Home
Class 14
MATHS
A, B and C working together can finish c...

A, B and C working together can finish certain piece of work in 40 days. If (A + B) work together then take `(1)/(3)` less time than that of C takes alone. If (A + C) work together then they take `(1)/(4)` less time than that of B takes alone. In how many days (B + C) working together will finish the work?

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will first define the efficiencies of A, B, and C based on the information provided in the question. ### Step 1: Define the work done by A, B, and C Let the work done by A in one day be \( a \), by B be \( b \), and by C be \( c \). Given that A, B, and C together can finish the work in 40 days, we can express this as: \[ a + b + c = \frac{1}{40} \quad \text{(work done in one day)} \] ### Step 2: Relationship between A + B and C The problem states that A + B take \( \frac{1}{3} \) less time than C alone. Let the time taken by C alone be \( x \) days. Then, the time taken by A + B is: \[ x - \frac{x}{3} = \frac{2x}{3} \] Thus, we can express the work done by A + B as: \[ a + b = \frac{1}{\frac{2x}{3}} = \frac{3}{2x} \] ### Step 3: Relationship between A + C and B Similarly, A + C take \( \frac{1}{4} \) less time than B alone. Let the time taken by B alone be \( y \) days. Then, the time taken by A + C is: \[ y - \frac{y}{4} = \frac{3y}{4} \] Thus, we can express the work done by A + C as: \[ a + c = \frac{1}{\frac{3y}{4}} = \frac{4}{3y} \] ### Step 4: Set up equations Now we have three equations: 1. \( a + b + c = \frac{1}{40} \) 2. \( a + b = \frac{3}{2x} \) 3. \( a + c = \frac{4}{3y} \) ### Step 5: Express C's work in terms of A + B From equation 1, we can express \( c \): \[ c = \frac{1}{40} - (a + b) \] Substituting \( a + b \) from equation 2: \[ c = \frac{1}{40} - \frac{3}{2x} \] ### Step 6: Express A in terms of B and C From equation 1, we can also express \( a \): \[ a = \frac{1}{40} - b - c \] ### Step 7: Solve for efficiencies Now, we can find the efficiencies of A, B, and C. We know: - \( a + b = \frac{3}{2x} \) - \( a + c = \frac{4}{3y} \) Using the ratios of time taken, we can express the efficiencies in terms of a common factor. ### Step 8: Find the efficiency of B + C Now we need to find the efficiency of B + C: \[ b + c = (a + b + c) - a = \frac{1}{40} - a \] ### Step 9: Calculate total work done The total work done can be calculated as: \[ \text{Total Work} = \text{Efficiency} \times \text{Time} \] Using the total efficiency of A, B, and C, we can find the total work done. ### Step 10: Calculate days taken by B + C Finally, we can find the time taken by B + C to finish the work: \[ \text{Time taken by } B + C = \frac{\text{Total Work}}{b + c} \] ### Final Calculation Substituting the values will give us the final answer.
Promotional Banner

Topper's Solved these Questions

  • SIMPLE INTEREST

    ADVANCED MATHS BY ABHINAY MATHS ENGLISH|Exercise QUESTIONS|108 Videos
  • TIME, SPEED & DISTNACE

    ADVANCED MATHS BY ABHINAY MATHS ENGLISH|Exercise QUESTIONS|108 Videos

Similar Questions

Explore conceptually related problems

A and B working together can finish a piece of work in 6 days, while A alone can do it in 9 days. How much time will B alone take to finish it?

A takes 4 hours more than that of A and B working together to finish certain piece of work. While B takes 9 hours more than that of A and B working together. Then find in how many hours A and B working together can finish the work?

A takes 4 days more to finish certain piece of work than that of B. If working together they can finish the work in 8(8)/(9) days. Then in how many days working alone each can finish the work?

A, B and C working together can finish a piece of work in 32 days. They started working together and worked for 20 days then A left the work. Rest work done by B and C in 20 days. In how many days A working alone will finish the work?

A is twice as good a workman as B and together they finish a piece of work in 20 days. In how many days will A alone finish the work?

A, B and C working together can finish a certain piece of work in 40 days. They work for 25 days and then B left and rest work done by A and C in 20 days. If efficiency of C is half of B's efficiency. Then in how many days A will finish the working alone?

A is twice as good a workman as B and together they finish a piece of work in 7 days. In how many days can B alone finish the work?

A can do a piece of work in 6 days. B takes 8 days and Ctakes as long as A and B would take working together. B and C working together will complete the work in

ADVANCED MATHS BY ABHINAY MATHS ENGLISH-TIME & WORK -QUESTIONS
  1. A, B and C can finish a piece of work in 20 days, 25 days and 30 days ...

    Text Solution

    |

  2. A, B and C can finish a piece of work in 16 days, 20 days and 24 days ...

    Text Solution

    |

  3. A, B and C can finish a piece of work in 12 days, 15 days and 20 days ...

    Text Solution

    |

  4. A, B and C can finish a piece of work in 12 days, 16 days and 20 days ...

    Text Solution

    |

  5. A, B and C can finish a piece of work in 10 days, 12 days and 15 days ...

    Text Solution

    |

  6. A, B and C working together can finish a piece of work in 32 days. The...

    Text Solution

    |

  7. A, B and C working together can finish a piece of work in 32 days. The...

    Text Solution

    |

  8. A takes 4 hours more than that of A and B working together to finish c...

    Text Solution

    |

  9. (A + B) working together can finish certain piece of work in 8 days an...

    Text Solution

    |

  10. A takes 4 days more to finish certain piece of work than that of B. If...

    Text Solution

    |

  11. A started a work and left after working for 4 days, then B was called ...

    Text Solution

    |

  12. A does half as much work as B, and C does half as much work as A and B...

    Text Solution

    |

  13. A and C working together can finish certain piece of work in 12 days. ...

    Text Solution

    |

  14. Mohan and Sohan are working on a assignment. Mohan takes 6 hours to ty...

    Text Solution

    |

  15. A can finish 80% of work done by B in 20% more time taken by B. Workin...

    Text Solution

    |

  16. A, B and C working together can finish a certain piece of work in 40 d...

    Text Solution

    |

  17. Shashank started a work and left after 12 days, rest work done by Niti...

    Text Solution

    |

  18. A, B and C working together can finish certain piece of work in 40 day...

    Text Solution

    |

  19. A can finish (2)/(5) of work done by B in (1)/(4) of time taken by B....

    Text Solution

    |

  20. A, B and C working together can finish certain piece of work in 28 day...

    Text Solution

    |