Home
Class 14
MATHS
(A + B) working together can finish cert...

(A + B) working together can finish certain piece of work in 8 days and (B + C) can finish it in 12 days. If A works for 4 days and B works for 7 days, rest work is done by C in 9 days. In how many days C will finish the work working alone?

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, let's denote the efficiencies of A, B, and C as \(a\), \(b\), and \(c\) respectively. ### Step 1: Calculate the efficiencies of A + B and B + C Given: - A + B can finish the work in 8 days. - B + C can finish the work in 12 days. The total work can be represented as 1 unit of work. Therefore, we can express the efficiencies as follows: - Efficiency of A + B: \[ a + b = \frac{1}{8} \quad \text{(work done in one day)} \] - Efficiency of B + C: \[ b + c = \frac{1}{12} \quad \text{(work done in one day)} \] ### Step 2: Find the total work done by A and B in 4 days and B in 7 days From the problem, A works for 4 days and B works for 7 days. The work done by A and B can be calculated as: - Work done by A in 4 days: \[ 4a \] - Work done by B in 7 days: \[ 7b \] ### Step 3: Calculate the remaining work done by C The total work is 1 unit, so the remaining work after A and B have worked is done by C in 9 days: - Work done by C in 9 days: \[ 9c \] ### Step 4: Set up the equation for total work Now we can set up the equation for the total work: \[ 4a + 7b + 9c = 1 \] ### Step 5: Substitute the values of a + b and b + c From the previous steps, we have: 1. \(a + b = \frac{1}{8}\) 2. \(b + c = \frac{1}{12}\) We can express \(a\) and \(c\) in terms of \(b\): - From \(a + b = \frac{1}{8}\): \[ a = \frac{1}{8} - b \] - From \(b + c = \frac{1}{12}\): \[ c = \frac{1}{12} - b \] ### Step 6: Substitute \(a\) and \(c\) into the total work equation Substituting \(a\) and \(c\) into the total work equation: \[ 4\left(\frac{1}{8} - b\right) + 7b + 9\left(\frac{1}{12} - b\right) = 1 \] ### Step 7: Simplify the equation Expanding the equation: \[ \frac{4}{8} - 4b + 7b + \frac{9}{12} - 9b = 1 \] \[ \frac{1}{2} - 4b + 7b + \frac{3}{4} - 9b = 1 \] Combining like terms: \[ \frac{1}{2} + \frac{3}{4} - 6b = 1 \] Convert \(\frac{1}{2}\) to quarters: \[ \frac{2}{4} + \frac{3}{4} - 6b = 1 \] \[ \frac{5}{4} - 6b = 1 \] Subtract \(\frac{5}{4}\) from both sides: \[ -6b = 1 - \frac{5}{4} \] \[ -6b = \frac{4}{4} - \frac{5}{4} = -\frac{1}{4} \] Dividing both sides by -6: \[ b = \frac{1}{24} \] ### Step 8: Find \(a\) and \(c\) Now substitute \(b\) back to find \(a\) and \(c\): \[ a = \frac{1}{8} - \frac{1}{24} = \frac{3}{24} - \frac{1}{24} = \frac{2}{24} = \frac{1}{12} \] \[ c = \frac{1}{12} - \frac{1}{24} = \frac{2}{24} - \frac{1}{24} = \frac{1}{24} \] ### Step 9: Calculate the time taken by C to finish the work alone Since \(c = \frac{1}{24}\), this means C can finish the work in: \[ \text{Time taken by C} = \frac{1}{c} = \frac{1}{\frac{1}{24}} = 24 \text{ days} \] ### Final Answer C will finish the work alone in **24 days**.
Promotional Banner

Topper's Solved these Questions

  • SIMPLE INTEREST

    ADVANCED MATHS BY ABHINAY MATHS ENGLISH|Exercise QUESTIONS|108 Videos
  • TIME, SPEED & DISTNACE

    ADVANCED MATHS BY ABHINAY MATHS ENGLISH|Exercise QUESTIONS|108 Videos

Similar Questions

Explore conceptually related problems

A and C working together can finish certain piece of work in 12 days. A and B can finish same piece of work in 20 days. If A work for 24 days and B for 6 days then rest work done by C in 2 days. Then find in how many days A, B and C can finish same piece of work, working together?

A and B can finish a work together in 12 days, and B and C together in 16 days. If A alone works for 5 days and then B alone continues for 7 days, then remaining work is done by C in 13 days. In how many days can C alone finish the complete work?

A, B and C working together can finish a piece of work in 32 days. They started working together and worked for 20 days then A left the work. Rest work done by B and C in 20 days. In how many days A working alone will finish the work?

A can do a piece of work in 4 days and B can do it in 12 days. In how many days will they finish the work, both working together ?

A, B and C working together can finish a certain piece of work in 40 days. They work for 25 days and then B left and rest work done by A and C in 20 days. If efficiency of C is half of B's efficiency. Then in how many days A will finish the working alone?

(A + B) can do a piece of work in 12 days. (B + C) can do same work in 6(2)/(3) days. A work for 3 days, B works for 4 days and C completed the remaining work in 7 days. In how many days will A, B and C do this work alone ?

ADVANCED MATHS BY ABHINAY MATHS ENGLISH-TIME & WORK -QUESTIONS
  1. A, B and C can finish a piece of work in 20 days, 25 days and 30 days ...

    Text Solution

    |

  2. A, B and C can finish a piece of work in 16 days, 20 days and 24 days ...

    Text Solution

    |

  3. A, B and C can finish a piece of work in 12 days, 15 days and 20 days ...

    Text Solution

    |

  4. A, B and C can finish a piece of work in 12 days, 16 days and 20 days ...

    Text Solution

    |

  5. A, B and C can finish a piece of work in 10 days, 12 days and 15 days ...

    Text Solution

    |

  6. A, B and C working together can finish a piece of work in 32 days. The...

    Text Solution

    |

  7. A, B and C working together can finish a piece of work in 32 days. The...

    Text Solution

    |

  8. A takes 4 hours more than that of A and B working together to finish c...

    Text Solution

    |

  9. (A + B) working together can finish certain piece of work in 8 days an...

    Text Solution

    |

  10. A takes 4 days more to finish certain piece of work than that of B. If...

    Text Solution

    |

  11. A started a work and left after working for 4 days, then B was called ...

    Text Solution

    |

  12. A does half as much work as B, and C does half as much work as A and B...

    Text Solution

    |

  13. A and C working together can finish certain piece of work in 12 days. ...

    Text Solution

    |

  14. Mohan and Sohan are working on a assignment. Mohan takes 6 hours to ty...

    Text Solution

    |

  15. A can finish 80% of work done by B in 20% more time taken by B. Workin...

    Text Solution

    |

  16. A, B and C working together can finish a certain piece of work in 40 d...

    Text Solution

    |

  17. Shashank started a work and left after 12 days, rest work done by Niti...

    Text Solution

    |

  18. A, B and C working together can finish certain piece of work in 40 day...

    Text Solution

    |

  19. A can finish (2)/(5) of work done by B in (1)/(4) of time taken by B....

    Text Solution

    |

  20. A, B and C working together can finish certain piece of work in 28 day...

    Text Solution

    |