

(A + B) can do a piece of work in 5 days. If A works with twice of his efficiency and B works with (1)/(3) of his efficiency, then work will be completed in 3 days. In how many days will A do this work alone ?

A and B working together can finish certain piece of work in 10 days. If A works at (2)/(3) of his actual efficiency and B works at (5)/(3) of his actual efficiency, then work will be completed in 9 days. If A works at (1)/(2) of his actual efficiency and B works at double of his actual efficiency, then in how many days work will be finished?

(A + B) can do a piece of work in 14 days. A works 3(1)/(2) days and B works for 11(1)/(2) days, then half of the work has been completed. In how many days will B do this work alone ?

(A + B) can do a piece of work in 10 days. A works 2(1)/(2) days and B works for 8(1)/(2) days, then half of the work has been completed. In how many days will B do this work alone ?

A and B can finish a certain piece of work in 4 days. If A reduces his efficiency by 30% and B increases by 10%, then work will be finished in 5 days. If A works with his original efficiency and B work with 1(1)/(2) times of his efficiency, then in how many days working together work will be finished?

A can do a piece of work in x days.If new joins B who is twice as efficient as A,then in How many days can both finish double the work.

(A + B) can do a piece of work in 12 days. (B + C) can do same work in 6(2)/(3) days. A work for 3 days, B works for 4 days and C completed the remaining work in 7 days. In how many days will A, B and C do this work alone ?

ADVANCED MATHS BY ABHINAY MATHS ENGLISH-TIME & WORK -QUESTIONS
  1. (A + B) can do a piece of work in 14 days. A works 3(1)/(2) days and...

    Text Solution

    |

  2. (A + B) can do a piece of work in 5 days. If A works with twice of his...

    Text Solution

    |

  3. (A + B) can do a piece of work in 5 days. If A works with twice of his...

    Text Solution

    |

  4. A can do a piece of work in 4 hours. (B + C) can do the same work in 3...

    Text Solution

    |

  5. A can make (1)/(3) part of a wall in 9 days and B can make (2)/(3) p...

    Text Solution

    |

  6. A can do (13)/(56) part of a work in 111 days and B can do (43)/(56) ...

    Text Solution

    |

  7. A can do (1)/(4) part of a work in 21 days and B can do (1)/(4) part...

    Text Solution

    |

  8. (A + B) can do a piece of work in 12 days. (B + C) can do same work in...

    Text Solution

    |

  9. (A + B) can do a piece of work in 12 days. (B + C) can do same work in...

    Text Solution

    |

  10. A work for 2 days, then B complete the remaining work in 9 days. If A ...

    Text Solution

    |

  11. A can do a piece of work in 80 days. A works for 10 days, then B compl...

    Text Solution

    |

  12. A and B can do a piece of work in 45 and 40 days respectively. They...

    Text Solution

    |

  13. A and B can do a piece of work in 20 days and 30 days respectively. A ...

    Text Solution

    |

  14. A and B can do a piece of work in 20 days and 25 days. A start the wor...

    Text Solution

    |

  15. A, B and C can do a piece of work in 12, 15 and 20 days. How much mini...

    Text Solution

    |

  16. A, B and C can do a piece of work in 10, 20 and 25 days. How much mini...

    Text Solution

    |

  17. A and B can do a work in 20 days and 30 days respectively. A and B wor...

    Text Solution

    |

  18. (A + B) can do a work in 6 days. (A + B + C) can do the same work in 5...

    Text Solution

    |

  19. A takes 27 days more than (A + B) together to complete a work. B takes...

    Text Solution

    |

  20. A takes 4(1)/(2) days more than (A + B) together to complete a work. B...

    Text Solution

    |