To do a certain work, the ratio of effic...

To do a certain work, the ratio of efficiencies of A and B is 3:7, working together, they can complete a work in 14 days. B started the work and after working for 8 days, he left and A completed the remaining work. For how many days did A work?
एक निश्चित कार्य करने के लिए, A और B की क्षमता का अनुपात 3: 7 है, एक साथ काम करते हुए, वे 14 दिनों में इस काम पूरा कर सकते हैं। B ने काम शुरू किया और 8 दिनों तक काम करने के बाद, उसने छोड़ दिया और A ने शेष कार्य पूरा कर लिया। A ने कितने दिनों तक काम किया?

A

28

B

30

C

24

D

27

Text Solution

AI Generated Solution

Promotional Banner

Topper's Solved these Questions

PINNACLE-WORK AND TIME-EXERCISE
  1. 36 men and 48 women can do a certain work in one day whereas 6 men and...

    Text Solution

    |

  2. A can complete one-third of a work in 5 days and B can do 2/5th of the...

    Text Solution

    |

  3. To do a certain work, the ratio of efficiencies of A and B is 3:7, wor...

    Text Solution

    |

  4. A and B can complete a certain work in 24 days and 42 days, respective...

    Text Solution

    |

  5. A and B have to do 13/15 part of a work together and B and C have to d...

    Text Solution

    |

  6. 12 buckets of water fill a tank when the capacity of each bucket is 13...

    Text Solution

    |

  7. Three pipes x, y, z leave three different chemicals A, B, C in a tank....

    Text Solution

    |

  8. A, B and C can individually complete a piece of work in 24 days, 15 da...

    Text Solution

    |

  9. A can complete a certain piece of work in 40 days. B is 25% more effic...

    Text Solution

    |

  10. A can finish work in 20 days and B can finish the same work in 25 days...

    Text Solution

    |

  11. A can complete a certain work in 30 days. B is 25% more efficient than...

    Text Solution

    |

  12. A and B, working together can complete a work in d days. Working alone...

    Text Solution

    |

  13. Four men and 6 women can complete a certain piece of work in 5 days wh...

    Text Solution

    |

  14. To complete a certain task, X is 40% more efficient than Y, and Z is 4...

    Text Solution

    |

  15. Sixteen men can finish a work in 8 days. Eight men and nine women work...

    Text Solution

    |

  16. A, B and C can individually complete a task in 24 days, 20 days and 18...

    Text Solution

    |

  17. Amit and Sunil together can complete a work in 9 days, Sunil and Dines...

    Text Solution

    |

  18. A, B and C can individually complete a task in 20 days, 16 days and 30...

    Text Solution

    |

  19. Ten men or twelve women can finish the same work in 10 days. If 5 men ...

    Text Solution

    |

  20. If 18 men can cut a field in 35 days, then in how many days can 21 men...

    Text Solution

    |