16 persons working 6 hours a day can com...

16 persons working 6 hours a day can complete a work in 10 days. In how many days 24 persons working 8 hours a day will complete 80% of that work?
एक दिन में 6 घंटे कार्य करके 16 व्यक्ति किसी कार्य को 10 दिनों में समाप्त कर सकते हैं | एक दिन में 8 घंटे कार्य करके 24 व्यक्ति इस कार्य का 80% भाग कितने दिनों में समाप्त कर सकते हैं ?

A

3

B

6

C

4

D

8

Text Solution

AI Generated Solution

Promotional Banner

Topper's Solved these Questions

PINNACLE-WORK AND TIME-EXERCISE
  1. 36 persons working 8 hours a day can do 3 units of work in 12 days. Ho...

    Text Solution

    |

  2. The efficiency of A, B and C are in the ratio 5:6:9 working together, ...

    Text Solution

    |

  3. 16 persons working 6 hours a day can complete a work in 10 days. In ho...

    Text Solution

    |

  4. The efficiencies of A,B and C are in the ratio 5 : 6 : 8, working toge...

    Text Solution

    |

  5. The efficiencies of A,B and C are in the ratio 4 : 5 : 6. Working toge...

    Text Solution

    |

  6. 24 persons working 8 hours a day can complete 2 units of a work in 10 ...

    Text Solution

    |

  7. 18 persons working 8 hours a day can complete 3 units of works in 10 d...

    Text Solution

    |

  8. The efficiencies of A, B and C are in the ratio 2 : 5 : 7 working toge...

    Text Solution

    |

  9. A can do a work in 12 days while B can do same work in 18 days. How lo...

    Text Solution

    |

  10. 3 men, 4 women and 6 children can complete a work in 7 days. A woman d...

    Text Solution

    |

  11. Three painters have to spend 6 hours a day for 12 days to finish a wor...

    Text Solution

    |

  12. A can do a work in 30 days, B can do the same work in 48 days. After w...

    Text Solution

    |

  13. If 15 men can do a piece of work in 14 days, how many men will be need...

    Text Solution

    |

  14. 21 typist can complete a task in 8 days. Then in how many days 15 typi...

    Text Solution

    |

  15. The efficiency of A is three times of B and efficiency of B is twice t...

    Text Solution

    |

  16. Both A and B working together can complete a task in 3 2/3 days. C and...

    Text Solution

    |

  17. A can do one fifth part of a task in 4 days, B can do one sixth part o...

    Text Solution

    |

  18. A earns Rs 40 per hour and works for 12 hours. B earns Rs 60 per hour ...

    Text Solution

    |

  19. Two teachers A and B can complete an academic work in 10 days and 15 d...

    Text Solution

    |

  20. A alone can do a piece of work in 30 days. B alone can do the same wor...

    Text Solution

    |