Home
Class 14
MATHS
A takes three times as long as (B + C) t...

A takes three times as long as (B + C) together to complete a work. B takes four times as much as (A + C) together to complete a work. If all the three, working together can complete the work in 22 days, then find the number of days A, B and C alone will take to complete this work

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will first define the efficiencies of A, B, and C based on the information provided in the question. ### Step 1: Define the relationships between A, B, and C 1. Let the time taken by B and C together to complete the work be \( x \) days. 2. According to the problem, A takes three times as long as B and C together, so A takes \( 3x \) days. 3. The efficiency of A is \( \frac{1}{3x} \) and the efficiency of B + C is \( \frac{1}{x} \). ### Step 2: Define the time taken by B 1. Let the time taken by A + C together be \( y \) days. 2. According to the problem, B takes four times as long as A + C together, so B takes \( 4y \) days. 3. The efficiency of B is \( \frac{1}{4y} \) and the efficiency of A + C is \( \frac{1}{y} \). ### Step 3: Set up the equations 1. From the efficiencies, we have: - Efficiency of A = \( \frac{1}{3x} \) - Efficiency of B + C = \( \frac{1}{x} \) - Efficiency of B = \( \frac{1}{4y} \) - Efficiency of A + C = \( \frac{1}{y} \) ### Step 4: Relate the efficiencies 1. Since B + C = A + C + B, we can express the efficiencies: - Efficiency of A + B + C = Efficiency of A + Efficiency of B + Efficiency of C - From the given information, we know that A takes 3 times as long as B + C, and B takes 4 times as long as A + C. ### Step 5: Calculate the total efficiency 1. We know that A + B + C working together can complete the work in 22 days, which means their combined efficiency is \( \frac{1}{22} \). 2. Therefore, \( \text{Efficiency of A} + \text{Efficiency of B} + \text{Efficiency of C} = \frac{1}{22} \). ### Step 6: Solve for individual efficiencies 1. Let’s assume the efficiencies of A, B, and C are \( a, b, c \) respectively. 2. From the relationships, we can derive: - \( a = \frac{1}{3}b \) - \( b = \frac{1}{4}c \) 3. Substitute these into the equation for total efficiency: - \( \frac{1}{3}b + b + c = \frac{1}{22} \) ### Step 7: Solve the equations 1. Substitute \( b = 4c \) into the equation: - \( \frac{1}{3}(4c) + 4c + c = \frac{1}{22} \) - This simplifies to \( \frac{4}{3}c + 4c + c = \frac{1}{22} \) - Combine like terms: \( \frac{4}{3}c + \frac{12}{3}c = \frac{16}{3}c = \frac{1}{22} \) - Solve for \( c \): \( c = \frac{1}{22} \times \frac{3}{16} = \frac{3}{352} \) ### Step 8: Calculate individual times 1. Now, using the efficiencies: - For A: \( a = \frac{1}{3}b \) and \( b = 4c \) - For B: \( b = 4c = 4 \times \frac{3}{352} = \frac{12}{352} = \frac{3}{88} \) - For C: \( c = \frac{3}{352} \) ### Step 9: Calculate the time taken by each 1. Time taken by A = \( \frac{1}{a} = \frac{1}{\frac{3}{88}} = \frac{88}{3} \approx 29.33 \) days 2. Time taken by B = \( \frac{1}{b} = \frac{1}{\frac{3}{88}} = 88 \) days 3. Time taken by C = \( \frac{1}{c} = \frac{1}{\frac{3}{352}} = 352/3 \approx 117.33 \) days ### Final Answer: - A will take approximately 29.33 days, - B will take 88 days, - C will take approximately 117.33 days.
Promotional Banner

Topper's Solved these Questions

  • SIMPLE INTEREST

    ADVANCED MATHS BY ABHINAY MATHS ENGLISH|Exercise QUESTIONS|108 Videos
  • TIME, SPEED & DISTNACE

    ADVANCED MATHS BY ABHINAY MATHS ENGLISH|Exercise QUESTIONS|108 Videos

Similar Questions

Explore conceptually related problems

B takes two times as long as (A + C) together to complete a work. C takes three times as much as (A + B) together to complete a work. If all the three, working together can complete the work in 36 days, then find the number of days A, B and C alone will take to complete this work.

B takes two times time as long as (A + C) together take to complete a work C takes three times time as much as (A + B) together take to complete a work. If all three working together can complete the work in 25 days. Then find the number of days in which A, B and C can complete the work individually.

A is twice as efficient as B and they together can complete a piece of work in 24 days. Find the number of days, that A alone takes to compelete the work.

A is twice as efficient as B and they together can complete a piece of work in 24 days. Find the number of days, that A alone takes to compelete the work.

A takes 27 days more than (A + B) together to complete a work. B takes 3 days more than (A + B) together to complete a work. In how many days will (A + B) complete this work ?

A takes 6 hours more than (A + B + C) together to complete a work. B takes 1 hours more than (A + B + C) together to complete a work. C takes twice as (A + B + C) together to complete a work. In how many days will A and B together complete this work ?

A and B working together can do 30% of the work in 6 days. B alone can do the same work in 25 days. How long will A alone take to complete the same work?

ADVANCED MATHS BY ABHINAY MATHS ENGLISH-TIME & WORK -QUESTIONS
  1. The ratio of efficiency of A and B is 3 : 5 and that of B and C is 2 :...

    Text Solution

    |

  2. A and B working together can finish certain piece of work in 10 days. ...

    Text Solution

    |

  3. A takes three times as long as (B + C) together to complete a work. B ...

    Text Solution

    |

  4. B takes two times as long as (A + C) together to complete a work. C ta...

    Text Solution

    |

  5. A does half as much work as B in one-sixth of the time.If together the...

    Text Solution

    |

  6. A does half as much work as B in three-fourth of the time. If together...

    Text Solution

    |

  7. A, B and C can do a work in 25, 40 and 60 days respectively. All three...

    Text Solution

    |

  8. A, B and C can do a work in 10, 12 and 15 days respectively. All three...

    Text Solution

    |

  9. A and B can do a work in 20 and 30 days respectively. They start the w...

    Text Solution

    |

  10. (A + B) together can complete a job in 8 days. Both B and C working al...

    Text Solution

    |

  11. A can complete a work in 18 days, B can do the same work in half the t...

    Text Solution

    |

  12. B takes two times time as long as (A + C) together take to complete a ...

    Text Solution

    |

  13. A does (4)/(5) part of the work in 20 days and rest of the work is do...

    Text Solution

    |

  14. A can do (1)/(2) of a piece of work in 5 days B can do (3)/(5) of the ...

    Text Solution

    |

  15. Rahul is twice efficient as Ram. If both of them can complete the work...

    Text Solution

    |

  16. A and B working together can complete the work in 12 days. A can compl...

    Text Solution

    |

  17. A, B and C can do a work in 12, 15 and 18 days respectively. They star...

    Text Solution

    |

  18. A and B can do a work in 15 days and 20 days respectively B started th...

    Text Solution

    |

  19. A, B and C can do a work in 20, 30 and 60 days respectively. A started...

    Text Solution

    |

  20. A, B and C can finish a piece of work in 20 days, 25 days and 30 days ...

    Text Solution

    |