Ram can do a work in 15 days, while Ram ...

Ram can do a work in 15 days, while Ram and Shiva work together they can complete the work in 10 days, in how many days Shiva can alone do the same work?

Text Solution

Verified by Experts

The correct Answer is:
30
Doubtnut Promotions Banner Mobile Dark
|

Topper's Solved these Questions

  • MAINS MOCK TEST

    ADVANCED MATHS BY ABHINAY MATHS ENGLISH|Exercise QUESTION|97 Videos
  • MIXTURE AND ALLIGATION

    ADVANCED MATHS BY ABHINAY MATHS ENGLISH|Exercise QUESTIONS|101 Videos

Similar Questions

Explore conceptually related problems

A can do a certain work in 15 days, while working together, A and B can do the same work in 7.5 days. How many days will B alone take to do the same work?

A can do a certain work in 15 days, while working together, A and B can do the same work in 7.5 days. How many days will B alone take to do the same work ?

Knowledge Check

  • A and B together can complete a work in 35 days while A alone can complete the same work in 60 days. In how many days, B alone will be able to complete the same work?

    A
    80 days
    B
    84 days
    C
    84 days
    D
    92 days
  • Ganesh, Ram and Sohan together can do a work in 16 days. If Ganesh and Ram together can do the same work in 24 days then, how long will take Sohan alone to do the same work ?

    A
    42 days
    B
    24 days
    C
    36 days
    D
    48 days
  • X alone can do a work in 10 days. Y alone can do the same in 15 days. X, Y and Z together can do the same work in 3 days. In how many days can Z alone do the work?

    A
    6
    B
    9
    C
    4
    D
    10
  • Similar Questions

    Explore conceptually related problems

    X alone can do a work in 10 days. Y alone can do the same in 15 days. X, Y and Z together can do the same work in 3 days. In how many days can Z alone do the work?

    If X and Y can complete a piece of work in 15 days, and X alone can do the same work in 30 days, find how many days will Y alone take to complete the same work?

    A can do a work in 20 days and B can do the same work in 30 days in how many days canA and B together do the work?

    A and B can do a work in 10 days .B and C can do the same work in 15 days . C and A can complete the same work in 20 days . In how many days can C alone complete the work ?

    W and T together can do a work in 12 days. W alone can do the work in 15 days. In how many days can T alone do the work?