A contract to be completed in 56 days an...

A contract to be completed in 56 days and 104 men were set towork each working 8 hours a day. After 30 days, 2/5th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?

Text Solution

Verified by Experts

The correct Answer is:
56
Promotional Banner

Topper's Solved these Questions

  • MAINS MOCK TEST

    ADVANCED MATHS BY ABHINAY MATHS ENGLISH|Exercise QUESTION|97 Videos
  • MIXTURE AND ALLIGATION

    ADVANCED MATHS BY ABHINAY MATHS ENGLISH|Exercise QUESTIONS|101 Videos

Similar Questions

Explore conceptually related problems

A contract to be completed in 46 days and 117 men were set work, each working 8 hours per day. After 33 day, 4/7th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day ?

A contract is to be completed in 46 days and 117 men were set to work, each working 8 hours a day. After 33 days, 4/7 of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day? 80 b. 82 c. 81 d. 83

A contract is to be completed in 50 days and 105 men were set to work,each working 8 hours a day.After 25 days,(2)/(5) of the work is finished.How many additional men are be employed so that the work many be completed on time,each man now working 9hours a day?

A contract is to be completed in 50 days and 105 men were set to work, each working 8 h a day. After 25 days, 2/5th of the work is finished. How many additional men be employed, so that the work may be completed on time, each man now working 9 h a day ?

A contract is to be completed in 92 days and 234 men set to work , each working 16h a day. After 66 days , 4/7 of the work is completed. How many additional men many be employed , so that the work may be completed in time , each man now working 18h a day ?

90 men are engaged to do a piece of work in 40 days but it is found that in 25 days, 2/3 work is completed. How many men should be allowed to go off, so that the work may be finished in time?

ADVANCED MATHS BY ABHINAY MATHS ENGLISH-MEN & WOMEN -QUESTIONS
  1. If 36 men can build a wall of 140 m length in 10.5 days, how many men ...

    Text Solution

    |

  2. A farmer can plough a field working 3 hours per days in 9 days. The fa...

    Text Solution

    |

  3. 8 men can do a work in 12 days. After 6 days of work, 4 more men were ...

    Text Solution

    |

  4. A can finish a work in 14 days at 6 hrs a day. B can finish it in 8 da...

    Text Solution

    |

  5. 2 men or 3 women or 4 boys can do a work in 52 days. Then in how many ...

    Text Solution

    |

  6. 12 men or 15 women or 30 boys can do a work in 45 days. Then in how ma...

    Text Solution

    |

  7. 2 men or 5 women or 3 boys can do a work in 10 days. Then in how many ...

    Text Solution

    |

  8. If 2 men and 3 boys can do a work in 10 days, 4 men can do a work in 1...

    Text Solution

    |

  9. If 6 men and 8 boys can do a piece of work in 10 days and 26 men and 4...

    Text Solution

    |

  10. If 5 men or 8 women can do a piece of work in 12 days, how many days w...

    Text Solution

    |

  11. 40 women together can complete a work in 32 days. 32 men together can ...

    Text Solution

    |

  12. A man and a woman working together can do a certain work in 18 days. T...

    Text Solution

    |

  13. A contractor undertakes to make a road in 40 days and employs 25 men. ...

    Text Solution

    |

  14. A contract to be completed in 56 days and 104 men were set towork each...

    Text Solution

    |

  15. A contract to be completed in 46 days and 117 men were set work, each ...

    Text Solution

    |

  16. A builder decided to build a farmhouse in 45 days. He employed 150 men...

    Text Solution

    |

  17. A builder decided to build a farmhouse in 20 days. He employed 40 men ...

    Text Solution

    |

  18. In a barrack of soldiers there was stock of food 190 days, for 4000 so...

    Text Solution

    |

  19. A team of 30 men is supposed to do a work in 38 days. After 25 days, 5...

    Text Solution

    |

  20. A does half as much work as B and C does half as much work as A and B ...

    Text Solution

    |