Home
Class 14
MATHS
A, B and C can finish a piece of work in...

A, B and C can finish a piece of work in 20 days, 25 days and 30 days respectively. They started working together. After how many days A should leave the work so that total work will be complete in 12 days?

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we can follow these calculations: ### Step 1: Determine the work done by A, B, and C in one day. - A can finish the work in 20 days, so A's work per day = \( \frac{1}{20} \) - B can finish the work in 25 days, so B's work per day = \( \frac{1}{25} \) - C can finish the work in 30 days, so C's work per day = \( \frac{1}{30} \) ### Step 2: Calculate the total work done by A, B, and C together in one day. To find the total work done by A, B, and C together in one day, we add their efficiencies: \[ \text{Total work per day} = \frac{1}{20} + \frac{1}{25} + \frac{1}{30} \] To add these fractions, we first find the least common multiple (LCM) of the denominators (20, 25, and 30). - LCM of 20, 25, and 30 is 300. Now, we convert each fraction to have a denominator of 300: - A's work: \( \frac{1}{20} = \frac{15}{300} \) - B's work: \( \frac{1}{25} = \frac{12}{300} \) - C's work: \( \frac{1}{30} = \frac{10}{300} \) Now, adding these gives: \[ \text{Total work per day} = \frac{15 + 12 + 10}{300} = \frac{37}{300} \] ### Step 3: Calculate the total work done by B and C in 12 days. We need to find out how much work B and C can do in 12 days: \[ \text{Work done by B and C in 12 days} = (B + C) \times 12 \] First, we find the combined work of B and C: \[ B + C = \frac{12}{300} + \frac{10}{300} = \frac{22}{300} \] Now, work done by B and C in 12 days: \[ \text{Work done by B and C in 12 days} = \frac{22}{300} \times 12 = \frac{264}{300} = \frac{44}{50} = \frac{22}{25} \] ### Step 4: Calculate the remaining work. The total work is 1 (or 300 units). Therefore, the remaining work that A needs to complete is: \[ \text{Remaining work} = 1 - \frac{22}{25} = \frac{3}{25} \] ### Step 5: Determine how many days A needs to work to finish the remaining work. A's work per day is \( \frac{15}{300} = \frac{1}{20} \). To find out how many days A needs to finish the remaining work: \[ \text{Days A needs to work} = \text{Remaining work} \div \text{A's work per day} = \frac{3}{25} \div \frac{1}{20} = \frac{3}{25} \times 20 = \frac{60}{25} = 2.4 \text{ days} \] ### Step 6: Calculate how many days A should leave the work. Since they are working together for 12 days, if A works for 2.4 days, then: \[ \text{Days A should leave} = 12 - 2.4 = 9.6 \text{ days} \] ### Final Answer: A should leave the work after approximately 9.6 days. ---
Promotional Banner

Topper's Solved these Questions

  • SIMPLE INTEREST

    ADVANCED MATHS BY ABHINAY MATHS ENGLISH|Exercise QUESTIONS|108 Videos
  • TIME, SPEED & DISTNACE

    ADVANCED MATHS BY ABHINAY MATHS ENGLISH|Exercise QUESTIONS|108 Videos

Similar Questions

Explore conceptually related problems

A, B and C can finish a piece of work in 12 days, 15 days and 20 days respectively. They started working together. B left the work after working 3 days and C left the work 3 days before completion of the work. In how many days work will be finished?

A , B and C can do a piece of work in 24days,36 days and 108 days, respectively. They started the work together but A left 9 days after the start of the work and B left 3 days before the work was completed. For how many days did C work ?

A, B and C can complete a piece of work in 10, 20 and 60 days respectively. Working together they can complete the same work in how many days?

A, B and C can do a piece of work in10 days, 12 days and 15 days respectively. How long will they take to finish it if they work together?

A,B and C can do a piece of work in 15,12 and 20 days respectively.They started the work together,but C left after 2 days.In how many days will the remaining work be completed by A and B?

ADVANCED MATHS BY ABHINAY MATHS ENGLISH-TIME & WORK -QUESTIONS
  1. A and B can do a work in 15 days and 20 days respectively B started th...

    Text Solution

    |

  2. A, B and C can do a work in 20, 30 and 60 days respectively. A started...

    Text Solution

    |

  3. A, B and C can finish a piece of work in 20 days, 25 days and 30 days ...

    Text Solution

    |

  4. A, B and C can finish a piece of work in 16 days, 20 days and 24 days ...

    Text Solution

    |

  5. A, B and C can finish a piece of work in 12 days, 15 days and 20 days ...

    Text Solution

    |

  6. A, B and C can finish a piece of work in 12 days, 16 days and 20 days ...

    Text Solution

    |

  7. A, B and C can finish a piece of work in 10 days, 12 days and 15 days ...

    Text Solution

    |

  8. A, B and C working together can finish a piece of work in 32 days. The...

    Text Solution

    |

  9. A, B and C working together can finish a piece of work in 32 days. The...

    Text Solution

    |

  10. A takes 4 hours more than that of A and B working together to finish c...

    Text Solution

    |

  11. (A + B) working together can finish certain piece of work in 8 days an...

    Text Solution

    |

  12. A takes 4 days more to finish certain piece of work than that of B. If...

    Text Solution

    |

  13. A started a work and left after working for 4 days, then B was called ...

    Text Solution

    |

  14. A does half as much work as B, and C does half as much work as A and B...

    Text Solution

    |

  15. A and C working together can finish certain piece of work in 12 days. ...

    Text Solution

    |

  16. Mohan and Sohan are working on a assignment. Mohan takes 6 hours to ty...

    Text Solution

    |

  17. A can finish 80% of work done by B in 20% more time taken by B. Workin...

    Text Solution

    |

  18. A, B and C working together can finish a certain piece of work in 40 d...

    Text Solution

    |

  19. Shashank started a work and left after 12 days, rest work done by Niti...

    Text Solution

    |

  20. A, B and C working together can finish certain piece of work in 40 day...

    Text Solution

    |