A, B and C can individually complete a p...

A, B and C can individually complete a piece of work in 24 days, 15 days and 12 days respectively. B and C started the work and worked for 3 days and left. The number of days required by A alone to complete the remaining work is:
A, B और C अकेले-अकेले किसी कार्य को क्रमशः 24, 15 और 12 दिनों में पूरा कर सकते हैं |B और C ने कार्य करना शुरू किया तथा 3 दिनों तक कार्य करके छोड़ दिया| शेष कार्य अकेले पूरा करने में A को कितने दिन लगेंगे ?

A

`15 1/2`

B

18

C

`13 1/5`

D

11

Text Solution

AI Generated Solution

Promotional Banner

Topper's Solved these Questions

Similar Questions

Explore conceptually related problems

A, B and C can individually complete a task in 24 days, 16 days and 32 days respectively. If A and C started the work and worked for 6 days and left, then the number of days required by B to complete the remaining task is :

A, B and C can individually complete a task in 24 days, 16 days and 32 days respectively. If A and C start the work and worked for 6 days and left, then the number of days required by B to complete the remaining task is: A, B और C व्यक्तिगत रूप से किसी कार्य को क्रमशः 24, 16 और 32 दिनों में पूरा कर सकते हैं | यदि A और C ने कार्य शुरू किया तथा 6 दिनों तक कार्य करके छोड़ दिया, तो शेष कार्य पूरा करने में B को कितने दिन लगेंगे ?

A, B and C can individually complete a task in 24 days, 20 days and 18 days respectively. B and C start the task, and they work for 6 days and leave. The number of days required by A alone to finish the remaining task is: A, B और C अकेले कार्य करते हुए किसी कार्य को क्रमशः 24 दिन, 20 दिन तथा 18 दिनों में पूरा कर सकते हैं | B और C ने कार्य शुरू किया और उन्होंने 6 दिन कार्य करके छोड़ दिया | शेष कार्य अकेले पूरा करने में A को कितने दिन लगेंगे ?

A, B and C can individually complete a task in 20 days, 16 days and 30 days, respectively. If A and B started working on the task, and they worked for 4 days and left, then the number of days required by C to finish the remaining tasks is: A, B तथा C अकेले कार्य करते हुए किसी कार्य को क्रमशः 20, 16 तथा 30 दिनों में पूरा कर सकते हैं | यदि Aऔर B ने यह कार्य शुरू किया तथा उन्होंने 4 दिन कार्य करके छोड़ दिया , तो शेष कार्य पूरा करने में C को कितने दिन लगेंगे ?

A, b and C can alone complete a work in 10, 12 and 15 days respectively. A and C started the work and after working for 4 days, A left and B joined. In how many days the total work was completed ?

A, B and C, alone can do a piece of work in 9, 12 and 18 days respectively. They all started the work together, but A left after 3 days. In how many days, was the remaining work completed ? A, B और C अकेले किसी कार्य को क्रमशः 9, 12 और 18 दिनों में कर सकते हैं | उन सभी ने साथ कार्य शुरू किया, लेकिन 3 दिन के बाद A ने कार्य छोड़ दिया | शेष कार्य कितने दिनों में समाप्त हुआ ?

Working together A, B and C can complete a piece of work in 24 days. After working together for 4 days. C left the work. A and B completed the remaining work in 30 days. The number of days taken by C alone to complete the same work is:

PINNACLE-WORK AND TIME-EXERCISE
  1. 12 buckets of water fill a tank when the capacity of each bucket is 13...

    Text Solution

    |

  2. Three pipes x, y, z leave three different chemicals A, B, C in a tank....

    Text Solution

    |

  3. A, B and C can individually complete a piece of work in 24 days, 15 da...

    Text Solution

    |

  4. A can complete a certain piece of work in 40 days. B is 25% more effic...

    Text Solution

    |

  5. A can finish work in 20 days and B can finish the same work in 25 days...

    Text Solution

    |

  6. A can complete a certain work in 30 days. B is 25% more efficient than...

    Text Solution

    |

  7. A and B, working together can complete a work in d days. Working alone...

    Text Solution

    |

  8. Four men and 6 women can complete a certain piece of work in 5 days wh...

    Text Solution

    |

  9. To complete a certain task, X is 40% more efficient than Y, and Z is 4...

    Text Solution

    |

  10. Sixteen men can finish a work in 8 days. Eight men and nine women work...

    Text Solution

    |

  11. A, B and C can individually complete a task in 24 days, 20 days and 18...

    Text Solution

    |

  12. Amit and Sunil together can complete a work in 9 days, Sunil and Dines...

    Text Solution

    |

  13. A, B and C can individually complete a task in 20 days, 16 days and 30...

    Text Solution

    |

  14. Ten men or twelve women can finish the same work in 10 days. If 5 men ...

    Text Solution

    |

  15. If 18 men can cut a field in 35 days, then in how many days can 21 men...

    Text Solution

    |

  16. A can do a piece of work in 6 days. B can do it in 9 days. With the as...

    Text Solution

    |

  17. Ram and Shyam can complete a task in 6 2/3 days and 15 days respective...

    Text Solution

    |

  18. A, B and C can individually complete a task in 24 days, 16 days and 32...

    Text Solution

    |

  19. Eight persons can finish a work in 20 days. After 5 days they were req...

    Text Solution

    |

  20. 15 men can complete a task in 10 days. In how many days can 20 men com...

    Text Solution

    |