Home
Class 14
MATHS
A contractor undertakes to make a road i...

A contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only one-third of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?

A

70

B

75

C

80

D

85

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will follow the reasoning laid out in the video transcript. ### Step-by-Step Solution: 1. **Understanding the Problem**: The contractor has 40 days to complete the road with 25 men. After 24 days, only one-third of the road is completed. The contractor wants to finish the remaining work 4 days earlier than the original schedule. 2. **Calculate the Total Work**: Let the total work required to complete the road be represented as \( W \). Since one-third of the road is completed in 24 days, the remaining work is: \[ W_{\text{remaining}} = W - \frac{1}{3}W = \frac{2}{3}W \] 3. **Determine the Remaining Time**: Since the contractor originally planned to complete the work in 40 days and has already spent 24 days, he has: \[ 40 - 24 = 16 \text{ days remaining} \] However, he wants to finish 4 days earlier, so the new time to complete the remaining work is: \[ 16 - 4 = 12 \text{ days} \] 4. **Calculate the Work Rate**: The work done by 25 men in 24 days is: \[ \text{Work done} = 25 \text{ men} \times 24 \text{ days} = 600 \text{ man-days} \] Since this represents one-third of the total work: \[ W = 3 \times 600 = 1800 \text{ man-days} \] 5. **Calculate Remaining Work**: The remaining work is: \[ W_{\text{remaining}} = \frac{2}{3}W = \frac{2}{3} \times 1800 = 1200 \text{ man-days} \] 6. **Determine Required Work Rate**: To complete the remaining work of 1200 man-days in 12 days, the required number of men \( M \) can be calculated as: \[ M \times 12 = 1200 \implies M = \frac{1200}{12} = 100 \text{ men} \] 7. **Calculate Extra Men Needed**: The contractor initially had 25 men. Therefore, the number of extra men \( x \) needed is: \[ x = M - 25 = 100 - 25 = 75 \] ### Final Answer: The contractor needs to employ **75 extra men** to complete the work 4 days earlier. ---
Promotional Banner

Topper's Solved these Questions

  • MAINS MOCK TEST

    ADVANCED MATHS BY ABHINAY MATHS ENGLISH|Exercise QUESTION|97 Videos
  • MIXTURE AND ALLIGATION

    ADVANCED MATHS BY ABHINAY MATHS ENGLISH|Exercise QUESTIONS|101 Videos
ADVANCED MATHS BY ABHINAY MATHS ENGLISH-MEN & WOMEN -QUESTIONS
  1. If 36 men can build a wall of 140 m length in 10.5 days, how many men ...

    Text Solution

    |

  2. A farmer can plough a field working 3 hours per days in 9 days. The fa...

    Text Solution

    |

  3. 8 men can do a work in 12 days. After 6 days of work, 4 more men were ...

    Text Solution

    |

  4. A can finish a work in 14 days at 6 hrs a day. B can finish it in 8 da...

    Text Solution

    |

  5. 2 men or 3 women or 4 boys can do a work in 52 days. Then in how many ...

    Text Solution

    |

  6. 12 men or 15 women or 30 boys can do a work in 45 days. Then in how ma...

    Text Solution

    |

  7. 2 men or 5 women or 3 boys can do a work in 10 days. Then in how many ...

    Text Solution

    |

  8. If 2 men and 3 boys can do a work in 10 days, 4 men can do a work in 1...

    Text Solution

    |

  9. If 6 men and 8 boys can do a piece of work in 10 days and 26 men and 4...

    Text Solution

    |

  10. If 5 men or 8 women can do a piece of work in 12 days, how many days w...

    Text Solution

    |

  11. 40 women together can complete a work in 32 days. 32 men together can ...

    Text Solution

    |

  12. A man and a woman working together can do a certain work in 18 days. T...

    Text Solution

    |

  13. A contractor undertakes to make a road in 40 days and employs 25 men. ...

    Text Solution

    |

  14. A contract to be completed in 56 days and 104 men were set towork each...

    Text Solution

    |

  15. A contract to be completed in 46 days and 117 men were set work, each ...

    Text Solution

    |

  16. A builder decided to build a farmhouse in 45 days. He employed 150 men...

    Text Solution

    |

  17. A builder decided to build a farmhouse in 20 days. He employed 40 men ...

    Text Solution

    |

  18. In a barrack of soldiers there was stock of food 190 days, for 4000 so...

    Text Solution

    |

  19. A team of 30 men is supposed to do a work in 38 days. After 25 days, 5...

    Text Solution

    |

  20. A does half as much work as B and C does half as much work as A and B ...

    Text Solution

    |