A, B and C can do a work in 12, 15 and 18 days respectively. They started the work together but A left after 2 days and B left the work 3 days before the competition of work. Find the number of days it took them to complete the work.

Text Solution

Verified by Experts

The correct Answer is:
`8(5)/(11)` days
Promotional Banner

Topper's Solved these Questions

  • SIMPLE INTEREST

    ADVANCED MATHS BY ABHINAY MATHS ENGLISH|Exercise QUESTIONS|108 Videos
  • TIME, SPEED & DISTNACE

    ADVANCED MATHS BY ABHINAY MATHS ENGLISH|Exercise QUESTIONS|108 Videos

Similar Questions

Explore conceptually related problems

A, B and C can complete a work in 16, 24 and 32 days, respectively. They started together but C left after 4 days of starting and A left 6 days before completion of the work. In how many days will the work be completed ?

A,B and C can do a work in 20,45 and 120 days respectively.They started the work. A left 10 days before and B left 5 days before the completion of work. In how many days is the total work completed ?

A,B and C can do a work in 20,45 and 120 days respectively.They started the work. A left 10 days before and B left 5 days before the completion of work. In how many days is the total work completed ?

A, B and C can finish a piece of work in 12 days, 15 days and 20 days respectively. They started working together. B left the work after working 3 days and C left the work 3 days before completion of the work. In how many days work will be finished?

A,B and C can do a piece of work in 15,12 and 20 days respectively.They started the work together,but C left after 2 days.In how many days will the remaining work be completed by A and B?

A, B and C can complete a piec of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work in completed ?

ADVANCED MATHS BY ABHINAY MATHS ENGLISH-TIME & WORK -QUESTIONS
  1. Rahul is twice efficient as Ram. If both of them can complete the work...

    Text Solution

    |

  2. A and B working together can complete the work in 12 days. A can compl...

    Text Solution

    |

  3. A, B and C can do a work in 12, 15 and 18 days respectively. They star...

    Text Solution

    |

  4. A and B can do a work in 15 days and 20 days respectively B started th...

    Text Solution

    |

  5. A, B and C can do a work in 20, 30 and 60 days respectively. A started...

    Text Solution

    |

  6. A, B and C can finish a piece of work in 20 days, 25 days and 30 days ...

    Text Solution

    |

  7. A, B and C can finish a piece of work in 16 days, 20 days and 24 days ...

    Text Solution

    |

  8. A, B and C can finish a piece of work in 12 days, 15 days and 20 days ...

    Text Solution

    |

  9. A, B and C can finish a piece of work in 12 days, 16 days and 20 days ...

    Text Solution

    |

  10. A, B and C can finish a piece of work in 10 days, 12 days and 15 days ...

    Text Solution

    |

  11. A, B and C working together can finish a piece of work in 32 days. The...

    Text Solution

    |

  12. A, B and C working together can finish a piece of work in 32 days. The...

    Text Solution

    |

  13. A takes 4 hours more than that of A and B working together to finish c...

    Text Solution

    |

  14. (A + B) working together can finish certain piece of work in 8 days an...

    Text Solution

    |

  15. A takes 4 days more to finish certain piece of work than that of B. If...

    Text Solution

    |

  16. A started a work and left after working for 4 days, then B was called ...

    Text Solution

    |

  17. A does half as much work as B, and C does half as much work as A and B...

    Text Solution

    |

  18. A and C working together can finish certain piece of work in 12 days. ...

    Text Solution

    |

  19. Mohan and Sohan are working on a assignment. Mohan takes 6 hours to ty...

    Text Solution

    |

  20. A can finish 80% of work done by B in 20% more time taken by B. Workin...

    Text Solution

    |