Home
Class 14
MATHS
A, B and C can finish a piece of work in...

A, B and C can finish a piece of work in 12 days, 15 days and 20 days respectively. They started working together. B left the work after working 3 days and C left the work 3 days before completion of the work. In how many days work will be finished?

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step-by-step, we will follow these steps: ### Step 1: Calculate the work done by A, B, and C in one day. - A can finish the work in 12 days, so in one day, A does: \[ \text{Work done by A in one day} = \frac{1}{12} \text{ of the work} \] - B can finish the work in 15 days, so in one day, B does: \[ \text{Work done by B in one day} = \frac{1}{15} \text{ of the work} \] - C can finish the work in 20 days, so in one day, C does: \[ \text{Work done by C in one day} = \frac{1}{20} \text{ of the work} \] ### Step 2: Find the total work done in one day by A, B, and C together. To find the total work done by A, B, and C together in one day, we need to find the least common multiple (LCM) of their days to work out the total work in terms of a common unit. The LCM of 12, 15, and 20 is 60. - A's work in one day: \[ \text{A's work in one day} = \frac{60}{12} = 5 \text{ units} \] - B's work in one day: \[ \text{B's work in one day} = \frac{60}{15} = 4 \text{ units} \] - C's work in one day: \[ \text{C's work in one day} = \frac{60}{20} = 3 \text{ units} \] Total work done by A, B, and C in one day: \[ \text{Total work in one day} = 5 + 4 + 3 = 12 \text{ units} \] ### Step 3: Calculate the work done in the first 3 days. Since they all worked together for the first 3 days: \[ \text{Work done in 3 days} = 3 \times 12 = 36 \text{ units} \] ### Step 4: Calculate the remaining work after B leaves. Total work is 60 units. After 3 days, the remaining work is: \[ \text{Remaining work} = 60 - 36 = 24 \text{ units} \] ### Step 5: Determine the work done after B leaves. After 3 days, B leaves, and only A and C continue working. Together, A and C can do: \[ \text{Work done by A and C in one day} = 5 + 3 = 8 \text{ units} \] ### Step 6: Calculate how many days A and C work together before C leaves. Let \( x \) be the number of days A and C work together before C leaves. The work done by A and C in \( x \) days is: \[ 8x \text{ units} \] Since C leaves 3 days before the entire work is completed, they will work together for \( x \) days, and then A will continue working alone for 3 more days. The total work equation is: \[ 8x + 5(3) = 24 \] \[ 8x + 15 = 24 \] \[ 8x = 24 - 15 \] \[ 8x = 9 \implies x = \frac{9}{8} = 1.125 \text{ days} \] ### Step 7: Calculate the total time taken to finish the work. The total time taken to finish the work is: \[ \text{Total time} = 3 \text{ (initial days)} + 1.125 \text{ (days A and C worked together)} + 3 \text{ (days A worked alone)} = 3 + 1.125 + 3 = 7.125 \text{ days} \] ### Final Answer: The work will be finished in **7.125 days**.
Promotional Banner

Topper's Solved these Questions

  • SIMPLE INTEREST

    ADVANCED MATHS BY ABHINAY MATHS ENGLISH|Exercise QUESTIONS|108 Videos
  • TIME, SPEED & DISTNACE

    ADVANCED MATHS BY ABHINAY MATHS ENGLISH|Exercise QUESTIONS|108 Videos

Similar Questions

Explore conceptually related problems

A , B and C can do a piece of work in 24days,36 days and 108 days, respectively. They started the work together but A left 9 days after the start of the work and B left 3 days before the work was completed. For how many days did C work ?

A, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?

A, B and C can do a piece of work in10 days, 12 days and 15 days respectively. How long will they take to finish it if they work together?

A, B and C can do a work in 12, 15 and 18 days respectively. They started the work together but A left after 2 days and B left the work 3 days before the competition of work. Find the number of days it took them to complete the work.

ADVANCED MATHS BY ABHINAY MATHS ENGLISH-TIME & WORK -QUESTIONS
  1. A, B and C can finish a piece of work in 20 days, 25 days and 30 days ...

    Text Solution

    |

  2. A, B and C can finish a piece of work in 16 days, 20 days and 24 days ...

    Text Solution

    |

  3. A, B and C can finish a piece of work in 12 days, 15 days and 20 days ...

    Text Solution

    |

  4. A, B and C can finish a piece of work in 12 days, 16 days and 20 days ...

    Text Solution

    |

  5. A, B and C can finish a piece of work in 10 days, 12 days and 15 days ...

    Text Solution

    |

  6. A, B and C working together can finish a piece of work in 32 days. The...

    Text Solution

    |

  7. A, B and C working together can finish a piece of work in 32 days. The...

    Text Solution

    |

  8. A takes 4 hours more than that of A and B working together to finish c...

    Text Solution

    |

  9. (A + B) working together can finish certain piece of work in 8 days an...

    Text Solution

    |

  10. A takes 4 days more to finish certain piece of work than that of B. If...

    Text Solution

    |

  11. A started a work and left after working for 4 days, then B was called ...

    Text Solution

    |

  12. A does half as much work as B, and C does half as much work as A and B...

    Text Solution

    |

  13. A and C working together can finish certain piece of work in 12 days. ...

    Text Solution

    |

  14. Mohan and Sohan are working on a assignment. Mohan takes 6 hours to ty...

    Text Solution

    |

  15. A can finish 80% of work done by B in 20% more time taken by B. Workin...

    Text Solution

    |

  16. A, B and C working together can finish a certain piece of work in 40 d...

    Text Solution

    |

  17. Shashank started a work and left after 12 days, rest work done by Niti...

    Text Solution

    |

  18. A, B and C working together can finish certain piece of work in 40 day...

    Text Solution

    |

  19. A can finish (2)/(5) of work done by B in (1)/(4) of time taken by B....

    Text Solution

    |

  20. A, B and C working together can finish certain piece of work in 28 day...

    Text Solution

    |