A and B can do a piece of work in 45 and 40 days respectively. They began the work together but A leaves after some das and B finished the remaining work in 23 days. After how many days did A leave?

Text Solution

Verified by Experts

The correct Answer is:
9 days
Promotional Banner

Topper's Solved these Questions

  • SIMPLE INTEREST

    ADVANCED MATHS BY ABHINAY MATHS ENGLISH|Exercise QUESTIONS|108 Videos
  • TIME, SPEED & DISTNACE

    ADVANCED MATHS BY ABHINAY MATHS ENGLISH|Exercise QUESTIONS|108 Videos

Similar Questions

Explore conceptually related problems

A and B can do a piece of work in 45 and 40 days respectively. They began the work together, but A leaves after some days and B finished the remaining work in 23 days. After how many days did A leave

A and B can do a piece of work in 45 and 40 days respectively.They began the work together but A leaves after some days and B finished the remaining work in 23 days.After how many days did A leave?

A and B can do a job in 15 days and 10 days, respectively. They began the work together but A leaves after some days and B finished the remaining job in 5 days. After how many days did A leave?

A and B can do a piece of work in 28 and 35 days respectively. They began to work together but A leaves after some time and B completed the remaining work in 17 days. After how many days did A leave ?

A and B can do a piece of work in 28 and 35 days respectively.They began to work together but A leaves after some time and B completed the remaining work in 17 days. After how many days did A leave? 7(5)/(9) days b. 8) days c.9backslash days d.14(2)/(5) days

ADVANCED MATHS BY ABHINAY MATHS ENGLISH-TIME & WORK -QUESTIONS
  1. A work for 2 days, then B complete the remaining work in 9 days. If A ...

    Text Solution

    |

  2. A can do a piece of work in 80 days. A works for 10 days, then B compl...

    Text Solution

    |

  3. A and B can do a piece of work in 45 and 40 days respectively. They...

    Text Solution

    |

  4. A and B can do a piece of work in 20 days and 30 days respectively. A ...

    Text Solution

    |

  5. A and B can do a piece of work in 20 days and 25 days. A start the wor...

    Text Solution

    |

  6. A, B and C can do a piece of work in 12, 15 and 20 days. How much mini...

    Text Solution

    |

  7. A, B and C can do a piece of work in 10, 20 and 25 days. How much mini...

    Text Solution

    |

  8. A and B can do a work in 20 days and 30 days respectively. A and B wor...

    Text Solution

    |

  9. (A + B) can do a work in 6 days. (A + B + C) can do the same work in 5...

    Text Solution

    |

  10. A takes 27 days more than (A + B) together to complete a work. B takes...

    Text Solution

    |

  11. A takes 4(1)/(2) days more than (A + B) together to complete a work. B...

    Text Solution

    |

  12. A takes 5(1)/(3) days more than (A + B) together to complete a work. ...

    Text Solution

    |

  13. A takes 7 days more than B and 16 days more than C to complete a work....

    Text Solution

    |

  14. A takes 24 days more than B and 32 days more than C to complete a work...

    Text Solution

    |

  15. A takes 5 days more than B and 9 days more than C to complete a work. ...

    Text Solution

    |

  16. A takes 6 hours more than (A + B + C) together to complete a work. B t...

    Text Solution

    |

  17. A and B together can do a piece of work in 12 days. While B and C toge...

    Text Solution

    |

  18. (A + B) together can do a piece of work in 12 days. While (B + C) toge...

    Text Solution

    |

  19. A takes as much time as B and C together to complete a work. While A a...

    Text Solution

    |

  20. A is 40 % more efficient than B. If B can complete this work in 24 day...

    Text Solution

    |