Home
Class 14
MATHS
Shashank started a work and left after 1...

Shashank started a work and left after 12 days, rest work done by Nitish in 15 days. Had Shashank left work, 2 days before, the rest work could have been done by Nitish in 18 days. If Shashank reduces his efficiency by 20% and Nitish increase his efficiency by 50%. Then in how many day working together they will finish the work?

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will first determine the efficiencies of Shashank and Nitish based on the information provided, and then calculate how long they will take to complete the work together after adjusting their efficiencies. ### Step 1: Determine the work done by Shashank and Nitish Let Shashank's efficiency be \( S \) and Nitish's efficiency be \( N \). - Shashank works for 12 days, so the work done by him is \( 12S \). - Nitish completes the remaining work in 15 days, so the work done by him is \( 15N \). The total work done can be expressed as: \[ W = 12S + 15N \tag{1} \] ### Step 2: Analyze the scenario if Shashank left 2 days earlier If Shashank had left after 10 days, he would have done: \[ 10S \] The remaining work would then be done by Nitish in 18 days, so: \[ \text{Remaining work} = 18N \] Setting the two expressions for the remaining work equal gives us: \[ 12S + 15N = 10S + 18N \] ### Step 3: Simplify the equation Rearranging the equation: \[ 12S - 10S = 18N - 15N \] \[ 2S = 3N \] From this, we can express \( S \) in terms of \( N \): \[ \frac{S}{N} = \frac{3}{2} \tag{2} \] ### Step 4: Assign values to efficiencies Let’s assume \( N = 2x \) (for simplicity), then: \[ S = 3x \] ### Step 5: Calculate total work done Substituting \( S \) and \( N \) back into equation (1): \[ W = 12(3x) + 15(2x) = 36x + 30x = 66x \] ### Step 6: Adjust efficiencies Shashank reduces his efficiency by 20%: \[ \text{New efficiency of Shashank} = S' = 3x - 0.2(3x) = 3x - 0.6x = 2.4x \] Nitish increases his efficiency by 50%: \[ \text{New efficiency of Nitish} = N' = 2x + 0.5(2x) = 2x + x = 3x \] ### Step 7: Calculate combined efficiency Now, the combined efficiency when they work together is: \[ \text{Total efficiency} = S' + N' = 2.4x + 3x = 5.4x \] ### Step 8: Calculate time to complete the work together The total work is \( 66x \). The time taken to complete the work together is: \[ \text{Time} = \frac{\text{Total Work}}{\text{Total Efficiency}} = \frac{66x}{5.4x} = \frac{66}{5.4} = 12.22 \text{ days} \approx 12 \text{ days} \] ### Final Answer Shashank and Nitish will finish the work together in approximately **12.22 days**.
Promotional Banner

Topper's Solved these Questions

  • SIMPLE INTEREST

    ADVANCED MATHS BY ABHINAY MATHS ENGLISH|Exercise QUESTIONS|108 Videos
  • TIME, SPEED & DISTNACE

    ADVANCED MATHS BY ABHINAY MATHS ENGLISH|Exercise QUESTIONS|108 Videos

Similar Questions

Explore conceptually related problems

A and B can finish a certain piece of work in 4 days. If A reduces his efficiency by 30% and B increases by 10%, then work will be finished in 5 days. If A works with his original efficiency and B work with 1(1)/(2) times of his efficiency, then in how many days working together work will be finished?

A, B and C working together can finish a certain piece of work in 40 days. They work for 25 days and then B left and rest work done by A and C in 20 days. If efficiency of C is half of B's efficiency. Then in how many days A will finish the working alone?

A, B and C working together can finish a piece of work in 32 days. They worked for 24 days and after that the C left. Rest of the work is completed by A and B in 28 days. Work done by A in 1 day is equal to work done by B in 2 days. In how many days working alone each one will finish the work?

S can finish 50% of a work in a day. T can do 25% of the work in a day. Both of them together will finish the work in...days.

A, B and C working together can finish certain piece of work in 28 days. They work together for 18 days, then B left. If rest work done by A and C in 25 days. Work done by A in 2 days is equal to work done by C in 3 days, then find in how many days A, B and C working alone will finish the work?

ADVANCED MATHS BY ABHINAY MATHS ENGLISH-TIME & WORK -QUESTIONS
  1. A, B and C can finish a piece of work in 20 days, 25 days and 30 days ...

    Text Solution

    |

  2. A, B and C can finish a piece of work in 16 days, 20 days and 24 days ...

    Text Solution

    |

  3. A, B and C can finish a piece of work in 12 days, 15 days and 20 days ...

    Text Solution

    |

  4. A, B and C can finish a piece of work in 12 days, 16 days and 20 days ...

    Text Solution

    |

  5. A, B and C can finish a piece of work in 10 days, 12 days and 15 days ...

    Text Solution

    |

  6. A, B and C working together can finish a piece of work in 32 days. The...

    Text Solution

    |

  7. A, B and C working together can finish a piece of work in 32 days. The...

    Text Solution

    |

  8. A takes 4 hours more than that of A and B working together to finish c...

    Text Solution

    |

  9. (A + B) working together can finish certain piece of work in 8 days an...

    Text Solution

    |

  10. A takes 4 days more to finish certain piece of work than that of B. If...

    Text Solution

    |

  11. A started a work and left after working for 4 days, then B was called ...

    Text Solution

    |

  12. A does half as much work as B, and C does half as much work as A and B...

    Text Solution

    |

  13. A and C working together can finish certain piece of work in 12 days. ...

    Text Solution

    |

  14. Mohan and Sohan are working on a assignment. Mohan takes 6 hours to ty...

    Text Solution

    |

  15. A can finish 80% of work done by B in 20% more time taken by B. Workin...

    Text Solution

    |

  16. A, B and C working together can finish a certain piece of work in 40 d...

    Text Solution

    |

  17. Shashank started a work and left after 12 days, rest work done by Niti...

    Text Solution

    |

  18. A, B and C working together can finish certain piece of work in 40 day...

    Text Solution

    |

  19. A can finish (2)/(5) of work done by B in (1)/(4) of time taken by B....

    Text Solution

    |

  20. A, B and C working together can finish certain piece of work in 28 day...

    Text Solution

    |