A can do a piece of work in 6 days. B can do it in 9 days. With the assistance of C they completed the work in 3 days. In how many days can C alone do the work? /
A 6 दिनों में एक काम कर सकता है। B इसे 9 दिनों में कर सकता हैं। C की सहायता से उन्होंने 3 दिनों में काम पूरा कर लिया। तो C अकेले कितने दिनों में यह काम करेगा?

A

16

B

8

C

18

D

12

Text Solution

AI Generated Solution

Promotional Banner

Topper's Solved these Questions

PINNACLE-WORK AND TIME-EXERCISE
  1. Ten men or twelve women can finish the same work in 10 days. If 5 men ...

    Text Solution

    |

  2. If 18 men can cut a field in 35 days, then in how many days can 21 men...

    Text Solution

    |

  3. A can do a piece of work in 6 days. B can do it in 9 days. With the as...

    Text Solution

    |

  4. Ram and Shyam can complete a task in 6 2/3 days and 15 days respective...

    Text Solution

    |

  5. A, B and C can individually complete a task in 24 days, 16 days and 32...

    Text Solution

    |

  6. Eight persons can finish a work in 20 days. After 5 days they were req...

    Text Solution

    |

  7. 15 men can complete a task in 10 days. In how many days can 20 men com...

    Text Solution

    |

  8. 30 men working 8 hours per day can dig a pond in 16 days. By working h...

    Text Solution

    |

  9. Shyam can complete a task in 12 days by working 10 hours a day. How ma...

    Text Solution

    |

  10. 5 men and 8 women can complete a task in 34 days, whereas 4 men and 18...

    Text Solution

    |

  11. A can finish a piece of work in a certain number of days. B takes 45% ...

    Text Solution

    |

  12. Ramu works 4 times as fast as Somu. If Somu can complete a work in 20 ...

    Text Solution

    |

  13. A can do a work in 12 days and B can do the same work in 16 days. If t...

    Text Solution

    |

  14. How many men will be required to plough 50 acres of land in 10 days if...

    Text Solution

    |

  15. Raju can finish a piece of work in 20 days. He worked at it for 5 days...

    Text Solution

    |

  16. A and B separately can build a wall in 12 days and 16 days, respective...

    Text Solution

    |

  17. A can complete a task in 18 days while B can complete the same task in...

    Text Solution

    |

  18. Amir and Akbar can finish a task in 30 days and 15 days, respectively....

    Text Solution

    |

  19. A and B together can complete a piece of work in 15 days. B and C toge...

    Text Solution

    |

  20. Antony and Vikash together can complete a piece of work in 20 days and...

    Text Solution

    |