Home
Class 14
MATHS
B takes two times as long as (A + C) tog...

B takes two times as long as (A + C) together to complete a work. C takes three times as much as (A + B) together to complete a work. If all the three, working together can complete the work in 36 days, then find the number of days A, B and C alone will take to complete this work.

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will define the efficiencies of A, B, and C based on the information provided and then calculate the time each would take to complete the work alone. ### Step 1: Define the efficiencies based on the given ratios 1. **B takes two times as long as (A + C) together**: - Let the time taken by A + C together to complete the work be \( t \). - Then, time taken by B = \( 2t \). - Efficiency is inversely proportional to time. Therefore, if A + C's efficiency is \( 1 \), then B's efficiency is \( \frac{1}{2} \). - Thus, the efficiency ratio of A + C to B is \( 1 : 2 \). 2. **C takes three times as long as (A + B) together**: - Let the time taken by A + B together to complete the work be \( s \). - Then, time taken by C = \( 3s \). - Similarly, if A + B's efficiency is \( 1 \), then C's efficiency is \( \frac{1}{3} \). - Thus, the efficiency ratio of A + B to C is \( 1 : 3 \). ### Step 2: Set up the equations based on the efficiencies 1. From the above, we can denote the efficiencies as: - Efficiency of A + C = \( e_{AC} \) - Efficiency of B = \( e_B = \frac{1}{2} e_{AC} \) - Efficiency of A + B = \( e_{AB} \) - Efficiency of C = \( e_C = \frac{1}{3} e_{AB} \) 2. Since A + C's efficiency and B's efficiency must be consistent, we can express: - \( e_B = \frac{1}{2} e_{AC} \) - \( e_C = \frac{1}{3} e_{AB} \) ### Step 3: Combine the efficiencies 1. Let’s denote the efficiencies of A, B, and C as \( e_A, e_B, e_C \): - From the ratios, we can say: - \( e_B = 4 \) (from the combined efficiency of A + C) - \( e_C = 3 \) (from the combined efficiency of A + B) - \( e_A + e_C = 8 \) (from A + C) - \( e_A + e_B = 12 \) (from A + B) 2. Solving these equations: - From \( e_A + e_C = 8 \) and \( e_C = 3 \): - \( e_A + 3 = 8 \) - \( e_A = 5 \) ### Step 4: Calculate total efficiency 1. Total efficiency of A, B, and C together: - \( e_A + e_B + e_C = 5 + 4 + 3 = 12 \) ### Step 5: Calculate total work done 1. Since they can complete the work in 36 days: - Total work = Total efficiency × Number of days - Total work = \( 12 \times 36 = 432 \) units of work. ### Step 6: Calculate the time taken by A, B, and C to complete the work alone 1. Time taken by A: - \( T_A = \frac{\text{Total work}}{e_A} = \frac{432}{5} = 86.4 \) days. 2. Time taken by B: - \( T_B = \frac{\text{Total work}}{e_B} = \frac{432}{4} = 108 \) days. 3. Time taken by C: - \( T_C = \frac{\text{Total work}}{e_C} = \frac{432}{3} = 144 \) days. ### Final Answer - A takes 86.4 days, - B takes 108 days, - C takes 144 days to complete the work alone.
Promotional Banner

Topper's Solved these Questions

  • SIMPLE INTEREST

    ADVANCED MATHS BY ABHINAY MATHS ENGLISH|Exercise QUESTIONS|108 Videos
  • TIME, SPEED & DISTNACE

    ADVANCED MATHS BY ABHINAY MATHS ENGLISH|Exercise QUESTIONS|108 Videos

Similar Questions

Explore conceptually related problems

A takes three times as long as (B + C) together to complete a work. B takes four times as much as (A + C) together to complete a work. If all the three, working together can complete the work in 22 days, then find the number of days A, B and C alone will take to complete this work

B takes two times time as long as (A + C) together take to complete a work C takes three times time as much as (A + B) together take to complete a work. If all three working together can complete the work in 25 days. Then find the number of days in which A, B and C can complete the work individually.

A is twice as efficient as B and they together can complete a piece of work in 24 days. Find the number of days, that A alone takes to compelete the work.

A is twice as efficient as B and they together can complete a piece of work in 24 days. Find the number of days, that A alone takes to compelete the work.

A takes 27 days more than (A + B) together to complete a work. B takes 3 days more than (A + B) together to complete a work. In how many days will (A + B) complete this work ?

A work three times as fast as B.B takes 56 days more than A to complete a work. Working together in how days can they complete the work?

A takes 4(1)/(2) days more than (A + B) together to complete a work. B takes 8 days more than (A + B) together to complete a work. In how many days will (A + B) complete this work ?

ADVANCED MATHS BY ABHINAY MATHS ENGLISH-TIME & WORK -QUESTIONS
  1. A and B working together can finish certain piece of work in 10 days. ...

    Text Solution

    |

  2. A takes three times as long as (B + C) together to complete a work. B ...

    Text Solution

    |

  3. B takes two times as long as (A + C) together to complete a work. C ta...

    Text Solution

    |

  4. A does half as much work as B in one-sixth of the time.If together the...

    Text Solution

    |

  5. A does half as much work as B in three-fourth of the time. If together...

    Text Solution

    |

  6. A, B and C can do a work in 25, 40 and 60 days respectively. All three...

    Text Solution

    |

  7. A, B and C can do a work in 10, 12 and 15 days respectively. All three...

    Text Solution

    |

  8. A and B can do a work in 20 and 30 days respectively. They start the w...

    Text Solution

    |

  9. (A + B) together can complete a job in 8 days. Both B and C working al...

    Text Solution

    |

  10. A can complete a work in 18 days, B can do the same work in half the t...

    Text Solution

    |

  11. B takes two times time as long as (A + C) together take to complete a ...

    Text Solution

    |

  12. A does (4)/(5) part of the work in 20 days and rest of the work is do...

    Text Solution

    |

  13. A can do (1)/(2) of a piece of work in 5 days B can do (3)/(5) of the ...

    Text Solution

    |

  14. Rahul is twice efficient as Ram. If both of them can complete the work...

    Text Solution

    |

  15. A and B working together can complete the work in 12 days. A can compl...

    Text Solution

    |

  16. A, B and C can do a work in 12, 15 and 18 days respectively. They star...

    Text Solution

    |

  17. A and B can do a work in 15 days and 20 days respectively B started th...

    Text Solution

    |

  18. A, B and C can do a work in 20, 30 and 60 days respectively. A started...

    Text Solution

    |

  19. A, B and C can finish a piece of work in 20 days, 25 days and 30 days ...

    Text Solution

    |

  20. A, B and C can finish a piece of work in 16 days, 20 days and 24 days ...

    Text Solution

    |