In sequencing problems one has to …. the...

In sequencing problems one has to …. the total processing time or cost.

Text Solution

AI Generated Solution

The correct Answer is:
To solve the given question, we need to determine the correct term to fill in the blank regarding sequencing problems in operations research. The question states: "In sequencing problems one has to _____ the total processing time or cost." ### Step-by-Step Solution: 1. **Understand the Concept of Sequencing Problems**: - Sequencing problems involve arranging jobs or tasks in a specific order to optimize certain criteria, such as time or cost. 2. **Identify the Goals of Sequencing**: - The primary objectives in sequencing problems often include maximizing profit or minimizing time and cost. 3. **Determine the Correct Term**: - Since the question specifically mentions "total processing time or cost," we need to focus on minimizing these factors. 4. **Fill in the Blank**: - Therefore, the correct term to fill in the blank is "minimize." The complete statement would be: "In sequencing problems, one has to minimize the total processing time or cost." ### Final Answer: In sequencing problems, one has to **minimize** the total processing time or cost. ---
Promotional Banner

Topper's Solved these Questions

  • QUESTION BANK 2021

    NAVNEET PUBLICATION - MAHARASHTRA BOARD|Exercise Part II ASSIGNMENT PROBLEMS AND SEQUENCING (III. State whether each of the following is true or false.)|12 Videos
  • QUESTION BANK 2021

    NAVNEET PUBLICATION - MAHARASHTRA BOARD|Exercise Part II ASSIGNMENT PROBLEMS AND SEQUENCING (IV. Attempt the following questions)|10 Videos
  • QUESTION BANK 2021

    NAVNEET PUBLICATION - MAHARASHTRA BOARD|Exercise Part II ASSIGNMENT PROBLEMS AND SEQUENCING (I. Select and write the most appropriate answer from the given alternatives for each sub question.)|12 Videos
  • PROBABILITY DISTRIBUTION

    NAVNEET PUBLICATION - MAHARASHTRA BOARD|Exercise MULTIPLE CHOICE QUESTIONS|9 Videos
  • THREE DIMENSIONAL GEOMETRY

    NAVNEET PUBLICATION - MAHARASHTRA BOARD|Exercise MULTIPLE CHOICE QUESTIONS|8 Videos

Similar Questions

Explore conceptually related problems

In sequencing problem one has to determine the …. in which jobs has to processed through the machines.

Total Cost

In sequencing problem the time required to transfer a job from one machine to another is…..

Solve the following problem of sequencing for minimizing the total elapsed time and idle time for both the machines. The optimal sequence of the jobs as follows: Total elapsed time is obtained as follows: Total elapsed time T = square minutes Idle time for Machine A = T- square = square minutes Idle time for Machine B = square

In sequencing problem the time which required to complete all the jobs i.e. entire task is called ….