The ratio of efficiencies of A , B and C...

The ratio of efficiencies of A , B and C is 7 : 5 : 8. Working together, they can complete a piece of work in 42 days. B and C worked together for 21 days and the remaining was completed by A alone. The whole work was completed in :
A, B और C की कार्य क्षमता का अनुपात 7 : 5 : 8 है | एक साथ कार्य करते हुए, वे किसी कार्य को 42 दिनों में कर सकते हैं |B और C ने एक साथ 21 दिनों तक कार्य किया और शेष कार्य A ने पूरा किया | पूरा कार्य कितने दिनों में समाप्त हुआ ?

A

96

B

99

C

102

D

93

Text Solution

AI Generated Solution

Promotional Banner

Topper's Solved these Questions

Similar Questions

Explore conceptually related problems

The ratio of efficiencies of A , B and C is 3 : 5 : 1. Working together, they can complete a piece of work in 5 days. A and B worked together for 3 days. The remaining will be completed by C alone in : A, B और C की कार्य क्षमता का अनुपात 3 : 5 : 1 है | एक साथ कार्य करते हुए, वे किसी कार्य को 5 दिनों में पूरा कर सकते हैं |A और B ने एक साथ 3 दिनों तक कार्य किया | C को अकेले शेष कार्य करने में कितना समय (दिन) लगेगा ?

The ratio of the efficiencies of A, B and C to do a certain work is 7:3: 5. Working together, they can complete work in 21 days. A and C worked together for 15 days. The remaining work will be completed by B alone in: A, B और C की कार्य क्षमता का अनुपात 7 : 3 : 5 है | एक साथ कार्य करते हुए, वे किसी कार्य को 21 दिनों में पूरा कर सकते हैं | A और C ने एक साथ 15 दिनों तक कार्य किया | शेष कार्य पूरा करने में B को अकेले कितने दिन लगेंगे ?

The efficiencies of A, B and C are in the ratio 5: 3: 8. Working together they can complete a work in 30 days. A and B worked together for 20 days. The remaining work will be completed by C alone in:

To do a certain work, the ratio of the efficiencies of A , B and C is 7 : 5 : 6. Working together, they can complete the same work in 35 days. B and C worked together for 21 days. The remaining work will be completed by A alone in : एक निश्चित कार्य को करने के लिए,A, B और C की कार्य क्षमता का अनुपात 7 : 5: 6 है| एक साथ कार्य करते हुए, वे इसी कार्य को 35 दिनों में पूरा कर सकते हैं | B और C ने 21 दिनों तक कार्य किया | शेष कार्य पूरा करने में A को अकेले कितने दिन लगेंगे ?

PINNACLE-WORK AND TIME-EXERCISE
  1. 6 men or 5 women earn Rs 14,820 in two days. How much will 4 women and...

    Text Solution

    |

  2. A can do a work in 20 days, while B can do the same work in 25 days. T...

    Text Solution

    |

  3. The ratio of efficiencies of A , B and C is 7 : 5 : 8. Working togethe...

    Text Solution

    |

  4. A can do 40% of a work in 6 days and B can do 30% of the same work in ...

    Text Solution

    |

  5. To do a certain work, the ratio of efficiency of A to that of B is 3:7...

    Text Solution

    |

  6. A and B can do a piece of work in 6 days and 8 days, respectively. Wit...

    Text Solution

    |

  7. A certain number of persons can complete a work in 34 days working 9 h...

    Text Solution

    |

  8. 4 men and 5 women can complete a work in 15 days, whereas 9 men and 6 ...

    Text Solution

    |

  9. To do a certain work, the ratio of the efficiencies of X and Y is 5:4....

    Text Solution

    |

  10. A can do 40% of a work in 12 days, whereas B can do 60% of the same wo...

    Text Solution

    |

  11. A is as efficient as B and C together. Working together A and B can co...

    Text Solution

    |

  12. A can do one-third of a work in 15 days, B can do 75% of the same work...

    Text Solution

    |

  13. 25 persons can complete a work in 60 days. They started the work. 10 p...

    Text Solution

    |

  14. The ratio of the efficiencies of A, B and C is 4 : 5 : 3. Working toge...

    Text Solution

    |

  15. The ratio of the efficiencies of A, B and C is 7:5:4. Working together...

    Text Solution

    |

  16. The efficiences of A , B and C are in ratio 5 : 3 : 8. Working togethe...

    Text Solution

    |

  17. To do a certain work, the ratio of the efficiencies of A , B and C is ...

    Text Solution

    |

  18. The ratio of efficiencies of A , B and C is 3 : 5 : 1. Working togethe...

    Text Solution

    |

  19. The ratio of the efficiencies of A, B and C to do a certain work is 7:...

    Text Solution

    |

  20. A is 40% more efficient than B and C is 20% less efficient than B. Wor...

    Text Solution

    |