Home
Class 14
MATHS
A, B and C can do a piece of work in 12,...

A, B and C can do a piece of work in 12, 15 and 20 days. How much minimum time should be required to complete this work if more than two persons can not work in a day and in any two consecutive days same pair can not work ?

A

`6(2)/(3)`

B

`7(1)/(17)`

C

8

D

9

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem, we need to determine how much minimum time is required to complete the work given the constraints. Let's break down the solution step by step. ### Step 1: Determine the work done by A, B, and C - A can complete the work in 12 days, so A's work per day = \( \frac{1}{12} \). - B can complete the work in 15 days, so B's work per day = \( \frac{1}{15} \). - C can complete the work in 20 days, so C's work per day = \( \frac{1}{20} \). ### Step 2: Find the least common multiple (LCM) of the days To find a common basis for the work, we can assume the total work to be the LCM of 12, 15, and 20. - LCM of 12, 15, and 20 = 60. ### Step 3: Calculate the efficiency of A, B, and C - A's efficiency = \( \frac{60}{12} = 5 \) units of work per day. - B's efficiency = \( \frac{60}{15} = 4 \) units of work per day. - C's efficiency = \( \frac{60}{20} = 3 \) units of work per day. ### Step 4: Determine the work done in two consecutive days Since more than two persons cannot work in a day and the same pair cannot work on consecutive days, we can have the following pairs: 1. Day 1: A and B 2. Day 2: A and C Calculating the work done: - Work done by A and B in one day = \( 5 + 4 = 9 \) units. - Work done by A and C in the next day = \( 5 + 3 = 8 \) units. ### Step 5: Total work done in two days - Total work done in two days = Work done on Day 1 + Work done on Day 2 = \( 9 + 8 = 17 \) units. ### Step 6: Calculate the number of days required to finish the work - Total work = 60 units. - Work done in 2 days = 17 units. - Total number of 2-day cycles needed = \( \frac{60}{17} \). ### Step 7: Calculate the total time - The number of complete 2-day cycles = \( \frac{60}{17} \) which is approximately \( 3.529 \) cycles. - This means we need 3 complete cycles (6 days) and then some additional work on the 7th day. ### Step 8: Calculate remaining work after 3 cycles - Work done in 3 cycles = \( 3 \times 17 = 51 \) units. - Remaining work = \( 60 - 51 = 9 \) units. ### Step 9: Determine the work done on the 7th day - On the 7th day, we can use A and B again (as they are not the same pair as the last day). - A and B can do 9 units of work in one day, which is enough to complete the remaining work. ### Conclusion Thus, the total time required to complete the work is \( 6 + 1 = 7 \) days. ### Final Answer The minimum time required to complete the work is **7 days**.
Promotional Banner

Topper's Solved these Questions

  • SIMPLE INTEREST

    ADVANCED MATHS BY ABHINAY MATHS ENGLISH|Exercise QUESTIONS|108 Videos
  • TIME, SPEED & DISTNACE

    ADVANCED MATHS BY ABHINAY MATHS ENGLISH|Exercise QUESTIONS|108 Videos

Similar Questions

Explore conceptually related problems

A, B and C can do a piece of work in 10, 20 and 25 days. How much minimum time should be required to complete this work if more than two persons can not work in a day and in any two consecutive days same pair can not work ?

15 persons can do a piece of work in 12 days. How many more people are required to complete the work in 10 days?

30 persons can do a piece of work in 24 days. How many more people are required to complete the work in 20 days?

If 40 persons can do a piece of work in 14 days, then the number of persons required to complete the work in 28 days.

If 20 persons can do a piece of work in 7 days, then the number of persons required to complete the work in 28 days:

If 20 persons can do a piece of work in 7 days then calculate the number of persons required to complete the work in 28 days

Rakesh can do piece of work in 20 days. How much work can be do in 4 days?

A, B and C can complete a piece of work in 10, 20 and 60 days respectively. Working together they can complete the same work in how many days?

ADVANCED MATHS BY ABHINAY MATHS ENGLISH-TIME & WORK -QUESTIONS
  1. A and B can do a piece of work in 20 days and 30 days respectively. A ...

    Text Solution

    |

  2. A and B can do a piece of work in 20 days and 25 days. A start the wor...

    Text Solution

    |

  3. A, B and C can do a piece of work in 12, 15 and 20 days. How much mini...

    Text Solution

    |

  4. A, B and C can do a piece of work in 10, 20 and 25 days. How much mini...

    Text Solution

    |

  5. A and B can do a work in 20 days and 30 days respectively. A and B wor...

    Text Solution

    |

  6. (A + B) can do a work in 6 days. (A + B + C) can do the same work in 5...

    Text Solution

    |

  7. A takes 27 days more than (A + B) together to complete a work. B takes...

    Text Solution

    |

  8. A takes 4(1)/(2) days more than (A + B) together to complete a work. B...

    Text Solution

    |

  9. A takes 5(1)/(3) days more than (A + B) together to complete a work. ...

    Text Solution

    |

  10. A takes 7 days more than B and 16 days more than C to complete a work....

    Text Solution

    |

  11. A takes 24 days more than B and 32 days more than C to complete a work...

    Text Solution

    |

  12. A takes 5 days more than B and 9 days more than C to complete a work. ...

    Text Solution

    |

  13. A takes 6 hours more than (A + B + C) together to complete a work. B t...

    Text Solution

    |

  14. A and B together can do a piece of work in 12 days. While B and C toge...

    Text Solution

    |

  15. (A + B) together can do a piece of work in 12 days. While (B + C) toge...

    Text Solution

    |

  16. A takes as much time as B and C together to complete a work. While A a...

    Text Solution

    |

  17. A is 40 % more efficient than B. If B can complete this work in 24 day...

    Text Solution

    |

  18. A works thrice as much as B. If A can complete this work in 12 days, t...

    Text Solution

    |

  19. B works four times as much as A. If B takes 15 days less than A to com...

    Text Solution

    |

  20. A is 40 % more efficient than B and B is 20 % less efficient than C. I...

    Text Solution

    |