A and B can complete a piece of work in ...

A and B can complete a piece of work in 20 days and 30 days respectively. A works full time while B works half of the time. In how many days the entire work will be completed?
A तथा B किसी कार्य को क्रमशः 20 दिनों तथा 30 दिनों में पूरा कर सकते हैं | A पूरे समय कार्य करता है जबकि B आधे समय कार्य करता है | पूरा कार्य कितने दिनों में समाप्त हो जाएगा?

A

9

B

15

C

12

D

10

Text Solution

AI Generated Solution

Promotional Banner

Topper's Solved these Questions

PINNACLE-WORK AND TIME-EXERCISE
  1. A, B and C can complete a piece of work in 36 days, 54 days and 108 da...

    Text Solution

    |

  2. 6 men can repair a road in 14 hours. How many men will be required to ...

    Text Solution

    |

  3. A and B can complete a piece of work in 20 days and 30 days respective...

    Text Solution

    |

  4. Satyam and Shivam can do a piece of work in 10 days and 15 days respec...

    Text Solution

    |

  5. A, B and C can do a work in 12, 15 and 20 days respectively. In how ma...

    Text Solution

    |

  6. A can complete a work in 20 days and B in 22 1/2 days. They both work ...

    Text Solution

    |

  7. A can do 40% of a work in 12 days, whereas B can do 60% of the same wo...

    Text Solution

    |

  8. 36 men and 48 women can do a certain work in one day whereas 6 men and...

    Text Solution

    |

  9. A can complete one-third of a work in 5 days and B can do 2/5th of the...

    Text Solution

    |

  10. To do a certain work, the ratio of efficiencies of A and B is 3:7, wor...

    Text Solution

    |

  11. A and B can complete a certain work in 24 days and 42 days, respective...

    Text Solution

    |

  12. A and B have to do 13/15 part of a work together and B and C have to d...

    Text Solution

    |

  13. 12 buckets of water fill a tank when the capacity of each bucket is 13...

    Text Solution

    |

  14. Three pipes x, y, z leave three different chemicals A, B, C in a tank....

    Text Solution

    |

  15. A, B and C can individually complete a piece of work in 24 days, 15 da...

    Text Solution

    |

  16. A can complete a certain piece of work in 40 days. B is 25% more effic...

    Text Solution

    |

  17. A can finish work in 20 days and B can finish the same work in 25 days...

    Text Solution

    |

  18. A can complete a certain work in 30 days. B is 25% more efficient than...

    Text Solution

    |

  19. A and B, working together can complete a work in d days. Working alone...

    Text Solution

    |

  20. Four men and 6 women can complete a certain piece of work in 5 days wh...

    Text Solution

    |