A can do (1)/(2) of a piece of work in 5...

A can do `(1)/(2)` of a piece of work in 5 days B can do `(3)/(5)` of the same work in 9 days and C can do `(2)/(3)` of that work in 8 days. In how many days can three of them to gether do the work ?

Text Solution

Verified by Experts

The correct Answer is:
4 days
Promotional Banner

Topper's Solved these Questions

  • SIMPLE INTEREST

    ADVANCED MATHS BY ABHINAY MATHS ENGLISH|Exercise QUESTIONS|108 Videos
  • TIME, SPEED & DISTNACE

    ADVANCED MATHS BY ABHINAY MATHS ENGLISH|Exercise QUESTIONS|108 Videos

Similar Questions

Explore conceptually related problems

A can do of a work in 10 days. B can do of the work in 20 days. In how many days can both A and B together do the work?

A can do (2)/(3) of a certain work in 16 days and B can do (1)/(4) of the same work in 3 days. In how many days can both finish the work, working together?

A can do (1)/(5)th of a work in 4 days and B can do (1)/(6) th of the same work in 5 days. In how many days they can finish the work, if they work together?

A can do 1/2 of the work in 5 days and B can do 2/5 of the weak in 10 days .in how many days both A and B together can do the work ?

If A can do a piece of work in 4 days, B can do the same work in 8 days and C can do the same work in 12 days , then working together , how many days will they take to complete the work ?

ADVANCED MATHS BY ABHINAY MATHS ENGLISH-TIME & WORK -QUESTIONS
  1. B takes two times time as long as (A + C) together take to complete a ...

    Text Solution

    |

  2. A does (4)/(5) part of the work in 20 days and rest of the work is do...

    Text Solution

    |

  3. A can do (1)/(2) of a piece of work in 5 days B can do (3)/(5) of the ...

    Text Solution

    |

  4. Rahul is twice efficient as Ram. If both of them can complete the work...

    Text Solution

    |

  5. A and B working together can complete the work in 12 days. A can compl...

    Text Solution

    |

  6. A, B and C can do a work in 12, 15 and 18 days respectively. They star...

    Text Solution

    |

  7. A and B can do a work in 15 days and 20 days respectively B started th...

    Text Solution

    |

  8. A, B and C can do a work in 20, 30 and 60 days respectively. A started...

    Text Solution

    |

  9. A, B and C can finish a piece of work in 20 days, 25 days and 30 days ...

    Text Solution

    |

  10. A, B and C can finish a piece of work in 16 days, 20 days and 24 days ...

    Text Solution

    |

  11. A, B and C can finish a piece of work in 12 days, 15 days and 20 days ...

    Text Solution

    |

  12. A, B and C can finish a piece of work in 12 days, 16 days and 20 days ...

    Text Solution

    |

  13. A, B and C can finish a piece of work in 10 days, 12 days and 15 days ...

    Text Solution

    |

  14. A, B and C working together can finish a piece of work in 32 days. The...

    Text Solution

    |

  15. A, B and C working together can finish a piece of work in 32 days. The...

    Text Solution

    |

  16. A takes 4 hours more than that of A and B working together to finish c...

    Text Solution

    |

  17. (A + B) working together can finish certain piece of work in 8 days an...

    Text Solution

    |

  18. A takes 4 days more to finish certain piece of work than that of B. If...

    Text Solution

    |

  19. A started a work and left after working for 4 days, then B was called ...

    Text Solution

    |

  20. A does half as much work as B, and C does half as much work as A and B...

    Text Solution

    |