A can do 40% of a work in 6 days and B c...

A can do 40% of a work in 6 days and B can do 30% of the same work in 3 days. They started the work together but B left after 2 days and A continued to work. In how many days was the entire work completed ?
A किसी कार्य का 40% भाग 6 दिनों में तथा B इसी कार्य का 30% भाग 3 दिनों में पूरा कर सकता है | उन्होंने एक साथ कार्य शुरू किया लेकिन 2 दिनों के बाद B हट गया और A ने कार्य जारी रखा | पूरा कार्य कितने दिनों में समाप्त हुआ ?

A

10

B

12

C

9

D

15

Text Solution

AI Generated Solution

Promotional Banner

Topper's Solved these Questions

PINNACLE-WORK AND TIME-EXERCISE
  1. A can do a work in 20 days, while B can do the same work in 25 days. T...

    Text Solution

    |

  2. The ratio of efficiencies of A , B and C is 7 : 5 : 8. Working togethe...

    Text Solution

    |

  3. A can do 40% of a work in 6 days and B can do 30% of the same work in ...

    Text Solution

    |

  4. To do a certain work, the ratio of efficiency of A to that of B is 3:7...

    Text Solution

    |

  5. A and B can do a piece of work in 6 days and 8 days, respectively. Wit...

    Text Solution

    |

  6. A certain number of persons can complete a work in 34 days working 9 h...

    Text Solution

    |

  7. 4 men and 5 women can complete a work in 15 days, whereas 9 men and 6 ...

    Text Solution

    |

  8. To do a certain work, the ratio of the efficiencies of X and Y is 5:4....

    Text Solution

    |

  9. A can do 40% of a work in 12 days, whereas B can do 60% of the same wo...

    Text Solution

    |

  10. A is as efficient as B and C together. Working together A and B can co...

    Text Solution

    |

  11. A can do one-third of a work in 15 days, B can do 75% of the same work...

    Text Solution

    |

  12. 25 persons can complete a work in 60 days. They started the work. 10 p...

    Text Solution

    |

  13. The ratio of the efficiencies of A, B and C is 4 : 5 : 3. Working toge...

    Text Solution

    |

  14. The ratio of the efficiencies of A, B and C is 7:5:4. Working together...

    Text Solution

    |

  15. The efficiences of A , B and C are in ratio 5 : 3 : 8. Working togethe...

    Text Solution

    |

  16. To do a certain work, the ratio of the efficiencies of A , B and C is ...

    Text Solution

    |

  17. The ratio of efficiencies of A , B and C is 3 : 5 : 1. Working togethe...

    Text Solution

    |

  18. The ratio of the efficiencies of A, B and C to do a certain work is 7:...

    Text Solution

    |

  19. A is 40% more efficient than B and C is 20% less efficient than B. Wor...

    Text Solution

    |

  20. A is 40% more efficient than B and C is 20% less efficient than B. Wor...

    Text Solution

    |