Home
Class 14
MATHS
A started a work and left after working ...

A started a work and left after working for 4 days, then B was called and he finished the work in 18 days. If A left the work after working for 6 days then B would have finished the remaining work in 12 days. In how many days can each of them, working alone finish the whole work?

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, let's denote the work done by A in one day as \( A \) and the work done by B in one day as \( B \). ### Step 1: Set up the equations based on the given information. 1. **First Scenario**: A works for 4 days and then B finishes the remaining work in 18 days. - Work done by A in 4 days = \( 4A \) - Work done by B in 18 days = \( 18B \) - Total work = \( 4A + 18B \) (Equation 1) 2. **Second Scenario**: A works for 6 days and then B finishes the remaining work in 12 days. - Work done by A in 6 days = \( 6A \) - Work done by B in 12 days = \( 12B \) - Total work = \( 6A + 12B \) (Equation 2) ### Step 2: Equate the total work from both scenarios. Since the total work is the same in both scenarios, we can set Equation 1 equal to Equation 2: \[ 4A + 18B = 6A + 12B \] ### Step 3: Simplify the equation. Rearranging the equation gives: \[ 4A + 18B - 12B = 6A \] \[ 4A + 6B = 6A \] \[ 6B = 6A - 4A \] \[ 6B = 2A \] \[ \frac{A}{B} = 3 \quad \text{(Equation 3)} \] ### Step 4: Substitute \( A \) in terms of \( B \). From Equation 3, we can express \( A \) as: \[ A = 3B \] ### Step 5: Substitute \( A \) back into one of the total work equations. Let's substitute \( A \) into Equation 1: \[ 4(3B) + 18B = \text{Total Work} \] \[ 12B + 18B = \text{Total Work} \] \[ 30B = \text{Total Work} \] ### Step 6: Find the total work. Now we know that the total work is \( 30B \). ### Step 7: Calculate the number of days each person takes to finish the work alone. 1. **For A**: \[ \text{Days taken by A} = \frac{\text{Total Work}}{A} = \frac{30B}{3B} = 10 \text{ days} \] 2. **For B**: \[ \text{Days taken by B} = \frac{\text{Total Work}}{B} = \frac{30B}{B} = 30 \text{ days} \] ### Final Answer: - A can finish the work alone in **10 days**. - B can finish the work alone in **30 days**.
Promotional Banner

Topper's Solved these Questions

  • SIMPLE INTEREST

    ADVANCED MATHS BY ABHINAY MATHS ENGLISH|Exercise QUESTIONS|108 Videos
  • TIME, SPEED & DISTNACE

    ADVANCED MATHS BY ABHINAY MATHS ENGLISH|Exercise QUESTIONS|108 Videos

Similar Questions

Explore conceptually related problems

A started a work and left after working for 2 days. Then B was called and he finished the work in 9 days. Had A left the work after working for 3 days, B would have finished the remaining work in 6 days. In how many days can each of them, working , alone, finish the whole work? a. 2.5 days , 7. 5 d a y s b. 5 d a y s , 8. 5 d a y s c. 5 d a y s , 15 d a y s d. none of these

Arjun started a task and left it after working for 2 days. Then, Bharath was called and he completed the task in 9 days. If Arjun alone had worked for 3 days, Bharath alone would have finished the remaining work in 6 days. In how many days can Arjun alone complete the task?

A can do a piece of work in 20 days and B can do the same piece of work in 30 days. They start working together and work for 5 days and then both leave he work. C alone finishes the remaining work in 14 days. In how many days will C alone finish the whole work?

Vaibhav can do a piece of work in 60 days. He works there for 15 days and then Sandeep alone finishes the remaining work in 30 days. In how many days will Vaibhav and Sandeep working together finish the work?

P can do a piece of work in 20 days and Q can do the same piece of work in 60 days. They start working together and work for 5 days and then both leave the work. R alone finishes the remaining work in 10 days. In how many days will R alone finish the whole work?

ADVANCED MATHS BY ABHINAY MATHS ENGLISH-TIME & WORK -QUESTIONS
  1. A, B and C can finish a piece of work in 20 days, 25 days and 30 days ...

    Text Solution

    |

  2. A, B and C can finish a piece of work in 16 days, 20 days and 24 days ...

    Text Solution

    |

  3. A, B and C can finish a piece of work in 12 days, 15 days and 20 days ...

    Text Solution

    |

  4. A, B and C can finish a piece of work in 12 days, 16 days and 20 days ...

    Text Solution

    |

  5. A, B and C can finish a piece of work in 10 days, 12 days and 15 days ...

    Text Solution

    |

  6. A, B and C working together can finish a piece of work in 32 days. The...

    Text Solution

    |

  7. A, B and C working together can finish a piece of work in 32 days. The...

    Text Solution

    |

  8. A takes 4 hours more than that of A and B working together to finish c...

    Text Solution

    |

  9. (A + B) working together can finish certain piece of work in 8 days an...

    Text Solution

    |

  10. A takes 4 days more to finish certain piece of work than that of B. If...

    Text Solution

    |

  11. A started a work and left after working for 4 days, then B was called ...

    Text Solution

    |

  12. A does half as much work as B, and C does half as much work as A and B...

    Text Solution

    |

  13. A and C working together can finish certain piece of work in 12 days. ...

    Text Solution

    |

  14. Mohan and Sohan are working on a assignment. Mohan takes 6 hours to ty...

    Text Solution

    |

  15. A can finish 80% of work done by B in 20% more time taken by B. Workin...

    Text Solution

    |

  16. A, B and C working together can finish a certain piece of work in 40 d...

    Text Solution

    |

  17. Shashank started a work and left after 12 days, rest work done by Niti...

    Text Solution

    |

  18. A, B and C working together can finish certain piece of work in 40 day...

    Text Solution

    |

  19. A can finish (2)/(5) of work done by B in (1)/(4) of time taken by B....

    Text Solution

    |

  20. A, B and C working together can finish certain piece of work in 28 day...

    Text Solution

    |