A can complete one-third of a work in 5 ...

A can complete one-third of a work in 5 days and B can do `2/5`th of the same work in 10 days. They work together for 6 days. The remaining work is completed by C in 18 days. C alone will do the same work in:
A एक काम का एक तिहाई 5 दिनों में पूरा कर सकता है और B उसी काम के `2/5` भाग को 10 दिनों में पूरा कर सकता है। वे 6 दिनों तक एक साथ काम करते हैं। शेष कार्य C द्वारा 18 दिनों में पूरा किया जाता है। अकेले C इस काम को कितने दिनों में पूरा करेगा ?

A

50

B

30

C

25

D

45

Text Solution

AI Generated Solution

Promotional Banner

Topper's Solved these Questions

Similar Questions

Explore conceptually related problems

A can complete one-third of a work in 10 days and B can do ""_(5)^(3) th of the same work in 24 days. They worked together for 10 days. The remaining work was completed by C alone in 15 days. In how many days can C alone do ""_(3)^(2) of the same work?

A can do a piece of work in 15 days and B can do it in 22 1/2 days.They worked together for 6 days and the remaining work was completed by C alone in 6 days. A, B and C together will do the same work in: A किसी कार्य को 15 दिनों में पूरा कर सकता है एवं B उसे दिनों में पूरा कर सकता है। उन्होंने 6 दिनों तक एक साथ काम किया और शेष कार्य 6 दिनों में अकेले C ने पूरा किया। A, B और C मिलकर इस कार्य को कितने दिन में पूरा कर देंगे?

A can do 2/5 of a work in 12 days while B can do 66^(2/3)% of the same work in 16 days. They work together for 10 days. B alone will complete the remaining work in

A can do 4/5 of a work in 20 days and B can do 3/4 of the same work in 15 days. They work together for 10 days. C alone completes the remaining work in 1 day. B and C together can complete 3/4 of the same work in:

A can complete a work in 20 days and B in 22 1/2 days. They both work together for 6 days and the remaining work is completed by C in 26 days. In how many days the work will be completed, if all the three work together? / किसी कार्य को A, 20 दिनों में पूरा कर सकता है और B उसे 22 1/2 दिनों में पूरा कर सकता है | वे दोनों मिलकर 6 दिनों तक एक साथ कार्य करते हैं और शेष कार्य को C द्वारा 26 दिनों में पूरा किया गया है | तीनों एक साथ मिलकर उसी कार्य को कितने दिनों में पूरा करेंगे?

A can do (1)/(3) of a work in 30 days. B can do (2)/(5) of the same work in 24 days. They worked together for 20 days. C completed the remaining work in 8 days. Working together A, B and C will complete the same work in:

A can complete some work in 35 days and B can complete the same work in 15 days. They worked together for 8 days, then B left the work. In how many days will A alone complete 60% of the remaining work? A किसी कार्य को 35 दिनों में पूरा कर सकता है और B उसी कार्य को 15 दिनों में पूरा कर सकता है। उन्होंने 8 दिनों तक एक साथ कार्य किया, फिर B ने कार्य छोड़ दिया। कितने दिनों में A शेष कार्य का 60% पूरा करेगा?

A can do 40% of a work in 12 days, whereas B can do 60% of the same work in 15 days. Both work together for 10 days. C completes the remaining work alone in 4 days. A, B and C together will complete 28% of the same work in : A किसी कार्य का 40% भाग 12 दिनों में कर सकता है जबकि B इसी कार्य का 60% भाग 15 दिनों में कर सकता है |दोनों 10 दिनों तक एक साथ कार्य करते हैं | C शेष कार्य 4 दिनों में पूरा करता है | A, B और C एक साथ इसी कार्य का 28% भाग कितने दिनों में पूरा करेंगे ?

A can do (2)/(5) of a work in 6 days and B can do (2)/(3) of the same work in 12 days. A and B worked together for 6 days. C alone completed the remaining work in 8 days. A and C, working together, will complete the same work in:

PINNACLE-WORK AND TIME-EXERCISE
  1. A can do 40% of a work in 12 days, whereas B can do 60% of the same wo...

    Text Solution

    |

  2. 36 men and 48 women can do a certain work in one day whereas 6 men and...

    Text Solution

    |

  3. A can complete one-third of a work in 5 days and B can do 2/5th of the...

    Text Solution

    |

  4. To do a certain work, the ratio of efficiencies of A and B is 3:7, wor...

    Text Solution

    |

  5. A and B can complete a certain work in 24 days and 42 days, respective...

    Text Solution

    |

  6. A and B have to do 13/15 part of a work together and B and C have to d...

    Text Solution

    |

  7. 12 buckets of water fill a tank when the capacity of each bucket is 13...

    Text Solution

    |

  8. Three pipes x, y, z leave three different chemicals A, B, C in a tank....

    Text Solution

    |

  9. A, B and C can individually complete a piece of work in 24 days, 15 da...

    Text Solution

    |

  10. A can complete a certain piece of work in 40 days. B is 25% more effic...

    Text Solution

    |

  11. A can finish work in 20 days and B can finish the same work in 25 days...

    Text Solution

    |

  12. A can complete a certain work in 30 days. B is 25% more efficient than...

    Text Solution

    |

  13. A and B, working together can complete a work in d days. Working alone...

    Text Solution

    |

  14. Four men and 6 women can complete a certain piece of work in 5 days wh...

    Text Solution

    |

  15. To complete a certain task, X is 40% more efficient than Y, and Z is 4...

    Text Solution

    |

  16. Sixteen men can finish a work in 8 days. Eight men and nine women work...

    Text Solution

    |

  17. A, B and C can individually complete a task in 24 days, 20 days and 18...

    Text Solution

    |

  18. Amit and Sunil together can complete a work in 9 days, Sunil and Dines...

    Text Solution

    |

  19. A, B and C can individually complete a task in 20 days, 16 days and 30...

    Text Solution

    |

  20. Ten men or twelve women can finish the same work in 10 days. If 5 men ...

    Text Solution

    |