Home
Class 8
MATHS
A can do a piece of work in 80 days and ...

A can do a piece of work in 80 days and B in 100 days. They work together for first 20 days before B goes away. In how many days will A manage to finish the remaining work?

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will first determine the work done by A and B, then calculate the remaining work after they work together for 20 days, and finally find out how long it will take A to finish the remaining work alone. ### Step 1: Determine the work done by A and B A can complete the work in 80 days, and B can complete it in 100 days. The efficiency (work done per day) of A is: \[ \text{Efficiency of A} = \frac{1}{80} \text{ (work units per day)} \] The efficiency of B is: \[ \text{Efficiency of B} = \frac{1}{100} \text{ (work units per day)} \] ### Step 2: Find the combined efficiency of A and B To find the combined efficiency of A and B when they work together, we add their efficiencies: \[ \text{Combined Efficiency} = \frac{1}{80} + \frac{1}{100} \] To add these fractions, we need a common denominator. The least common multiple of 80 and 100 is 400. Therefore: \[ \frac{1}{80} = \frac{5}{400} \quad \text{and} \quad \frac{1}{100} = \frac{4}{400} \] \[ \text{Combined Efficiency} = \frac{5}{400} + \frac{4}{400} = \frac{9}{400} \] ### Step 3: Calculate the work done in the first 20 days Now, we calculate the total work done by A and B together in the first 20 days: \[ \text{Work done in 20 days} = \text{Combined Efficiency} \times \text{Time} = \frac{9}{400} \times 20 \] \[ \text{Work done in 20 days} = \frac{180}{400} = \frac{9}{20} \text{ of the total work} \] ### Step 4: Determine the total work Since A can complete the total work in 80 days, the total work can be represented in terms of work units: \[ \text{Total Work} = 80 \times \text{Efficiency of A} = 80 \times \frac{1}{80} = 1 \text{ (total work units)} \] ### Step 5: Calculate the remaining work The remaining work after A and B have worked together for 20 days is: \[ \text{Remaining Work} = 1 - \frac{9}{20} = \frac{20}{20} - \frac{9}{20} = \frac{11}{20} \] ### Step 6: Calculate how long it will take A to finish the remaining work Now, we need to find out how long it will take A to finish the remaining \(\frac{11}{20}\) of the work alone. A's efficiency is \(\frac{1}{80}\), so we can set up the equation: \[ \text{Time} = \frac{\text{Remaining Work}}{\text{Efficiency of A}} = \frac{\frac{11}{20}}{\frac{1}{80}} = \frac{11}{20} \times 80 = 44 \text{ days} \] ### Final Answer A will take **44 days** to finish the remaining work alone. ---
Promotional Banner

Topper's Solved these Questions

  • DIRECT AND INVERSE VARIATIONS

    ICSE|Exercise EXERCISE 10 (A) |13 Videos
  • DIRECT AND INVERSE VARIATIONS

    ICSE|Exercise EXERCISE 10 (B)|11 Videos
  • DATA HANDLING

    ICSE|Exercise EXERCISE 22 (B) |10 Videos
  • EXPONENTS (POWERS)

    ICSE|Exercise EXERCISE 2(B)|50 Videos

Similar Questions

Explore conceptually related problems

A can finish a piece of work in 15 days and B can do it in 10 days. They worked together for 2 days and then B goes away. In how many days will A finish the remaining work ?

A can do a piece of work in 25 days and B can finish it in 20 days. They work together for 5 days and then A goes away. In how many days will B finish the remaining work ?

A can do a piece of work in 40 days and B in 45 days.They work together for 10 days and then B goes away. In how many days will A finish the remaining work?

A\ a n d\ B can do a piece of work in 20 days and 15 days. They work together for 2 days and then A goes away. In how many days will B finish the remaining work?

A can do a piece of work in 20 days and B in 15 days. They worked together on it for 6 days and then A left. How long will B take to finish the remaining work ?

A can do a piece of work in 10 days and B in 15 days. How long will they take to finish it working together ?

A and B together can do a piece of work in 15 days. If one day's work of A be 1 (1)/(2) times one day's work of B, find how many days will each take to finish the work alone?

A can do a work in 15 days and B in 20 days. If they work together on it for 4 days, what fraction of the work will be left ?

A and B can do a piece of work in 45 days and 40 days respectively.They began the work together but A leaves after some days and B finishes the remaining work in 23 days. After how many days did A leave the work ?

A can do a piece of work in 10 days, B in 18 days and A, B and C together in 4 days. In what time would C do it alone ?

ICSE-DIRECT AND INVERSE VARIATIONS-EXERCISE 10 (E)
  1. A can do a piece of work in 80 days and B in 100 days. They work toget...

    Text Solution

    |

  2. A can do a piece of work in 10 days and B in 15 days. How long will th...

    Text Solution

    |

  3. A and B together can do a piece of work in 6(2)/(3) days, but B along ...

    Text Solution

    |

  4. A can do a work in 15 days and B in 20 days. If they work together on ...

    Text Solution

    |

  5. A, B and C can do a piece of work in 6 days, 12 days and 24 days resp...

    Text Solution

    |

  6. A and B working together can mow a field in 56 days and with the help ...

    Text Solution

    |

  7. A can do a piece of work in 24 days, A and B can do it in 16 days and ...

    Text Solution

    |

  8. A can do a piece of work in 20 days and B in 15 days. They worked toge...

    Text Solution

    |

  9. A can finish a piece of work in 15 days and B can do it in 10 days. Th...

    Text Solution

    |

  10. A can do a piece of work in 10 days, B in 18 days and A, B and C toget...

    Text Solution

    |

  11. A can do (1)/(4) of a work in 5 days and B can do (1)/(3) of the same ...

    Text Solution

    |

  12. One tap can fill a cistern in 3 hours and the waste pipe can empty the...

    Text Solution

    |

  13. A and B can do a work in 8 days, B and C in 12 days, and A and C in 16...

    Text Solution

    |

  14. A and B complete a piece of work in 24 days, B and C do the same work ...

    Text Solution

    |

  15. A and B complete a piece of work in 24 days, B and C do the same work ...

    Text Solution

    |

  16. A and B complete a piece of work in 24 days, B and C do the same work ...

    Text Solution

    |

  17. A and B can do a piece of work in 40 days, B and C in 30 days, and C a...

    Text Solution

    |

  18. A and B can do a piece of work in 40 days, B and C in 30 days, and C a...

    Text Solution

    |

  19. A can do a piece of work in 10 days, B in 12 days and C in 15 days. Al...

    Text Solution

    |

  20. Two pipes P and Q would fill an empty cistern in 24 minutes and 32 min...

    Text Solution

    |