Thirty men were engged to construct a ro...

Thirty men were engged to construct a road in 2 months. But 6 men did not come to work at all. How many days will it take to construct the road ?
(Assume that 2 months = 60 days.)

Text Solution

Verified by Experts

The correct Answer is:
75 days
Promotional Banner

Similar Questions

Explore conceptually related problems

5 men can complete a job in 8 days. How many days will it take if 12 men do the job?

72 men do a piece of work in 25 days. In how many days will 30 men do the same work ?

If 36 men can do a piece of work in 25 days, in how many days will 15 men do it?

If 78 men can do a work in 140 days, in how many days will 42 men do the same work ?

36 men can do a piece of work in 7 days. How many men will do the same work in 42 days ?

If 56 men can do a piece of work in 42 days. How many men will do it in 14 days?

If 52 men can do a piece of work in 35 days in how many days 28 men will do it ?

A takes 9 days more than B to do a certain piece of work. Together they can do the work in 6 days. How many days will A alone take to do the work?

If 15 men can complete a piece of work in 30 days, in how many days will 18 men complete it ?

6 men can complete the electric fitting in a building in 7 days. How many days will it take if 21 men do the job?