Home
Class 14
MATHS
(A + B) can do a piece of work in 12 day...

(A + B) can do a piece of work in 12 days. (B + C) can do same work in 16 days. A work for 5 days, B works for 7 days and C completed the remaining work in 13 days. In how many days will A, B and C do this work alone ?

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will first determine the efficiencies of A, B, and C based on the information provided. ### Step 1: Determine the total work Given: - A + B can complete the work in 12 days. - B + C can complete the work in 16 days. To find the total work, we can take the least common multiple (LCM) of the two durations: - LCM of 12 and 16 is 48. Thus, the total work is 48 units. ### Step 2: Calculate the efficiencies of A + B and B + C - The efficiency of A + B: \[ \text{Efficiency of } (A + B) = \frac{\text{Total Work}}{\text{Days}} = \frac{48}{12} = 4 \text{ units/day} \] - The efficiency of B + C: \[ \text{Efficiency of } (B + C) = \frac{\text{Total Work}}{\text{Days}} = \frac{48}{16} = 3 \text{ units/day} \] ### Step 3: Set up the equations based on the work done Let: - Efficiency of A = a - Efficiency of B = b - Efficiency of C = c From the information: 1. \( a + b = 4 \) (from A + B) 2. \( b + c = 3 \) (from B + C) ### Step 4: Calculate the work done by A, B, and C - A works for 5 days: \[ \text{Work done by A} = 5a \] - B works for 7 days: \[ \text{Work done by B} = 7b \] - C completes the remaining work in 13 days: \[ \text{Work done by C} = 13c \] ### Step 5: Set up the equation for total work The total work done by A, B, and C should equal the total work: \[ 5a + 7b + 13c = 48 \] ### Step 6: Substitute the values of a and b From the equations: 1. \( a + b = 4 \) → \( a = 4 - b \) 2. Substitute \( a \) in the total work equation: \[ 5(4 - b) + 7b + 13c = 48 \] Simplifying this gives: \[ 20 - 5b + 7b + 13c = 48 \] \[ 2b + 13c = 28 \] ### Step 7: Substitute \( c \) from \( b + c = 3 \) From \( b + c = 3 \): \[ c = 3 - b \] Substituting \( c \) in the equation \( 2b + 13c = 28 \): \[ 2b + 13(3 - b) = 28 \] Expanding this gives: \[ 2b + 39 - 13b = 28 \] Combining like terms: \[ -11b + 39 = 28 \] \[ -11b = 28 - 39 \] \[ -11b = -11 \] \[ b = 1 \] ### Step 8: Find a and c Using \( b = 1 \): - From \( a + b = 4 \): \[ a = 4 - 1 = 3 \] - From \( b + c = 3 \): \[ c = 3 - 1 = 2 \] ### Step 9: Calculate the time taken by A, B, and C to complete the work alone - Time taken by A: \[ \text{Time} = \frac{\text{Total Work}}{\text{Efficiency}} = \frac{48}{3} = 16 \text{ days} \] - Time taken by B: \[ \text{Time} = \frac{48}{1} = 48 \text{ days} \] - Time taken by C: \[ \text{Time} = \frac{48}{2} = 24 \text{ days} \] ### Final Answer - A can complete the work alone in 16 days. - B can complete the work alone in 48 days. - C can complete the work alone in 24 days.
Promotional Banner

Topper's Solved these Questions

  • SIMPLE INTEREST

    ADVANCED MATHS BY ABHINAY MATHS ENGLISH|Exercise QUESTIONS|108 Videos
  • TIME, SPEED & DISTNACE

    ADVANCED MATHS BY ABHINAY MATHS ENGLISH|Exercise QUESTIONS|108 Videos

Similar Questions

Explore conceptually related problems

(A + B) can do a piece of work in 12 days. (B + C) can do same work in 6(2)/(3) days. A work for 3 days, B works for 4 days and C completed the remaining work in 7 days. In how many days will A, B and C do this work alone ?

A and B can do a piece of work in 12 days and B and C can do the same piece of work in 16 days.A work for 5 days and B work for 7 days and C complete the remaining work in 13 days then in how many days C would complete the same work?

A can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?

A can do 2/5 of a work in 12 days while B can do 66^(2/3)% of the same work in 16 days. They work together for 10 days. B alone will complete the remaining work in

A and B can do a piece of work in 8 days, B and C can do the same work in 12 days. If A, B and C can complete the same work in 6 days, in how many days can A and C complete the same work?

ADVANCED MATHS BY ABHINAY MATHS ENGLISH-TIME & WORK -QUESTIONS
  1. A can do (13)/(56) part of a work in 111 days and B can do (43)/(56) ...

    Text Solution

    |

  2. A can do (1)/(4) part of a work in 21 days and B can do (1)/(4) part...

    Text Solution

    |

  3. (A + B) can do a piece of work in 12 days. (B + C) can do same work in...

    Text Solution

    |

  4. (A + B) can do a piece of work in 12 days. (B + C) can do same work in...

    Text Solution

    |

  5. A work for 2 days, then B complete the remaining work in 9 days. If A ...

    Text Solution

    |

  6. A can do a piece of work in 80 days. A works for 10 days, then B compl...

    Text Solution

    |

  7. A and B can do a piece of work in 45 and 40 days respectively. They...

    Text Solution

    |

  8. A and B can do a piece of work in 20 days and 30 days respectively. A ...

    Text Solution

    |

  9. A and B can do a piece of work in 20 days and 25 days. A start the wor...

    Text Solution

    |

  10. A, B and C can do a piece of work in 12, 15 and 20 days. How much mini...

    Text Solution

    |

  11. A, B and C can do a piece of work in 10, 20 and 25 days. How much mini...

    Text Solution

    |

  12. A and B can do a work in 20 days and 30 days respectively. A and B wor...

    Text Solution

    |

  13. (A + B) can do a work in 6 days. (A + B + C) can do the same work in 5...

    Text Solution

    |

  14. A takes 27 days more than (A + B) together to complete a work. B takes...

    Text Solution

    |

  15. A takes 4(1)/(2) days more than (A + B) together to complete a work. B...

    Text Solution

    |

  16. A takes 5(1)/(3) days more than (A + B) together to complete a work. ...

    Text Solution

    |

  17. A takes 7 days more than B and 16 days more than C to complete a work....

    Text Solution

    |

  18. A takes 24 days more than B and 32 days more than C to complete a work...

    Text Solution

    |

  19. A takes 5 days more than B and 9 days more than C to complete a work. ...

    Text Solution

    |

  20. A takes 6 hours more than (A + B + C) together to complete a work. B t...

    Text Solution

    |