Home
Class 14
MATHS
A, B and C can do a work in 10, 12 and 1...

A, B and C can do a work in 10, 12 and 15 days respectively. All three start the work together but A left 5 days before the completion of the work and after 2 days B left, how much time shall be taken to do whole work?

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem, we need to determine how long it will take A, B, and C to complete the work together, considering the conditions given in the question. ### Step-by-Step Solution: 1. **Calculate the Work Rates of A, B, and C**: - A can complete the work in 10 days, so A's work rate is \( \frac{1}{10} \) of the work per day. - B can complete the work in 12 days, so B's work rate is \( \frac{1}{12} \) of the work per day. - C can complete the work in 15 days, so C's work rate is \( \frac{1}{15} \) of the work per day. 2. **Find the Combined Work Rate**: - To find the combined work rate of A, B, and C working together, we add their individual work rates: \[ \text{Combined work rate} = \frac{1}{10} + \frac{1}{12} + \frac{1}{15} \] - To add these fractions, we need a common denominator. The LCM of 10, 12, and 15 is 60. - Converting each fraction: \[ \frac{1}{10} = \frac{6}{60}, \quad \frac{1}{12} = \frac{5}{60}, \quad \frac{1}{15} = \frac{4}{60} \] - Now, adding them: \[ \text{Combined work rate} = \frac{6}{60} + \frac{5}{60} + \frac{4}{60} = \frac{15}{60} = \frac{1}{4} \] - This means together they can complete \( \frac{1}{4} \) of the work in one day. 3. **Determine the Total Work**: - The total work can be considered as 1 unit of work. 4. **Calculate the Time Taken to Complete the Work**: - Let \( T \) be the total time taken to complete the work. - Since A leaves 5 days before completion and B leaves 2 days after A, we can break down the work: - Let \( T - 5 \) be the time A worked (A works for \( T - 5 \) days). - B works for \( T - 2 \) days (B works for 2 days longer than A). - C works for the entire \( T \) days. 5. **Set Up the Equation**: - The work done by A, B, and C can be expressed as: \[ \text{Work done by A} = \frac{1}{10}(T - 5) \] \[ \text{Work done by B} = \frac{1}{12}(T - 2) \] \[ \text{Work done by C} = \frac{1}{15}(T) \] - The total work done by A, B, and C together should equal 1: \[ \frac{1}{10}(T - 5) + \frac{1}{12}(T - 2) + \frac{1}{15}(T) = 1 \] 6. **Solve the Equation**: - Multiply through by 60 (the LCM of 10, 12, and 15) to eliminate the denominators: \[ 6(T - 5) + 5(T - 2) + 4T = 60 \] - Expanding this gives: \[ 6T - 30 + 5T - 10 + 4T = 60 \] - Combine like terms: \[ 15T - 40 = 60 \] - Add 40 to both sides: \[ 15T = 100 \] - Divide by 15: \[ T = \frac{100}{15} = \frac{20}{3} \approx 6.67 \text{ days} \] ### Final Answer: The total time taken to complete the work is approximately \( 6.67 \) days.
Promotional Banner

Topper's Solved these Questions

  • SIMPLE INTEREST

    ADVANCED MATHS BY ABHINAY MATHS ENGLISH|Exercise QUESTIONS|108 Videos
  • TIME, SPEED & DISTNACE

    ADVANCED MATHS BY ABHINAY MATHS ENGLISH|Exercise QUESTIONS|108 Videos

Similar Questions

Explore conceptually related problems

A, B and C can do a work in 25, 40 and 60 days respectively. All three start the work together and work for 5 days then A left and B left 10 days before the completion of work, how much time shall be taken to do whole work?

A and B can do a work in 20 and 30 days respectively. They start the work together and work for 7 days then both left and C complete the remaining work in 10 days, how much time shall be taken by C to do whole work?

A,B and C can complete a work in 10,12 and 15 days respectively.They started the work together.But A left the work 5 days before its completion.B also left the work 2 days after A left.In how many days was the work completed? 4 b.15 c.7 d.8

A, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?

A, B and C can complete a piec of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work in completed ?

ADVANCED MATHS BY ABHINAY MATHS ENGLISH-TIME & WORK -QUESTIONS
  1. A does half as much work as B in three-fourth of the time. If together...

    Text Solution

    |

  2. A, B and C can do a work in 25, 40 and 60 days respectively. All three...

    Text Solution

    |

  3. A, B and C can do a work in 10, 12 and 15 days respectively. All three...

    Text Solution

    |

  4. A and B can do a work in 20 and 30 days respectively. They start the w...

    Text Solution

    |

  5. (A + B) together can complete a job in 8 days. Both B and C working al...

    Text Solution

    |

  6. A can complete a work in 18 days, B can do the same work in half the t...

    Text Solution

    |

  7. B takes two times time as long as (A + C) together take to complete a ...

    Text Solution

    |

  8. A does (4)/(5) part of the work in 20 days and rest of the work is do...

    Text Solution

    |

  9. A can do (1)/(2) of a piece of work in 5 days B can do (3)/(5) of the ...

    Text Solution

    |

  10. Rahul is twice efficient as Ram. If both of them can complete the work...

    Text Solution

    |

  11. A and B working together can complete the work in 12 days. A can compl...

    Text Solution

    |

  12. A, B and C can do a work in 12, 15 and 18 days respectively. They star...

    Text Solution

    |

  13. A and B can do a work in 15 days and 20 days respectively B started th...

    Text Solution

    |

  14. A, B and C can do a work in 20, 30 and 60 days respectively. A started...

    Text Solution

    |

  15. A, B and C can finish a piece of work in 20 days, 25 days and 30 days ...

    Text Solution

    |

  16. A, B and C can finish a piece of work in 16 days, 20 days and 24 days ...

    Text Solution

    |

  17. A, B and C can finish a piece of work in 12 days, 15 days and 20 days ...

    Text Solution

    |

  18. A, B and C can finish a piece of work in 12 days, 16 days and 20 days ...

    Text Solution

    |

  19. A, B and C can finish a piece of work in 10 days, 12 days and 15 days ...

    Text Solution

    |

  20. A, B and C working together can finish a piece of work in 32 days. The...

    Text Solution

    |