Three persons undertake to complete a pi...

Three persons undertake to complete a piece of work for Rs 1,200. The first person can complete the work in 8 days, second person in 12 days and third person in 16 days. They complete the work with the help of a fourth person in 3 days. What does the fourth person get?

A

Rs.180

B

Rs.200

C

Rs.225

D

Rs.250

Text Solution

Verified by Experts

Promotional Banner

Topper's Solved these Questions

  • 2013 TIER-II PAPER(20)

    CHAMPION PUBLICATION|Exercise EXERCISE|100 Videos
  • 2014 TIER-II PAPER(18)

    CHAMPION PUBLICATION|Exercise EXERCISE|100 Videos

Similar Questions

Explore conceptually related problems

A and B undertake to complete a piece of work for Rupees 1200. A can do it in 8 days, B can do it in 12 days and with the help of C they complete the work in 4 days. Find the share of C ?

15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?

12 persons can complete half of a work in 9 days. How many persons can complete the same work (whole) in 6 days?

If a person X completes ((1)/(n)) thpart of the work in one day then person X will take n days to complete the work.

If 20 persons can do a piece of work in 7 days, then the number of persons required to complete the work in 28 days:

If 3 persons can do a piece of work in 4 days, then 4 persons can do it in …… days.

CHAMPION PUBLICATION-2013 TIER-II PAPER(21)-EXERCISE
  1. The odd term in the sequence 0 7 26 63 124 217 is

    Text Solution

    |

  2. If x men can do a piece of work In x days, then the number of days in ...

    Text Solution

    |

  3. Three persons undertake to complete a piece of work for Rs 1,200. The ...

    Text Solution

    |

  4. Two workers A and B working together completed a job in 5 days. If A w...

    Text Solution

    |

  5. A can do a piece of work in 20 days and B in 30 days. They work togeth...

    Text Solution

    |

  6. Sunil completes a work in 4 days, whereas Dinesh completes the work in...

    Text Solution

    |

  7. A farmer can plough a field working 6 hours per day in 18 days. The wo...

    Text Solution

    |

  8. Successive discounts of p% and q% on the catalogue price of an article...

    Text Solution

    |

  9. A tradesman marks his goods 30% more than the cost price. If he allows...

    Text Solution

    |

  10. A shopkeeper purchased a chair of M.P. Rs 600 after getting two consec...

    Text Solution

    |

  11. The marked price of a paino was Rs 15,000. At the time of sale, there ...

    Text Solution

    |

  12. The third proportional of 12 and 18 is- 12 तथा 18 का तीसरा समानुपाति...

    Text Solution

    |

  13. Ram got twice as many marks in English as in Science. His total marks ...

    Text Solution

    |

  14. Three numbers are in the ratio 2:3:4. If the sum of their squares is 1...

    Text Solution

    |

  15. If x runs are scored by A y runs by B and z runs by C, then x:y = y:z=...

    Text Solution

    |

  16. Rs.900 is divided among A, B, C, the division is such that 1/2 of A’s ...

    Text Solution

    |

  17. If Rs 126.50 is divided among A, B and C in the ratio of 2 : 5 : 4, th...

    Text Solution

    |

  18. The average of first three numbers is double of the fourth number. If ...

    Text Solution

    |

  19. If the average of 6 consecutive even numbers is 25, the difference bet...

    Text Solution

    |

  20. A train goes from Ballygunge to Sealdah at an average speed of 20 km/h...

    Text Solution

    |