Amit and Sunil together can complete a w...

Amit and Sunil together can complete a work in 9 days, Sunil and Dinesh together can complete the same work in 12days, and Amit and Dinesh together can complete the same work in 18 days. In how many days will they complete the work if Amit, Sunil and Dinesh work together? /
अमित और सुनील एक साथ किसी कार्य को 9 दिनों में पूरा कर सकते हैं | सुनील तथा दिनेश एक साथ इस कार्य को 12 दिनों में पूरा कर सकते हैं तथा अमित और दिनेश इस कार्य को एक साथ 18 दिनों में पूरा कर सकते हैं | यदि अमित, सुनील तथा दिनेश एक साथ कार्य करें, तो वे इस कार्य को कितने दिनों में पूरा करेंगे ?

A

14 days

B

16 days

C

12 days

D

8 days

Text Solution

AI Generated Solution

Promotional Banner

Topper's Solved these Questions

Similar Questions

Explore conceptually related problems

A and C together can complete a work in 120 days, C and E together can complete the same work in 80 days and A and E together can complete the same work in 160 days. In how many days A, C and E together can complete the same work?

Anil, Dinesh and Deepak together can complete a work in 40 days. Anil and Dinesh together can complete the same work in 50 days. In how many days Deepak alone can complete the same work?

Both X and Y together can complete a work in 12 days and Y alone can complete the same work in 30 days. In how many days will X alone complete the work?

A alone can complete a work in 12 days and B alone can complete the same work in 24 days. In how many days can A and B together complete the same work?

A alone can complete a work in 6 days and B alone can complete the same work in 8 days. In how many days both A and B together can complete the same work?

Anil, Bhuvan and Chirag together can complete a work in 35 days. Anil and Chirag together can complete the same work in 60 days. In how many days Bhuvan alone can complete the same work?

PINNACLE-WORK AND TIME-EXERCISE
  1. Sixteen men can finish a work in 8 days. Eight men and nine women work...

    Text Solution

    |

  2. A, B and C can individually complete a task in 24 days, 20 days and 18...

    Text Solution

    |

  3. Amit and Sunil together can complete a work in 9 days, Sunil and Dines...

    Text Solution

    |

  4. A, B and C can individually complete a task in 20 days, 16 days and 30...

    Text Solution

    |

  5. Ten men or twelve women can finish the same work in 10 days. If 5 men ...

    Text Solution

    |

  6. If 18 men can cut a field in 35 days, then in how many days can 21 men...

    Text Solution

    |

  7. A can do a piece of work in 6 days. B can do it in 9 days. With the as...

    Text Solution

    |

  8. Ram and Shyam can complete a task in 6 2/3 days and 15 days respective...

    Text Solution

    |

  9. A, B and C can individually complete a task in 24 days, 16 days and 32...

    Text Solution

    |

  10. Eight persons can finish a work in 20 days. After 5 days they were req...

    Text Solution

    |

  11. 15 men can complete a task in 10 days. In how many days can 20 men com...

    Text Solution

    |

  12. 30 men working 8 hours per day can dig a pond in 16 days. By working h...

    Text Solution

    |

  13. Shyam can complete a task in 12 days by working 10 hours a day. How ma...

    Text Solution

    |

  14. 5 men and 8 women can complete a task in 34 days, whereas 4 men and 18...

    Text Solution

    |

  15. A can finish a piece of work in a certain number of days. B takes 45% ...

    Text Solution

    |

  16. Ramu works 4 times as fast as Somu. If Somu can complete a work in 20 ...

    Text Solution

    |

  17. A can do a work in 12 days and B can do the same work in 16 days. If t...

    Text Solution

    |

  18. How many men will be required to plough 50 acres of land in 10 days if...

    Text Solution

    |

  19. Raju can finish a piece of work in 20 days. He worked at it for 5 days...

    Text Solution

    |

  20. A and B separately can build a wall in 12 days and 16 days, respective...

    Text Solution

    |