Home
Class 8
MATHS
A can do a piece of work in 10 days, B i...

A can do a piece of work in 10 days, B in 12 days and C in 15 days. All begin together but A leaves the work after 2 days and B leaves 3 days befor the work is finished. How long did the work last ?

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will first determine the efficiency of each worker, then calculate the total work done, and finally find out how long the work lasted. ### Step 1: Determine the efficiency of A, B, and C - A can complete the work in 10 days, so A's efficiency = 1/10 of the work per day. - B can complete the work in 12 days, so B's efficiency = 1/12 of the work per day. - C can complete the work in 15 days, so C's efficiency = 1/15 of the work per day. ### Step 2: Find the least common multiple (LCM) of the days To find a common measure for their efficiencies, we calculate the LCM of 10, 12, and 15. - LCM(10, 12, 15) = 60 ### Step 3: Convert efficiencies to a common scale Now we convert their efficiencies based on the LCM: - A's efficiency = 60/10 = 6 units of work per day - B's efficiency = 60/12 = 5 units of work per day - C's efficiency = 60/15 = 4 units of work per day ### Step 4: Calculate the total work The total work can be calculated as: Total work = Efficiency × Time = 60 units (as calculated from A's work). ### Step 5: Calculate work done in the first 2 days In the first 2 days, all three work together: - Total efficiency of A, B, and C = 6 + 5 + 4 = 15 units/day - Work done in 2 days = 2 × 15 = 30 units ### Step 6: Remaining work after 2 days Remaining work = Total work - Work done in 2 days = 60 - 30 = 30 units ### Step 7: Determine the time taken by B and C B leaves 3 days before the work is finished, which means we need to find out how long B and C worked together before B left. Let T be the total time taken to finish the work. Since B leaves 3 days before the work is finished, B and C work together for (T - 3) days. ### Step 8: Work done by B and C together During the time B and C work together: - Work done by B and C in (T - 3) days = (5 + 4) × (T - 3) = 9(T - 3) units ### Step 9: Work done by C alone After B leaves, C works alone for 3 days: - Work done by C in 3 days = 4 × 3 = 12 units ### Step 10: Set up the equation Total work done = Work done by A + Work done by B and C + Work done by C alone: \[ 30 + 9(T - 3) + 12 = 60 \] ### Step 11: Solve the equation Expanding the equation: \[ 30 + 9T - 27 + 12 = 60 \] \[ 9T + 15 = 60 \] \[ 9T = 60 - 15 \] \[ 9T = 45 \] \[ T = 5 \] ### Step 12: Calculate total time of work Total time of work = Time A worked + Time B and C worked together + Time C worked alone \[ = 2 + (T - 3) + 3 \] \[ = 2 + (5 - 3) + 3 \] \[ = 2 + 2 + 3 = 7 \text{ days} \] ### Final Answer The total duration of the work lasted **7 days**. ---
Promotional Banner

Topper's Solved these Questions

  • DIRECT AND INVERSE VARIATIONS

    ICSE|Exercise EXERCISE 10 (D)|13 Videos
  • DATA HANDLING

    ICSE|Exercise EXERCISE 22 (B) |10 Videos
  • EXPONENTS (POWERS)

    ICSE|Exercise EXERCISE 2(B)|50 Videos

Similar Questions

Explore conceptually related problems

A can do a piece of work in 10 days, B in 18 days and A, B and C together in 4 days. In what time would C do it alone ?

A can do a piece of work in 10 days and B in 15 days. How long will they take to finish it working together ?

If 36 men can do a piece of work in 25 days, in how many days will 15 men do it?

Rakesh can do piece of work in 20 days. How much work can be do in 4 days?

If 12 women can do a piece of work in 9 days, in how many days can 18 women do it ?

A and B can do a piece of work in 40 days, B and C in 30 days, and C and A in 24 days. How long will it take them to do the work, working together ?

A and B can do a piece of work in 18 days .B and C in 24 days and A and C in 36 days .In what time can they do it , all works together

A and B can do a piece of work in 40 days, B and C in 30 days, and C and A in 24 days. In what time can each finish it working alone ?

A can do a piece of work in 40 days and B in 45 days.They work together for 10 days and then B goes away. In how many days will A finish the remaining work?

Anil can do a piece of work in 5 days and ankur in 4 days. How long will they take to do the same work, if they work together?

ICSE-DIRECT AND INVERSE VARIATIONS-EXERCISE 10 (E)
  1. A can do a piece of work in 10 days and B in 15 days. How long will th...

    Text Solution

    |

  2. A and B together can do a piece of work in 6(2)/(3) days, but B along ...

    Text Solution

    |

  3. A can do a work in 15 days and B in 20 days. If they work together on ...

    Text Solution

    |

  4. A, B and C can do a piece of work in 6 days, 12 days and 24 days resp...

    Text Solution

    |

  5. A and B working together can mow a field in 56 days and with the help ...

    Text Solution

    |

  6. A can do a piece of work in 24 days, A and B can do it in 16 days and ...

    Text Solution

    |

  7. A can do a piece of work in 20 days and B in 15 days. They worked toge...

    Text Solution

    |

  8. A can finish a piece of work in 15 days and B can do it in 10 days. Th...

    Text Solution

    |

  9. A can do a piece of work in 10 days, B in 18 days and A, B and C toget...

    Text Solution

    |

  10. A can do (1)/(4) of a work in 5 days and B can do (1)/(3) of the same ...

    Text Solution

    |

  11. One tap can fill a cistern in 3 hours and the waste pipe can empty the...

    Text Solution

    |

  12. A and B can do a work in 8 days, B and C in 12 days, and A and C in 16...

    Text Solution

    |

  13. A and B complete a piece of work in 24 days, B and C do the same work ...

    Text Solution

    |

  14. A and B complete a piece of work in 24 days, B and C do the same work ...

    Text Solution

    |

  15. A and B complete a piece of work in 24 days, B and C do the same work ...

    Text Solution

    |

  16. A and B can do a piece of work in 40 days, B and C in 30 days, and C a...

    Text Solution

    |

  17. A and B can do a piece of work in 40 days, B and C in 30 days, and C a...

    Text Solution

    |

  18. A can do a piece of work in 10 days, B in 12 days and C in 15 days. Al...

    Text Solution

    |

  19. Two pipes P and Q would fill an empty cistern in 24 minutes and 32 min...

    Text Solution

    |