To do a certain work, the ratio of the efficiencies of A , B and C is 7 : 5 : 6. Working together, they can complete the same work in 35 days. B and C worked together for 21 days. The remaining work will be completed by A alone in :
एक निश्चित कार्य को करने के लिए,A, B और C की कार्य क्षमता का अनुपात 7 : 5: 6 है| एक साथ कार्य करते हुए, वे इसी कार्य को 35 दिनों में पूरा कर सकते हैं | B और C ने 21 दिनों तक कार्य किया | शेष कार्य पूरा करने में A को अकेले कितने दिन लगेंगे ?

A

60 days

B

57 days

C

54 days

D

50 days

Text Solution

AI Generated Solution

Promotional Banner

Topper's Solved these Questions

PINNACLE-WORK AND TIME-EXERCISE
  1. The ratio of the efficiencies of A, B and C is 7:5:4. Working together...

    Text Solution

    |

  2. The efficiences of A , B and C are in ratio 5 : 3 : 8. Working togethe...

    Text Solution

    |

  3. To do a certain work, the ratio of the efficiencies of A , B and C is ...

    Text Solution

    |

  4. The ratio of efficiencies of A , B and C is 3 : 5 : 1. Working togethe...

    Text Solution

    |

  5. The ratio of the efficiencies of A, B and C to do a certain work is 7:...

    Text Solution

    |

  6. A is 40% more efficient than B and C is 20% less efficient than B. Wor...

    Text Solution

    |

  7. A is 40% more efficient than B and C is 20% less efficient than B. Wor...

    Text Solution

    |

  8. A is 50% more efficient than B and C is 40% less efficient than B. Wor...

    Text Solution

    |

  9. A is 50% more efficient than B and C is 40% less efficient than B. Wor...

    Text Solution

    |

  10. The efficiencies of A , B and C are 2 : 5 : 3. Working together, they ...

    Text Solution

    |

  11. The efficiencies of A, B and C are in the ratio 2:5:3. Working togethe...

    Text Solution

    |

  12. The efficiencies of A, B and C are in the ratio of 5:3:2. Working toge...

    Text Solution

    |

  13. If 30 persons take 10 days to complete a certain work working 8 hours ...

    Text Solution

    |

  14. A and B together can do a piece of work in 10 days, B and C together c...

    Text Solution

    |

  15. A, B and C can complete a piece of work in 10, 20 and 60 respectively....

    Text Solution

    |

  16. A, B and C can complete a piece of work in 4, 28 and 56 respectively. ...

    Text Solution

    |

  17. A, B and C can complete a piece of work in 5, 20 and 60 days respectiv...

    Text Solution

    |

  18. A, B and C can complete a piece of work in 4, 20 and 60 days respectiv...

    Text Solution

    |

  19. A, B and C can complete a piece of work in 4, 20 and 60 days respectiv...

    Text Solution

    |

  20. A and B can complete a piece of work in 15 days and 10 days respective...

    Text Solution

    |