One of the assumptions is made while sequencing n jobs on 2 machines is: two jobs must be loaded at a time on any machine. (True/False)

Text Solution

Verified by Experts

The correct Answer is:
False
Promotional Banner

Topper's Solved these Questions

  • QUESTION BANK 2021

    NAVNEET PUBLICATION - MAHARASHTRA BOARD|Exercise Part II ASSIGNMENT PROBLEMS AND SEQUENCING (IV. Attempt the following questions)|10 Videos
  • QUESTION BANK 2021

    NAVNEET PUBLICATION - MAHARASHTRA BOARD|Exercise Part II ASSIGNMENT PROBLEMS AND SEQUENCING (V. Activities) |2 Videos
  • QUESTION BANK 2021

    NAVNEET PUBLICATION - MAHARASHTRA BOARD|Exercise Part II ASSIGNMENT PROBLEMS AND SEQUENCING (II. Fill in the blanks)|12 Videos
  • PROBABILITY DISTRIBUTION

    NAVNEET PUBLICATION - MAHARASHTRA BOARD|Exercise MULTIPLE CHOICE QUESTIONS|9 Videos
  • THREE DIMENSIONAL GEOMETRY

    NAVNEET PUBLICATION - MAHARASHTRA BOARD|Exercise MULTIPLE CHOICE QUESTIONS|8 Videos

Similar Questions

Explore conceptually related problems

The Hungarian method is used to assign n jobs on 2 machines to get the optimal sequence. (True/False)

The idle time for a machine is the time when machine is available but is not waiting for any job to be processed. (True/False)

In assignment problem each worker or machine is assigned only one job. (True/False)

In sequencing problem one has to determine the …. in which jobs has to processed through the machines.

A furniture form manufactures chairs and tables, each requiring the use of three machines A, B and C. Production of one chair requires 2 hours on machine A, 1 hour on machine B, and 1 hour on machine C. Each table requires 1 hour each on machines A and B and 3 hours on machine C. Profit realized by selling one chair is Rs. 30 while for a table the figure is Rs. 60. The total time available per week on machine A is 70 hours, on machine B is 40 hours, and on machine C is 90 hours. How many chairs and table should be made per week so as to maximize profit? Develop a mathematical formulation.

Solve the following problem of sequencing for minimizing the total elapsed time and idle time for both the machines. The optimal sequence of the jobs as follows: Total elapsed time is obtained as follows: Total elapsed time T = square minutes Idle time for Machine A = T- square = square minutes Idle time for Machine B = square