A can do 40% of a work in 12 days, where...

A can do 40% of a work in 12 days, whereas B can do 60% of the same work in 15 days. Both work together for 10 days. C completes the remaining work alone in 4 days. A, B and C together will complete 28% of the same work in :
A किसी कार्य का 40% भाग 12 दिनों में कर सकता है जबकि B इसी कार्य का 60% भाग 15 दिनों में कर सकता है |दोनों 10 दिनों तक एक साथ कार्य करते हैं | C शेष कार्य 4 दिनों में पूरा करता है | A, B और C एक साथ इसी कार्य का 28% भाग कितने दिनों में पूरा करेंगे ?

A

`2 1/2` days

B

3 days

C

`1 1/2` days

D

2 days

Text Solution

AI Generated Solution

Promotional Banner

Topper's Solved these Questions

PINNACLE-WORK AND TIME-EXERCISE
  1. 4 men and 5 women can complete a work in 15 days, whereas 9 men and 6 ...

    Text Solution

    |

  2. To do a certain work, the ratio of the efficiencies of X and Y is 5:4....

    Text Solution

    |

  3. A can do 40% of a work in 12 days, whereas B can do 60% of the same wo...

    Text Solution

    |

  4. A is as efficient as B and C together. Working together A and B can co...

    Text Solution

    |

  5. A can do one-third of a work in 15 days, B can do 75% of the same work...

    Text Solution

    |

  6. 25 persons can complete a work in 60 days. They started the work. 10 p...

    Text Solution

    |

  7. The ratio of the efficiencies of A, B and C is 4 : 5 : 3. Working toge...

    Text Solution

    |

  8. The ratio of the efficiencies of A, B and C is 7:5:4. Working together...

    Text Solution

    |

  9. The efficiences of A , B and C are in ratio 5 : 3 : 8. Working togethe...

    Text Solution

    |

  10. To do a certain work, the ratio of the efficiencies of A , B and C is ...

    Text Solution

    |

  11. The ratio of efficiencies of A , B and C is 3 : 5 : 1. Working togethe...

    Text Solution

    |

  12. The ratio of the efficiencies of A, B and C to do a certain work is 7:...

    Text Solution

    |

  13. A is 40% more efficient than B and C is 20% less efficient than B. Wor...

    Text Solution

    |

  14. A is 40% more efficient than B and C is 20% less efficient than B. Wor...

    Text Solution

    |

  15. A is 50% more efficient than B and C is 40% less efficient than B. Wor...

    Text Solution

    |

  16. A is 50% more efficient than B and C is 40% less efficient than B. Wor...

    Text Solution

    |

  17. The efficiencies of A , B and C are 2 : 5 : 3. Working together, they ...

    Text Solution

    |

  18. The efficiencies of A, B and C are in the ratio 2:5:3. Working togethe...

    Text Solution

    |

  19. The efficiencies of A, B and C are in the ratio of 5:3:2. Working toge...

    Text Solution

    |

  20. If 30 persons take 10 days to complete a certain work working 8 hours ...

    Text Solution

    |