Home
Class 14
MATHS
(A + B) together can complete a job in 8...

(A + B) together can complete a job in 8 days. Both B and C working alone can finish the same job in 12 days. A and B commence work on the job and work for 4 days, where upon A leaves, B continues for 2 more days and then he leaves too, C now starts working and finishes the job, how many days will C require ?

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will first determine the work efficiencies of A, B, and C, and then calculate how much work is left after each phase of the work. ### Step 1: Determine the total work Since A + B can complete the job in 8 days, we can express the total work in terms of work units. If we assume the total work is 24 units (which is a common multiple of 8 and 12), then: - Total work = 24 units ### Step 2: Determine the efficiency of A + B The efficiency of A + B can be calculated as follows: - Efficiency of A + B = Total work / Time taken = 24 units / 8 days = 3 units/day ### Step 3: Determine the efficiency of B and C Since B and C together can complete the job in 12 days, we can calculate their combined efficiency: - Efficiency of B + C = Total work / Time taken = 24 units / 12 days = 2 units/day ### Step 4: Determine the efficiency of B Now, we know that A + B's efficiency is 3 units/day and B + C's efficiency is 2 units/day. We can express A's efficiency as follows: Let the efficiency of A be \( a \), the efficiency of B be \( b \), and the efficiency of C be \( c \). From the equations: 1. \( a + b = 3 \) (1) 2. \( b + c = 2 \) (2) ### Step 5: Calculate the work done by A and B in the first 4 days A and B work together for 4 days: - Work done by A + B in 4 days = 4 days * 3 units/day = 12 units ### Step 6: Calculate the remaining work After A and B have worked for 4 days, the remaining work is: - Remaining work = Total work - Work done = 24 units - 12 units = 12 units ### Step 7: Calculate the work done by B in the next 2 days B continues to work alone for 2 more days: - Work done by B in 2 days = 2 days * b units/day From equation (1), we can express \( b \): - Since \( a + b = 3 \), we can substitute \( b = 3 - a \). Now, we need to find \( b \) using equation (2): - From \( b + c = 2 \), we can express \( c \) as \( c = 2 - b \). ### Step 8: Substitute and solve for B's efficiency Assuming \( b = 1 \) (since \( b + c = 2 \) and it should be less than 2), we can find \( c \): - If \( b = 1 \), then \( c = 2 - 1 = 1 \). ### Step 9: Work done by B in 2 days Now, substituting \( b = 1 \): - Work done by B in 2 days = 2 days * 1 unit/day = 2 units ### Step 10: Calculate the remaining work after B's contribution After B works for 2 days, the remaining work is: - Remaining work = 12 units - 2 units = 10 units ### Step 11: Calculate how long C will take to finish the remaining work C now starts working to finish the remaining 10 units of work. Since C's efficiency is 1 unit/day: - Days required by C = Remaining work / C's efficiency = 10 units / 1 unit/day = 10 days ### Final Answer C will require **10 days** to finish the job. ---
Promotional Banner

Topper's Solved these Questions

  • SIMPLE INTEREST

    ADVANCED MATHS BY ABHINAY MATHS ENGLISH|Exercise QUESTIONS|108 Videos
  • TIME, SPEED & DISTNACE

    ADVANCED MATHS BY ABHINAY MATHS ENGLISH|Exercise QUESTIONS|108 Videos

Similar Questions

Explore conceptually related problems

A and B together can complete a job in 8 days. Both B and C. working alone can finish the same job in 12 days. A and B commence work on the job, and work for 4 days, whereupon A leaves. B continues for 2 more days, and then the he leaves too. C now starts working days did C require?

A and B together can finish a job in 24 days , while A,B and C together can finish can finish the same job in 8 days. C along will finish the job in

X can complete a job in 12 days. If X and Y work together, they can complete the job in 6 days. Y alone can complete the job in

A,B and C together can finish a job in 4 days .A and B together can finish the same job in 5 days .In how many days ,C alone will finish the same job ?

A and B together can do a job in 15 days and A alone could do the same job in 20 days how many days would B take to do half the job if he worked alone

P and Q together can do a job in 6 days. Q and R can finish the same job in 60//7 days. P started the work and worked for 3 days. Q and R continued for 6 days. Then the difference of days in which R and P can complete the job is

ADVANCED MATHS BY ABHINAY MATHS ENGLISH-TIME & WORK -QUESTIONS
  1. A, B and C can do a work in 10, 12 and 15 days respectively. All three...

    Text Solution

    |

  2. A and B can do a work in 20 and 30 days respectively. They start the w...

    Text Solution

    |

  3. (A + B) together can complete a job in 8 days. Both B and C working al...

    Text Solution

    |

  4. A can complete a work in 18 days, B can do the same work in half the t...

    Text Solution

    |

  5. B takes two times time as long as (A + C) together take to complete a ...

    Text Solution

    |

  6. A does (4)/(5) part of the work in 20 days and rest of the work is do...

    Text Solution

    |

  7. A can do (1)/(2) of a piece of work in 5 days B can do (3)/(5) of the ...

    Text Solution

    |

  8. Rahul is twice efficient as Ram. If both of them can complete the work...

    Text Solution

    |

  9. A and B working together can complete the work in 12 days. A can compl...

    Text Solution

    |

  10. A, B and C can do a work in 12, 15 and 18 days respectively. They star...

    Text Solution

    |

  11. A and B can do a work in 15 days and 20 days respectively B started th...

    Text Solution

    |

  12. A, B and C can do a work in 20, 30 and 60 days respectively. A started...

    Text Solution

    |

  13. A, B and C can finish a piece of work in 20 days, 25 days and 30 days ...

    Text Solution

    |

  14. A, B and C can finish a piece of work in 16 days, 20 days and 24 days ...

    Text Solution

    |

  15. A, B and C can finish a piece of work in 12 days, 15 days and 20 days ...

    Text Solution

    |

  16. A, B and C can finish a piece of work in 12 days, 16 days and 20 days ...

    Text Solution

    |

  17. A, B and C can finish a piece of work in 10 days, 12 days and 15 days ...

    Text Solution

    |

  18. A, B and C working together can finish a piece of work in 32 days. The...

    Text Solution

    |

  19. A, B and C working together can finish a piece of work in 32 days. The...

    Text Solution

    |

  20. A takes 4 hours more than that of A and B working together to finish c...

    Text Solution

    |