A, B and C can complete a piece of work ...

A, B and C can complete a piece of work in 36 days, 54 days and 108 days respectively. They started working together, but 9 days after the start of work, A quit working and B also stopped working 3 days before the work was completed. How many days did C work?
A, B और C, एक कार्य को क्रमशः 36 दिनों, 54 दिनों और 108 दिनों में पूरा कर सकते हैं | उन्होंने एक साथ कार्य करना शुरू किया, लेकिन कार्य शुरू होने के 9 दिनों के बाद A ने कार्य करना छोड़ दिया और कार्य पूरा होने के 3 दिन पहले B ने भी कार्य करना छोड़ दिया | C ने कितने दिन कार्य किया?

A

29

B

33

C

31

D

30

Text Solution

AI Generated Solution

Promotional Banner

Topper's Solved these Questions

Similar Questions

Explore conceptually related problems

A , B and C can do a piece of work in 24days,36 days and 108 days, respectively. They started the work together but A left 9 days after the start of the work and B left 3 days before the work was completed. For how many days did C work ?

A, B and C can finish a piece of work in 12 days, 15 days and 20 days respectively. They started working together. B left the work after working 3 days and C left the work 3 days before completion of the work. In how many days work will be finished?

A, B and C can complete a piece of work in 10, 20 and 60 days respectively. Working together they can complete the same work in how many days?

A, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?

PINNACLE-WORK AND TIME-EXERCISE
  1. A can do a piece of work in 15 days and B can do it in 22 1/2 days.The...

    Text Solution

    |

  2. A can do a piece of work in 30 days. He completed 40% of the work and ...

    Text Solution

    |

  3. A, B and C can complete a piece of work in 36 days, 54 days and 108 da...

    Text Solution

    |

  4. 6 men can repair a road in 14 hours. How many men will be required to ...

    Text Solution

    |

  5. A and B can complete a piece of work in 20 days and 30 days respective...

    Text Solution

    |

  6. Satyam and Shivam can do a piece of work in 10 days and 15 days respec...

    Text Solution

    |

  7. A, B and C can do a work in 12, 15 and 20 days respectively. In how ma...

    Text Solution

    |

  8. A can complete a work in 20 days and B in 22 1/2 days. They both work ...

    Text Solution

    |

  9. A can do 40% of a work in 12 days, whereas B can do 60% of the same wo...

    Text Solution

    |

  10. 36 men and 48 women can do a certain work in one day whereas 6 men and...

    Text Solution

    |

  11. A can complete one-third of a work in 5 days and B can do 2/5th of the...

    Text Solution

    |

  12. To do a certain work, the ratio of efficiencies of A and B is 3:7, wor...

    Text Solution

    |

  13. A and B can complete a certain work in 24 days and 42 days, respective...

    Text Solution

    |

  14. A and B have to do 13/15 part of a work together and B and C have to d...

    Text Solution

    |

  15. 12 buckets of water fill a tank when the capacity of each bucket is 13...

    Text Solution

    |

  16. Three pipes x, y, z leave three different chemicals A, B, C in a tank....

    Text Solution

    |

  17. A, B and C can individually complete a piece of work in 24 days, 15 da...

    Text Solution

    |

  18. A can complete a certain piece of work in 40 days. B is 25% more effic...

    Text Solution

    |

  19. A can finish work in 20 days and B can finish the same work in 25 days...

    Text Solution

    |

  20. A can complete a certain work in 30 days. B is 25% more efficient than...

    Text Solution

    |