Home
Class 14
MATHS
A, B and C can do a work in 25, 40 and 6...

A, B and C can do a work in 25, 40 and 60 days respectively. All three start the work together and work for 5 days then A left and B left 10 days before the completion of work, how much time shall be taken to do whole work?

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will first calculate the work done by A, B, and C, and then determine how long it takes to complete the entire work. ### Step 1: Determine the work rates of A, B, and C. - A can complete the work in 25 days, so A's work rate is \( \frac{1}{25} \) of the work per day. - B can complete the work in 40 days, so B's work rate is \( \frac{1}{40} \) of the work per day. - C can complete the work in 60 days, so C's work rate is \( \frac{1}{60} \) of the work per day. ### Step 2: Find the combined work rate of A, B, and C. To find the combined work rate, we add their individual work rates: \[ \text{Combined work rate} = \frac{1}{25} + \frac{1}{40} + \frac{1}{60} \] To add these fractions, we need to find a common denominator. The LCM of 25, 40, and 60 is 600. Calculating each work rate: - \( \frac{1}{25} = \frac{24}{600} \) - \( \frac{1}{40} = \frac{15}{600} \) - \( \frac{1}{60} = \frac{10}{600} \) Now, adding them together: \[ \text{Combined work rate} = \frac{24 + 15 + 10}{600} = \frac{49}{600} \] ### Step 3: Calculate the work done in the first 5 days. In 5 days, the amount of work done by A, B, and C together is: \[ \text{Work done in 5 days} = 5 \times \frac{49}{600} = \frac{245}{600} \] ### Step 4: Determine the remaining work. The total work is considered as 1 (or 600 units). The remaining work after 5 days is: \[ \text{Remaining work} = 1 - \frac{245}{600} = \frac{355}{600} \] ### Step 5: Determine when B leaves the work. Let \( x \) be the total number of days taken to complete the work. B leaves 10 days before the work is completed, which means B works for \( x - 10 \) days. ### Step 6: Calculate the work done by B and C after A leaves. After 5 days, A leaves, and B and C continue working. Their combined work rate is: \[ \text{B's work rate} + \text{C's work rate} = \frac{1}{40} + \frac{1}{60} \] Finding a common denominator (LCM of 40 and 60 is 120): - \( \frac{1}{40} = \frac{3}{120} \) - \( \frac{1}{60} = \frac{2}{120} \) Adding them together: \[ \text{B + C work rate} = \frac{3 + 2}{120} = \frac{5}{120} = \frac{1}{24} \] ### Step 7: Calculate the work done by B and C. Let \( y \) be the number of days B and C work together after A leaves. Thus: \[ y = x - 5 - 10 = x - 15 \] The work done by B and C together is: \[ \text{Work done by B and C} = (x - 15) \times \frac{1}{24} \] ### Step 8: Set up the equation for total work. The total work done can be expressed as: \[ \frac{245}{600} + (x - 15) \times \frac{1}{24} = 1 \] ### Step 9: Solve for \( x \). Rearranging the equation: \[ (x - 15) \times \frac{1}{24} = 1 - \frac{245}{600} \] Calculating the right side: \[ 1 - \frac{245}{600} = \frac{600 - 245}{600} = \frac{355}{600} \] Thus: \[ (x - 15) \times \frac{1}{24} = \frac{355}{600} \] Multiplying both sides by 24: \[ x - 15 = \frac{355 \times 24}{600} \] Calculating the right side: \[ \frac{355 \times 24}{600} = \frac{8520}{600} = 14.2 \] Thus: \[ x - 15 = 14.2 \implies x = 29.2 \] ### Step 10: Finalize the total time taken. Since we are looking for the total time taken, we round \( x \) to the nearest whole number: \[ \text{Total time taken} = 29.2 \text{ days} \approx 30 \text{ days} \] ### Final Answer: The total time taken to complete the work is approximately **30 days**.
Promotional Banner

Topper's Solved these Questions

  • SIMPLE INTEREST

    ADVANCED MATHS BY ABHINAY MATHS ENGLISH|Exercise QUESTIONS|108 Videos
  • TIME, SPEED & DISTNACE

    ADVANCED MATHS BY ABHINAY MATHS ENGLISH|Exercise QUESTIONS|108 Videos

Similar Questions

Explore conceptually related problems

A, B and C can do a work in 10, 12 and 15 days respectively. All three start the work together but A left 5 days before the completion of the work and after 2 days B left, how much time shall be taken to do whole work?

A and B can do a work in 20 and 30 days respectively. They start the work together and work for 7 days then both left and C complete the remaining work in 10 days, how much time shall be taken by C to do whole work?

A,B and C can do a work in 20,45 and 120 days respectively.They started the work. A left 10 days before and B left 5 days before the completion of work. In how many days is the total work completed ?

A,B and C can do a work in 20,45 and 120 days respectively.They started the work. A left 10 days before and B left 5 days before the completion of work. In how many days is the total work completed ?

A, B and C can complete a piec of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work in completed ?

A, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?

A, B and C can do a work in 12, 15 and 18 days respectively. They started the work together but A left after 2 days and B left the work 3 days before the competition of work. Find the number of days it took them to complete the work.

ADVANCED MATHS BY ABHINAY MATHS ENGLISH-TIME & WORK -QUESTIONS
  1. A does half as much work as B in one-sixth of the time.If together the...

    Text Solution

    |

  2. A does half as much work as B in three-fourth of the time. If together...

    Text Solution

    |

  3. A, B and C can do a work in 25, 40 and 60 days respectively. All three...

    Text Solution

    |

  4. A, B and C can do a work in 10, 12 and 15 days respectively. All three...

    Text Solution

    |

  5. A and B can do a work in 20 and 30 days respectively. They start the w...

    Text Solution

    |

  6. (A + B) together can complete a job in 8 days. Both B and C working al...

    Text Solution

    |

  7. A can complete a work in 18 days, B can do the same work in half the t...

    Text Solution

    |

  8. B takes two times time as long as (A + C) together take to complete a ...

    Text Solution

    |

  9. A does (4)/(5) part of the work in 20 days and rest of the work is do...

    Text Solution

    |

  10. A can do (1)/(2) of a piece of work in 5 days B can do (3)/(5) of the ...

    Text Solution

    |

  11. Rahul is twice efficient as Ram. If both of them can complete the work...

    Text Solution

    |

  12. A and B working together can complete the work in 12 days. A can compl...

    Text Solution

    |

  13. A, B and C can do a work in 12, 15 and 18 days respectively. They star...

    Text Solution

    |

  14. A and B can do a work in 15 days and 20 days respectively B started th...

    Text Solution

    |

  15. A, B and C can do a work in 20, 30 and 60 days respectively. A started...

    Text Solution

    |

  16. A, B and C can finish a piece of work in 20 days, 25 days and 30 days ...

    Text Solution

    |

  17. A, B and C can finish a piece of work in 16 days, 20 days and 24 days ...

    Text Solution

    |

  18. A, B and C can finish a piece of work in 12 days, 15 days and 20 days ...

    Text Solution

    |

  19. A, B and C can finish a piece of work in 12 days, 16 days and 20 days ...

    Text Solution

    |

  20. A, B and C can finish a piece of work in 10 days, 12 days and 15 days ...

    Text Solution

    |