Rs. 10,000 has to be distributed among 3...

Rs. 10,000 has to be distributed among 3 craftsmen, 5 helpers and 6 labourers such that each helper receives the amount twice as much as a labourer receives and each craftsman receives the amount thrice as much as a labourer receives. What is the amount received by the three craftsmen ?
10000 रुपये का वितरण 3 शिल्पकारों, 5 सहायकों तथा 6 श्रमिकों के बीच इस प्रकार करना है कि प्रत्येक सहायक को मिलने वाली राशि एक श्रमिक को मिलने वाली राशि से दोगुनी हो तथा प्रत्येक शिल्पकार को मिलने वाली राशि एक श्रमिक को मिलने वाली राशि से तिगुनी हो | तीनों शिल्पकारों द्वारा प्राप्त की गयी राशि ज्ञात करें |

A

Rs. 2400

B

Rs. 4000

C

Rs. 3600

D

Rs. 2700

Text Solution

AI Generated Solution

Promotional Banner

Topper's Solved these Questions

PINNACLE-WORK AND TIME-EXERCISE
  1. It is given that men are twice as efficient than women in respect to d...

    Text Solution

    |

  2. A and B can complete a piece of work in 15 days and 10 days respective...

    Text Solution

    |

  3. Rs. 10,000 has to be distributed among 3 craftsmen, 5 helpers and 6 la...

    Text Solution

    |

  4. A can complete a piece of work in 20 days and B can complete 20% of th...

    Text Solution

    |

  5. A, B and C, alone can do a piece of work in 9, 12 and 18 days respecti...

    Text Solution

    |

  6. A and B can finish a work together in 30 days, B and C can finish the ...

    Text Solution

    |

  7. A can do work in 12 days. B can do work in 18 days. After 5 days of wo...

    Text Solution

    |

  8. 6 men or 5 women earn Rs 14,820 in two days. How much will 4 women and...

    Text Solution

    |

  9. A can do a work in 20 days, while B can do the same work in 25 days. T...

    Text Solution

    |

  10. The ratio of efficiencies of A , B and C is 7 : 5 : 8. Working togethe...

    Text Solution

    |

  11. A can do 40% of a work in 6 days and B can do 30% of the same work in ...

    Text Solution

    |

  12. To do a certain work, the ratio of efficiency of A to that of B is 3:7...

    Text Solution

    |

  13. A and B can do a piece of work in 6 days and 8 days, respectively. Wit...

    Text Solution

    |

  14. A certain number of persons can complete a work in 34 days working 9 h...

    Text Solution

    |

  15. 4 men and 5 women can complete a work in 15 days, whereas 9 men and 6 ...

    Text Solution

    |

  16. To do a certain work, the ratio of the efficiencies of X and Y is 5:4....

    Text Solution

    |

  17. A can do 40% of a work in 12 days, whereas B can do 60% of the same wo...

    Text Solution

    |

  18. A is as efficient as B and C together. Working together A and B can co...

    Text Solution

    |

  19. A can do one-third of a work in 15 days, B can do 75% of the same work...

    Text Solution

    |

  20. 25 persons can complete a work in 60 days. They started the work. 10 p...

    Text Solution

    |